PROCUREMENT PLAN
FOR
EPC FOR CONSTRUCTING PIPE LINE AND POWER LINE
FOR SANGSAM OIL DEVELOPMENT
Status Code :
A = Issued for Review and Approval, B = Approved for Construction/Implementation, C = Issued for
As Built, I = Issued for Information, X = Document cancelled
Revision Status :
0 = original status,
1
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
CONTENT
2
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
3
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
4
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
2.5. Expediting
A formal process of Vendor expediting will be employed throughout the process. In the event that
problems are identified with the Vendor delivery of engineering data or fabrication progress,
engineering staff or inspection personnel will be dispatched to the Vendor office to develop a
corrective action plan. For key equipment and critical path equipment, independent inspectors will
provide expediting and inspection services periodically throughout the Vendor engineering and
fabrication process.
An expediting and tracking log will be maintained for all equipment items.
Responsibilities of the expediting staff include:
Development of the expediting plan
Participate in bid clarification meetings to ensure supplier understanding of jobsite delivery
requirements and confirmation of delivery commitment
Regular contact with Vendors to confirm status of the schedule.
Obtains milestone schedules and progress reports from Vendors.
Work with Vendors to develop a recovery plan in case problems with the delivery schedule
are determined
Provide input to the overall project schedule so that the Project Manager can determine the
impact of procurement milestones on the overall schedule. Inform project team of potential
Vendor problems.
Maintains expediting records.
Coordinate shipping with the transportation group.
5
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
6
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
3.1. General
KBP will assign a procurement coordinator for this project and the assigned procurement coordinator
will prepare more detail procurement plan to ensure all procurement activities during project
execution are well planned. The procurement plan prepared shall also include the coordination work
with the head office procurement team since procurement activities for specification development,
technical review, expediting, Inspection & testing and Shipping & Clearance will be handled by Head
Office procurement team. By the assistance of the head office team, the procurement coordinator
could work out to support the project execution.
The basic understanding of KBP for the procurement work is overall scope of work defined by CPI as
shown in the following matrix:
3.5. Expediting
KBP realize that expediting is one of a factor to succeed the procurement works, the expediting
activities to be performed for the project is expediting vendor’s documents such as engineering
documents and forwarded to COMPANY for review or approval, expedite the status of review and
7
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001
approval drawing and others related documents in order to get the vendors starting the fabrication
works, supervision, inspection in the vendors workshop, factory acceptance test, shipment
preparation until the material hand over in the job site and also the inspect the shipment for the non-
engineered material or ex-stock material.
Expediting activities will be handled by an expeditor for the purposes of the surveying and anticipate
any problem happened during the material preparation or fabrication process which potential to
make delay for the fabrication works it self and also delay in the shipment. In case of any potential
problem happened, the expeditor has to act promptly to look for the proper corrective action and
coordinate with related function.
The duties of an expeditor for shall be at least below;
Responsibilities of the expediting staff include:
Development of the expediting plan
Participate in bid clarification meetings to ensure supplier understanding of jobsite delivery
requirements and confirmation of delivery commitment
Regular contact with Vendors to confirm status of the schedule.
Obtains milestone schedules and progress reports from Vendors.
Work with Vendors to develop a recovery plan in case problems with the delivery schedule
are determined
Studied and understand the material specification and understand the term and
condition as mention in the purchase order.
Provide input to the overall project schedule so that the Project Manager can determine the
impact of procurement milestones on the overall schedule. Inform project team of potential
Vendor problems.
Maintains expediting records.
Coordinate with QC inspector to meet quality requirement
Coordinate shipping with the transportation group.
Expediting activities are organized based on the level of priority, such as critical path for delivery and
the level of tight or un-tight supervision/ inspection required.
8
CONSTRUCTION EXECUTION DOCUMENT NUMBER
PLAN (CEP) KBP – CEP - PROC – 001