Professional Documents
Culture Documents
CODE Implications
A: For Review and Comments
B: Information or Reference
NAVIGATOR
OF
DAY DURATION
SATURDAY
MAR 2021
1. SAFETY 4. SCHEDULE
2. QUALITY 5. LOOK AHEAD
3. PROJECT STATUS 6. KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE GABON ROAD PROJECT LAYOUT
Building
B
Building
A
NAVIGATOR
WEEKLY UPDATE SAFETY STATISTICS
NCR ISSUED : 00
NAVIGATOR
WEEKLY UPDATE QUALITY STATISTICS
NCR ISSUED : 00
NCR OPEN : 00
NRC PAST WEEK : 00
OBSERVATION PAST WEEK :00
OBSERAVATION OPEN :00 QUALITY
OBSERVATION PAST WEEK :00
NAVIGATOR
WEEKLY UPDATE PROJECT STATUS
START
Monday SURVEY WORKS GEO TECHNICAL MOBILISATION
FINISH
Monday
22 % 22
STATUS
COMPLETION FOR
NTP FOR SEGMENT 4
PROJECT NTP FOR NTP FOR
CONSTRUCTION 22 FEB 2022
COMMENCEMENT CONSTRUCTION CONSTRUCTION
FOR SEGMENT 4 FOR SEGMENT 5 &6 FOR SEGMENT 1 &3
DATE- 22 JAN OVERALL PROJECT
22 MAR 2021 22 JUN 2021 22 SEP 2021
2021 COMPLETION DATE-
22 JUL 2022
NTP FOR
NTP FOR
DETAILED
DETAILED
DESIGN FOR
DESIGN FOR
SEGMENT 4,5 & 6
SEGMENT 1, 2 & 3
- 22 JAN 2021
22 APR 2021
2021 2022
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18
NAVIGATOR
WEEKLY UPDATE ROW MARKING AT PK 75+000 IS IN PROGRESS
STATUS
NAVIGATOR
RIVER SAND AND BORROW AREA SAMPLING IS
WEEKLY UPDATE
IN PROGRESS
STATUS
NAVIGATOR
WEEKLY UPDATE GSB LAYING IN CAMP AND TRANSFORMER CABIN
WORK IS IN PROGRESS
STATUS
NAVIGATOR
WEEKLY UPDATE 100MT WEIGHBRIDGE WORKS IS IN PROGRESS
STATUS
NAVIGATOR
WEEKLY UPDATE ENGINEER’S MESS SUBSTRUCTURE WORKS
ALMOST COMPLETED
STATUS
NAVIGATOR
WEEKLY UPDATE VEHICLE SANITIZATION & SAFETY PROTOCOL
FOLLOWS AT SITE
STATUS
NAVIGATOR
WEEKLY UPDATE KEY STAFF STATUS
STATUS
NAVIGATOR
WEEKLY UPDATE WORKMEN STATUS
SR.
MANPOWER UNIT MOBILISED
NO
1 NATIONAL WORKFORCE NOS 175
NAVIGATOR
WEEKLY UPDATE WEATHER REPORT
10-Mar-21 30 25 Rainfall ⛈
11-Mar-21 30 25 Sunny
12-Mar-21 29 25 Rainfall ⛈
13-Mar-21 31 25 Sunny
NAVIGATOR
WEEKLY UPDATE EXPATS MOBILISATION STATUS
SCHEDULE
NAVIGATOR
PLANT AND MACHINERY MOBILISATION STATUS
WEEKLY UPDATE
AND SCHEDULE
May-21
May-22
Aug-21
Sep-21
Nov-21
Dec-21
Mar-22
Jun-21
Jan-22
Feb-22
Jun-22
Apr-21
Oct-21
Apr-22
Jul-21
Jul-22
Description of Assets Cap. Plan. Avl.
Excavator 20/30T 9 4 6 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Crawler Bull Dozer D6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Motor Grader 120 k 5 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4
Soil Compactors 10T 6 2 5 6 6 6 6 6 6 6 6 6 6 6 6 5 5 4
Tractor Dozer 75 HP 4 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Dumpers 25/40T 66 18 58 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66
Wheel Loader 2.1 Cum 7 3 3 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Backhoe Loader 0.3 Cum 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Water Tanker 10 KLit 8 0 1 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Trailer 50 TON 3 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
SCHEDULE
Generator 82.5 to 500 KVA 8 8 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Weigh Bridge 100 TON 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Concrete Batching Plant 30 cum/Hr 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Transit Mixer 6 Cum 10 0 1 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
HOT Mix Plant 260 / 160 TPH 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
9/10m
Asphalt Paver 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Width
Tandem Rollers 14T 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
PTR 24T 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Cement Bulker 30T 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Stone Crusher 250TPH 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 144 53 107 145 146 146 146 146 146 146 146 146 146 146 146 145 145 142
NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN
Location/ Completion
Activity Unit Scope Balance Mar'21 Apr'21
Facility %
Segment 4 Km 25 - 100%
Hydraulic Design
Segment 5 Km 20 20 0%
Report
Segment 6 Km 10 10 0%
LOOK AHEAD
Segment 4 Km 25 - 100%
Pavement
Segment 5 Km 20 20 0%
Design Report
Segment 6 Km 10 10 0%
NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN
Location/ Completion
Activity Unit Scope Balance Mar'21 Apr'21
Facility %
Batching Plant
No 100% 0% 100%
Installation
Internal Road
m 1612 931 42% 220 260 236 215
Works-Earthwork
Internal Road
Works-Laterite m 1612 1,402 13% 300 325 375 402
Boulder
Internal Road
m 1612 1,402 13% 300 325 375 402
Works-GSB
Afcons
Accomodation Nos 42 20 52% 10 10
Containers Shifting
NAVIGATOR
WEEKLY UPDATE KEY HIGHLIGHTS
KEY HIGHLIGHT :
Project Review Meeting held 10th March’ 21 at Prime Minister’s office, Libreville.
KEY HIGHLIGHTS
Pavement Design, Construction Programme, Quality formats & Method statement
submitted to employer for review.
NAVIGATOR
WEEKLY UPDATE SUPPORT REQUIRED
SUPPORT REQUIRED:
Facilitation for royalty exemption for the earth, laterite and sand being
project of national importance as per taxation rules of Gabon and
precedence of earlier projects executed in Gabon.
NAVIGATOR
www.afcons.com
NAVIGATOR