QUALITY REQUIREMENT

INDEX
1.0 OBJECTIVE

2.0 SCOPE

3.0 ORGANISATIONAL DESCRIPTION

4 .0 CONTRACTORS QUALITY SYSTEM: TENDER STAGE

4.1 QUALITY RELATED


4.2 QGPC EVALUATION

5.0 CONTRACT AWARD: DOCUMENTS REQUIRED

5.1 REQUIREMENTS
5.2 GENERAL SECTION
5.3 ORGANISATION
5.4 RESPONSIBILITY
5.5 TECHNICAL AND QUALITY AUDITS
5.6 NON COMPLIANCE REPORTING/CORRECTIVE ACTION

6.0 DESIGN AND ENGINEERING CONTROL

6.1 PRINCIPAL REQUIREMENTS

7.0 DOCUMENT CONTROL

7.1 BASIC REQUIREMENTS


7.2 ESSENTIAL PROJECT DOCUMENTATION

8.0 PROCUREMENT CONTROL

8.1 BASIC REQUIREMENTS


8.2 REQUISITIONING
8.3 QUALIFICATION OF SUB CONTRACTORS
8.4 BID EVALUATION
8.5 QUALITY CONTROL AT CONTRACTORS & SUB CONTRACTORS
WORKS

9.0 GENERAL INSPECTION REQUIREMENTS

9.1 BASIC REQUIREMENTS

DOC. NO.: QSP-QAC-09 Page 2 of 39


QUALITY REQUIREMENT

9.2 APPOINTMENT OF THIRD PARTIES


9.3 QGPC APPOINTED CERTIFICATION AUTHORITY/THIRD
PARTIES

10.0 PRESERVATION PACKING & STORAGE

10.1 SHORT AND LONG TERM STORAGE

11.0 CONSTRUCTION AND MECHANICAL COMPLETION

11.1 DATA REPORTS


11.2 COMMISSIONING AND HAND OVER
11.3 OPERATION AND MAINTENANCE INSTRUCTIONS

12.0 APPENDIXES
APPENDIX 01 ISO 9000 Self Assessment Proforma
APPENDIX 02 Criticality Rating Proforma (examples)
APPENDIX 03 Matrix of Essential Project Documentation (examples)
APPENDIX 04 Sample Mechanical Completion Proforma (examples)

DOC. NO.: QSP-QAC-09 Page 3 of 39


QUALITY REQUIREMENT

1.0 OBJECTIVE

This document states the Quality requirements for CONTRACTORS engaged in


providing goods and services to QGPC on Projects and related work activity. The
custodian of this document is QAC which is a division within the QGPC Quality
Assurance Department. Queries concerning the interpretation or use of this document
should be directed to the appropriate Project Manager .

2.0 SCOPE

The requirements of this document applies to STC, LTC and GTC contracts, covering
the FEED and EPIC phases of Projects executed to enhance or exploit the recovery of
oil and gas reserves, or their derivatives. CONTRACTORS employed by QGPC to
provide Project goods and services shall therefore address the issue of: the “Quality of
the goods and services provided,” which shall be appropriate to their scope of supply
and the requirements of the particular Project Phase.
The following Table 01 demonstrates the expected application of this documents
requirements, additionally if considered appropriate particular areas of the document
can be applied to Service Orders or Plant Changes.

Table 01
LTC GTC STC Plant Changes
QSP-QC-009 A A E E

A = Application of this document


E = Evaluate particular section if required. Consult QAC for advice

3.0 ORGANISATIONAL DESCRIPTION

Projects are executed through the combined effort of QGPC and CONTRACTORS
Project Management Teams. As each CONTRACTOR is responsible for the Quality
of the products and services provided under its Contractual Terms, a description of
how these Quality requirements will be achieved for each Project Stage: i.e. TENDER,
FEED, EPIC, shall be clearly specified in the CONTRACTORS submission as
specified here. Post Tender stage and subsequent contract award will require a detailed
schedule of precise requirements which are also laid out in this document.

To aid clarity an organisational chart showing a typical QGPC-CONTRACTOR


organisation and the various interfaces of the Quality groups is displayed in Fig 01.
This is followed by a description of the Quality requirement relative to a typical
Project Activity sequence.

DOC. NO.: QSP-QAC-09 Page 4 of 39


QUALITY REQUIREMENT

Fig 01: A Typical Project Organisation showing Authoritative & Functional


Reporting
Typical QGPC Project Organisation

QGPC
PROJECT MANAGER

Operations Engineering Construction Lead QAC


Advisor Support Engineer Engineer

Planning QAC Appointed


Engineer Project Engineer

QAC Inspection
Staff as Required

Interface

Contractor Project Manager

Project Engineer

Engineering Cost Engineer Construction QA-QC Manager-Engineer

Certification Piping-Welding
Planning Authority Inspectors

Mechanical/
Lifetime
Rotating
Records
Equipment

Coatings Electrical/
Inspector Instruments

Interface

Specialist Sub- Specialist Sub-Contractors:


Contractor NDE-Coatings -PWHT-Civil-Supplier-Vendor
Reps.

Typical Project Organigram Showing:


Authoritative( ) and Functional Reporting ( )

Note: Chart is for illustration only.

4.0 CONTRACTORS QUALITY SYSTEM: TENDER STAGE

4.1 QUALITY RELATED DOCUMENTS REQUIRED

To enable QGPC to evaluate bids at the Tender stage, Tenderers shall submit, with
their Tender Documents, a general or corporate Quality Programme based on its
proposed application to the Tendered scope of work in conjunction with Tender
Conditions e.g. Appendix G of the standard conditions of Tenders. These data shall
include:

• an organigram of the proposed CONTRACTOR’S Project Management Team (C-


PMT) showing authoritative and functional reporting of personnel responsible for
Quality Activities,
DOC. NO.: QSP-QAC-09 Page 5 of 39
QUALITY REQUIREMENT

• cv’s of the proposed staff that will be used on the Project,


• a list of proposed SUB-CONTRACTORS and their intended activity,
• a typical Project Quality Plan as used on similar projects,
• confirmation of Certification or working in compliance with an International
Quality Standard. e.g. an appropriate model of the ISO 9000 series: (9001 Design,
9002 Manufacture etc.), Appendix 01 contains a CONTRACTORS self
assessment form based on ISO 9001 (1994) which shall be completed,
• If Certified or in compliance with another scheme please state separately,
• a list of applicable specialist procedures which will be used to control the tendered
Work which are appropriate to the CONTRACTORS business process.

4.2 QGPC QUALITY EVALUATION

These data will be evaluated by QGPC Quality Assurance Department against the
requirement of this document and the appropriate Project Specifications, looking
specifically at:

• previous experience with the CONTRACTOR,


• Quality System approval or compliance with an International Standard,
• specific Tender requirements.

The results of these evaluations shall be communicated to the appropriate QGPC


Project Management Team (PMT) for appraisal, and ultimate feedback to the
Tenderers.

5.0 CONTRACT AWARD: QUALITY DOCUMENTS REQUIRED

5.1 REQUIREMENTS

Within two months of Contract award, CONTRACTOR shall submit to QGPC a


detailed and dedicated Project Quality Plan, which describes the specific practices,
procedures and resources to implement the Project Activities as laid down in this
document, in an effective, and auditable manner. A schedule of development of
applicable areas of the Project Quality Plan, e.g. (procedures) can be supplied where
the workscope requirements dictate. The Project Quality Plan shall contain but not be
limited to the following requirements:

5.2 GENERAL SECTION

The section shall contain as a minimum information of the following nature:

• an index of contents,
• the distribution list of the Project Quality Plan,
• the method of revision and approval of the Project Quality Plan,
• a statement defining the authority of the CONTRACTORS personnel and the
application of the Project Quality Plan in the CONTRACTORS Organisation,
DOC. NO.: QSP-QAC-09 Page 6 of 39
QUALITY REQUIREMENT

• a schedule of progressive development in particular workscope areas and specialist


procedural controls not yet required,

5.3 ORGANISATION

This section shall contain a detailed description of CONTRACTOR’S organisation


relevant to the Project workscope which should include:

• an organigram of the CONTRACTORS Project Management Team,


• interfaces with QGPC, Third Parties etc.,
• cv’s of the proposed staff that will be used on the Project showing: qualifications,
training and experience relevant to the proposed appointment,
• job descriptions showing authority and responsibilities,
• authoritative and functional reporting relationships,

A CONTRACTORS Quality Representative, reporting to senior management shall


be appointed, who will have the necessary authority for ensuring that the Project
Quality requirements are implemented and maintained. A schedule of appointments
showing growth and reduction of Quality personnel shall be submitted by
CONTRACTOR to QGPC and updated throughout the Project in relation to
workload.

5.4 RESPONSIBILITY

A statement of the prime responsibility of CONTRACTOR personnel, assigned to


Quality tasks, e.g., to ensure that the agreed Project Policies, Procedures, Instructions
and the documented evidence thereof, are effectively and efficiently implemented.
That equipment, parts, and units are built in accordance with the relevant Contractual
Documents such as Codes, Standards, Specifications and Procedures and will perform
satisfactorily in service.

That CONTRACTORS quality personnel are given sufficient authority to implement


the Project Quality Plan and take corrective measures whenever necessary to maintain
a desired level of Quality. It must be emphasised that the authority of
CONTRACTORS Quality personnel shall not supplant or reduce the responsibility of
other departments concerning their contribution to the Project Quality requirements.

5.5 TECHNICAL AND QUALITY AUDITS

This section shall describe CONTRACTORS procedures for carrying out a systematic
investigation of both the implementation and effectiveness of the Project Quality Plan.
This shall be executed by a formal schedule of Internal/External Audits, covering each
discipline and worksite/SUB-CONTRACTOR (if appropriate), that will be performed
at regular intervals. Details of these Audit Program shall be included in this section.
Personnel authorised to conduct Audits shall have experience and training appropriate
to the area examined. CONTRACTOR should consider the use of “Audit Teams”
involving technical specialists to provide a more detailed evaluation of the issues or
DOC. NO.: QSP-QAC-09 Page 7 of 39
QUALITY REQUIREMENT

areas examined by the Audit. Copies of Audit Reports should be forwarded to QGPC
for evaluation and comment.

QGPC reserves the right to participate in CONTRACTORS/SUB-CONTRACTORS


Audits as an observer and therefore requires a minimum of five working days notice of
Audits to determine if this right will be exercised. QGPC also reserves the right to
initiate an unscheduled Audit of any CONTRACTOR/SUB-CONTRACTOR where
efficient functioning of their Project activity may be suspect.

5.6 NON COMPLIANCE REPORTING/CORRECTIVE ACTION

CONTRACTOR shall generate a procedure to be followed in the event that a Non-


Compliance is observed either during an Audit, site surveillance, or other activity. The
procedure for Corrective Action shall ensure that the organisation and functions
responds to the corrective action in a quick and efficient manner, thus emphasising the
organisational commitment to the Project Quality Plan Requirements. Details of Non
Conformances shall be made available to QGPC. Corrective Action by
CONTRACTOR shall include an evaluation of the following:

• commercial issues,
• technical considerations,
• schedule impact,
• raising of site or technical queries and change control issues.

6.0 DESIGN AND ENGINEERING CONTROL

6.1 PRINCIPAL REQUIREMENTS

CONTRACTOR shall describe the systems and procedures to be followed, including


the function of individuals (see section 5.3) responsible for ensuring that the design
engineering activity and applicable documents are:

• planned, reviewed and commented upon,


• executed distributed and released in a systematic and controlled manner at the
proper levels of authority,
• evaluated and contain defined responsibilities and interface functions, between
design engineering and the Quality department, in CONTRACTORS organisation
and externally with specialist SUB-CONTRACTORS Third Parties and QGPC.

During the design stage and subsequent Project phases if required, CONTRACTOR
shall initiate appropriate procedural controls over the following activity sequence:

• contract review including amendments,


• pre engineering: contracting strategy, bid system, estimates (percentage and
definitive), budget authorisation, identification of long lead items, Project
engineering manual,
• feasibility, conceptual and detailed studies as required,
DOC. NO.: QSP-QAC-09 Page 8 of 39
QUALITY REQUIREMENT

• planning the workscope at Level 1-4 as appropriate,


• work breakdown structure (WBS) as required,
• use of units and symbols,
• discipline, interdiscipline and multidiscipline checks,
• design reviews and verifications, including interim validation reports to QGPC if
required,
• use of computer software and hardware,
• basis of design documentation,
• calculations and alternative calculations,
• technical audits,
• technical library including: specifications, standards, codes, vendor data etc.
• technical and change control,
• production of specifications including amendments,
• production of drawings and material take-offs (MTO’s) including revisions,
• safety design assessments (SAFOPS),
• hazard design assessments (HAZOP),
• operability design assessment,
• constructability design assessment,
• maintainability design assessment,
• spares philosophy including manuals,
• criticality rating,
• identification of Project essential documentation, for lifetime quality records,
• the unique characteristics of individual plant item and their specific requirements
concerning packaging, preservation, storage and handling,
• quality audits as required by internal schedule or certification,
• interface management including QGPC, SUB-CONTRACTORS etc.,
• communications and document control,
• production of technical and commercial reports.

Note: The foregoing list can be developed into a table, with the precise contractual
requirements, shown as: required/not-required by contract etc. (similar to Table 2 for
example).

During the design stage CONTRACTOR shall provide a criticality award to each
plant item included in the design scope of work. This award shall be directly related to
the required inspection level for each applicable plant item. An example of a
Criticality Rating Scheme is provided in (Appendix 02) with the expected inspection
level appropriate to a given value of the scheme. CONTRACTOR can at its discretion
provide a criticality scheme, provided the same level of inspection data is available to
QGPC.

7.0 DOCUMENT CONTROL

7.1 BASIC REQUIREMENTS

DOC. NO.: QSP-QAC-09 Page 9 of 39


QUALITY REQUIREMENT

CONTRACTOR shall initiate procedural control of documentation at the necessary


level to satisfy QGPC that timely distribution of the required documents to Project
personnel takes place. The procedure shall specify as a minimum:

• a brief description of the scope and extent of the system,


• who is responsible for documentation control,
• how existing new/amended Project deliverables are identified and controlled,
• how documents are numbered,
• how transmission of documents is controlled,
• how internal distribution is controlled,
• how documentation interfaces work, e.g., QGPC, SUB-CONTRACTORS etc.,
• how checking, approval and amending documents etc., is controlled,
• how receipt, control, review and approval of SUB-CONTRACTORS documents is
controlled,
• control of lifetime quality records including: number of copies, sizes, electronic or
hard copy requirements etc.
• how confidentiality of documents is maintained.

During the various Project phases control of documentation shall be exercised at the
appropriate level by CONTRACTOR, e.g., some documents will require filing as
lifetime records, (see 7.2 below), and the following table defines a list of documents
that will require control on a day-to-day basis. For a precise list the actual Contract
details should be evaluated against the requirement of the Project.

Table 2: Typical Working Documentation Requiring Control


Controlled Documents Control
9= Yes x = No
Feed & Epic Deliverables
DOC. NO.: QSP-QAC-09 Page 10 of 39
QUALITY REQUIREMENT

Contract Documentation & Amendments


Technical-Site- Queries
Change Control
Agenda and minutes of meetings
Faxes-Letters-Memos as appropriate
Monthly reports & planning data
Material and equipment certification
Data sheets, requisitions, purchase orders, sub-orders etc.
Drawings and revisions
Equipment drawings
Vendor evaluation and survey reports
Agreed deviations
Clarifications and action items
Issue and follow-up of the Manufacturer’s Quality Plan
Fabrication, Inspection and Test Plans
Fabrication, Inspection and Test Schedules including “look
aheads”
Non-conformance reports
Notifications for meetings, inspections etc.
Welding, NDE, fabrication procedures and procedure
qualification records
Material substitution reports
Sub Contractors inspection and test status
Third party workscopes
Reports related to activities of third party inspection and test
agencies
Inspection acceptance and rejection reports
Qualifications and cv’s of Quality personnel
Audit reports
Corrective action reports
Procedures, work instructions etc.
Transmittals
Manufacturer’s reports

Note: Example only this is not a definitive list.

CONTRACTOR shall employ an efficient and retrievable information and data


storage, distribution and filing system in both hard copy and electronic form which
shall also provide for traceability of released documents and transmittals.

7.2 ESSENTIAL PROJECT DOCUMENTATION

CONTRACTOR shall also provide a matrix of Lifetime Quality Records classified as


Essential Project Documentation appropriate to the applicable scope of work, see
(Appendix 03). CONTRACTOR, in conjunction with QGPC, shall evaluate and
define the actual Project required documentation, identified as essential and
DOC. NO.: QSP-QAC-09 Page 11 of 39
QUALITY REQUIREMENT

appropriate to each project phase, i.e. FEED, EPIC, etc. It is a primary requirement
that the production of Essential Documentation is concurrent with CONTRACTORS
workscope throughout all Project stages/phases, e.g. Design, Procurement,
Construction, Commissioning and Hand-Over.

Note: If SUB-CONTRACTORS are used for different stage/phase of Project activity,


then Essential Documentation shall be indexed and handed over to QGPC in an agreed
format on completion of that stage/phase by the particular CONTRACTOR.

8.0 PROCUREMENT CONTROL

8.1 BASIC REQUIREMENTS

This section describes the controls to be taken to ensure that procurement policies,
procedures and instructions are effectively and systematically carried out. They will
achieve the specified technical and Quality Requirements with regard to the procured
items and meet the specific requirements of the Project Schedule.

8.2 REQUISITIONING

Procedural Control shall be exercised on documents that are prepared by


CONTRACTORS Design and Engineering Department for requisitioning of materials,
parts, equipment and units, considering the following:

• basic design data, (approval for construction issue)


• general and particular information on materials and equipment and the provision
for material substitution if found necessary at a later date,
• applicable Codes, Standards, Specifications and other special project requirements
including their revisions, and checking for anomalies, and their timely distribution
to all concerned,
• materials of constructions to be used, including clearly specified requirements on
material testing, certification and acceptance criteria,
• inspection and tests to be carried out detailing scope, extent and acceptance criteria
as indicated in the “Fabrication: Inspection and Test Plan” for the parts and
equipment,
• the unique characteristics of individual plant item and their specific requirements
concerning packaging, preservation, storage and handling,
• data and drawing requirements for SUBCONTRACTORS: including the
requirements for the content and compilation of manufacturing reports, data
books, records, etc.

8.3 QUALIFICATION OF SUB CONTRACTORS

CONTRACTOR shall place orders and suborders with suppliers, manufacturers and
stockists, contained in the preferred list of QGPC suppliers, for procurement and
manufacture of all equipment, parts and materials, including bulk and all special
DOC. NO.: QSP-QAC-09 Page 12 of 39
QUALITY REQUIREMENT

materials. CONTRACTOR shall ensure that the vendors selected from the QGPC
preferred list are currently capable of manufacturing the equipment, parts and
materials to the requirements of the Project considering the following issues:

• technical ability,
• commercial requirements,
• ability to supply,
• schedule requirements,
• evaluation of previous performance (if any),
• availability of spares,
• location of support services,
• ongoing improvements and innovations of Vendor’s activities,
• adaptability to QGPC’s testing system.

CONTRACTOR shall also verify against the Project Requirements and/or the
applicable ISO 9000 Quality Requirements, or equivalent specification, that the
Quality System currently in operation at the SUB CONTRACTORS works, for the
commodity to be purchased/ordered/fabricated is sufficient to ensure that it will be
acceptable and suitable for its intended use. The following salient features shall be
considered:

• size, type and number/quantity of equipment and materials,


• metallurgy and technology,
• knowledge and working experience with Project Codes and Specifications,
• organisational and manpower qualifications, experience and availability,
• resources for meeting Project Quality Requirements, describing any external
assistance required by the SUB-CONTRACTOR in the field of fabrication,
inspection and testing and/or additional manpower requirements,
• the type of management of the SUB-CONTRACTOR: their operations,
verification and documentation systems, procedure structure, organisation and
auditing system,
• housekeeping and material storage and handling.

CONTRACTOR is fully responsible for the completion, checking, implementation


and approval, of the SUBCONTRACTORS documentation including reports,
Essential Project Documents, and Quality Plans, etc.

8.4 BID EVALUATION

This section defines the measures applicable to the reception of bids by


CONTRACTOR. The following issues should be addressed:

• conformance of bids with the conditions and requirements of the bid invitation,
• deviation/exceptions stated by bidders to the bid invitation,

DOC. NO.: QSP-QAC-09 Page 13 of 39


QUALITY REQUIREMENT

• technical review of contents of bids and subsequent evaluation and


recommendation.

In particular the bids shall be checked and evaluated for:

• quality programme of SUB-CONTRACTOR,


• comprehension and compliance with applicable Codes, Standards, Specifications
and other special requirements, if any,
• evaluation of and control measures established by SUB-CONTRACTOR to
monitor his quality system and activities,
• procurement system and use of required materials of construction and their
appropriate certification and control,
• in-house inspection capabilities, including knowledge and experience of dealing
with Third Party inspection agencies,
• compliance with stipulated fabrication, testing, inspection and acceptance
requirements,
• preliminary Inspection and Test Planning including: specifying the extent of
involvement of QGPC, CONTRACTOR, stockists, SUB-CONTRACTORS and
Third Party inspection agencies at appropriate stages of fabrication/assembly,
• production of drawings and planned date of issue,
• identification of Essential Documents including As Builds,
• past experience of the SUB-CONTRACTORS on Projects of a similar nature and
scope.

The foregoing activities, checks, evaluations, reviews, shall be documented and


readily available for Auditing purposes at the discretion of QGPC.

8.5 QUALITY CONTROL AT CONTRACTORS & SUB


CONTRACTORS WORKS

CONTRACTOR shall state the controls and systems that will be implemented to
ensure that material, parts and equipment are in compliance with the precise Project
Requirements and Specifications. This section shall therefore, contain such essentials
as a detailed description of the Quality Control Organisation, indicating the number,
background and function of each individual, the lines and mode of reporting and
communication and the interface with personnel assigned to engineering tasks.
As works inspections form a major part of the overall Project Quality Control System
the inspection policy and procedures to be followed for the Project shall provide for:

• schedule of inspections and manpower allocation at SUB-CONTRACTOR’S


works,
• details of Quality Plans to be used for various categories of equipment and
materials,
• review and reports of SUB-CONTRACTOR’S QA/QC systems, procedures,
records of inspections and tests performed,
• format, language, contents, and frequency of inspection reporting,

DOC. NO.: QSP-QAC-09 Page 14 of 39


QUALITY REQUIREMENT

• procedures to be followed in case fabrication and inspection requirements have to


change due to design and engineering change,
• procedures to be followed in case modification, repairs (minor or major) or
replacements have to be carried out; re-inspected, tested and accepted, by all
parties concerned, when required or considered necessary by the QGPC Project
Manager,
• issue and handling of non-conformance and rejection reports,
• follow-up of outstanding inspection activities,
• participation at SUB-CONTRACTOR co-ordination meetings prior to placement
of purchase orders,
• works survey prior to SUB-CONTRACTOR qualification when necessary,
• scheduling, participation, and recording of meetings with the sub-contractors,
stockists etc.,
• notification to inspection parties involved for witnessing repairs, carrying out tests
and inspections due etc.,
• final inspection and release procedures.

9.0 GENERAL INSPECTION REQUIREMENTS

9.1 BASIC REQUIREMENTS

This section shall contain CONTRACTOR’S procedures for the execution of


inspection/tests, showing the acceptance/approval requirements for the equipment,
parts, materials or work, etc. The foregoing and following issues shall be addressed by
the CONTRACTOR, eg:

• inspection/tests/approvals and/or acceptance necessary to comply with local


statutory requirements in connection with the granting of permits to the
construction, installation and operation of the Project, as applicable,
• inspections/tests and approvals and/or acceptance necessary to ensure full
compliance with the Project Specification, good manufacturing practices and to
prove that all materials, parts, equipment and work are suitable for the duties they
are intended to perform,
• inspection/tests and approvals and/or acceptance required for insurance purposes
and for shipment/transportation purposes,

• the role of the CONTRACTOR’S appointed inspection organisation which shall be


completely independent of the Project Organisation, i.e., it shall report to the
CONTRACTORS Quality Representative, who in turn shall report to the Project
Engineer/Manager,
• the organisation scheme, personnel resumes, qualification records, certification of
inspectors and inspection procedure and programme which shall be evaluated by
CONTRACTOR and may be subject to review by QGPC at their discretion,

DOC. NO.: QSP-QAC-09 Page 15 of 39


QUALITY REQUIREMENT

• CONTRACTORS inspectors must be qualified and certified to an Internationally


Recognised agency/institute in accordance with established written requirements,
defining at least education, experience, training and knowledge of applicable codes
and language(s) etc.,
• where special expertise is required during inspection activities, CONTRACTORS
specialists discipline engineers will either assist the inspector or execute the
inspection/tests themselves,
• inspection personnel shall be made thoroughly familiar with any special Project
Requirements and the procedures and schedule for achieving this familiarisation
shall be detailed in this section.

9.2 APPOINTMENT OF THIRD PARTIES

This section shall contain CONTRACTORS procedures covering inspections of


equipment, material and work by Third Party inspection agencies/certification
authorities appointed by CONTRACTOR. It should be noted that although inspections
may be delegated to independent inspection agencies, CONTRACTOR remains at all
times, fully responsible for the inspection work performed by these Third Party
inspection agencies.

If CONTRACTOR engages the services of an independent (Third Party) inspection


agency, the following issues should be addressed:

• the Third Party inspection agency shall operate as an independent body and shall
not act as an employee of CONTRACTOR,
• the scope of inspection services by the independent Third Party agency shall be
governed by but not be limited to the verification requirements as stipulated in the
purchase order and its attachments and/or the requirements as detailed in the
Project Quality Plan,
• the scope of inspections, expected man-hours and the control of growth (extending
man-hours/scope) shall be approved/agreed by QGPC prior to contract award,
• QGPC may review/audit CONTRACTORS inspection arrangements and systems
taking into account the requirements noted here.

9.3 QGPC APPOINTED CERTIFICATION AUTHORITY/THIRD


PARTIES

This section shall contain the specific interfaces to be followed when QGPC
nominates their own representatives either from their own organisation, or hired from
an independent inspection agency on their behalf to monitor the quality inspection
activities of CONTRACTOR or SUB CONTRACTOR covering “selected items” in
particular or other equipment and materials in general.
DOC. NO.: QSP-QAC-09 Page 16 of 39
QUALITY REQUIREMENT

QGPC’S representation shall be totally independent of CONTRACTORS inspection


arrangement, and shall not relieve CONTRACTOR of any Contractual Obligation in
any respect.

QGPC reserves the right to visit or send their nominated representative to visit any
CONTRACTOR, SUB-CONTRACTOR etc., to inspect/witness tests, of materials and
equipment at any time or stage of fabrication and carry out audit and/or review of the
applicable Quality System.

These visits shall be co-ordinated by CONTRACTOR and will be made in the


presence of CONTRACTORS personnel. CONTRACTOR shall give notification to
concerned parties of any audit/review/visit and/or inspection due to be witnessed by
QGPC as per contractual arrangements or Quality Plan requirements.

CONTRACTORS and SUB-CONTRACTORS shall provide all the necessary


information, co-operation and access to documentation to the QGPC representative in
a prompt and timely manner, if requested in advance.

10.0 PRESERVATION PACKING & STORAGE

The section shall describe procedures and systems to ensure that the appropriate
preservation and packing instructions are issued in a timely manner. Are properly
controlled and understood in order to: safeguard materials and equipment against
corrosion and damage during transit and storage and that all markings used for
identification purposes are protected.

10.1 SHORT AND LONG TERM STORAGE

This section shall clearly state CONTRACTORS and SUB-CONTRACTORS short


and long term storage control measures and procedures for safeguarding materials and
equipment from damage; particularly, in the period between manufacturing and Ready
for Installation/Start-up at the job site. Spare parts storage shall be given special
attention where applicable. The following issues concerning packaging and
preservation should be addressed in CONTRACTORS procedure:

• the unique characteristics of individual plant item and their specific requirements
concerning packaging preservation storage and handling,
• handling and preservation during sea voyages including loading and unloading,
• outside storage and handling at remote desert locations,
• internal storage and handling at warehouse locations,
• lifting operations at remote locations,
• protecting/preserving part installed equipment,
• use of suitable materials for packaging and preservation,
• marking and identification,
• schedule of inspections of long term stored items including preservation,
• inspection of plant item to ensure removal of storage materials before installation,
DOC. NO.: QSP-QAC-09 Page 17 of 39
QUALITY REQUIREMENT

• special lifting requirements/equipment.

11.0 CONSTRUCTION AND MECHANICAL COMPLETION

Quality control shall be exercised at the job site throughout the construction phase,
covering all aspects of the workscope from receipt of materials and equipment, to final
inspection and CONTRACTOR/SUB-CONTRACTOR data reports. This section shall
also contain the procedures to ensure that construction and mechanical completion are
carried out in accordance with the Project Quality Requirements and shall include, but
not be limited to the following:

• construction inspection & test planning,


• construction procedures and work instructions,
• inspection, testing and acceptance procedures,
• generic and discipline inspection and test plans,
• specialist technical procedures: Welding, NDE, Hydrotesting, PWHT, Lifting etc.,
• interface control between: QGPC, CONTRACTOR, SUB-CONTRACTOR, etc.,
• documentation/records control,
• scheduling and planning sub contractor activity,
• receipt storage and issue of materials/equipment including spare part control,
• non-conformances,
• ongoing program of approvals/certification as appropriate,
• site-technical and change control,
• as-built documentation concurrency with manufacture, (Essential Project
Documents),
• mechanical completion procedures,
• raising/clearing and status of construction punchlists,
• pre-commission/commissioning/as built dossier,
• procedure for hand over to commissioning teams.

11.1 Data Reports

This section shall describe procedures to be followed in safeguarding the Quality


Control of the timely compilation, distribution, checking and approval of
documentation and reports. (Refer to Appendix 3 Essential Projects Documents
and Precise Contractual Requirements) The following guidelines and requirements
shall be incorporated into the relevant engineering documents plus the requirements of
QGPC Specifications and Contractual Requirements.

For equipment and materials, pressure vessels etc., the vendor data reports shall be in
accordance with the requirements as stipulated in the Contract/Purchase order.
Generally the contents of these reports shall reflect the material and fabrication history
of the equipment and provide sufficient information with respect to the integrity and
Quality of workmanship: including compliance with Purchase Order requirements.
They shall contain the following as a minimum:

DOC. NO.: QSP-QAC-09 Page 18 of 39


QUALITY REQUIREMENT

• general data to sufficiently identify and trace the equipment and its components,
• relevant material certificates for each part of the equipment, duly signed, stamped,
dated and accepted by the appropriate authorities,
• approved Welding Procedure Specifications and Procedure Qualification records,
• list of qualified welders and/or welding operators employed along with their
welder mark/number used for identification, and the name of the qualifying
authority and the date of qualification,
• for relevant equipment these welder identifications shall be shown on a weld map
indicating locations/joints they have welded,
• certificates of all non-destructive testing carried out with reference to test locations
on equipment,
• certificates of any heat treatment operation carried out, showing temperature
ranges, type of heating system and verification marking,
• report on all repairs carried out for relevant equipment, a sketch shall be included
showing the location(s) of the repair(s),
• list of agreed deviations regarding Design, Fabrication, Inspection and Testing,
adequately referenced for traceability,
• hydrostatic/pneumatic test reports,
• mechanical/performance test reports,
• electrical performance and acceptance test reports,
• instrumentation acceptance test reports,
• fire and gas panels acceptance test reports,
• HVAC test reports,
• proof-load test reports,
• report on final dimensions and extent of deviations, tolerances to be shown on the
report including inspection findings on flange facing etc.,
• as-built general assembly drawing,
• design release report issued by CONTRACTOR and/or (Third Party Inspection
/Certification Authority) where applicable,
• certificate of compliance to applicable codes issued by the appropriate authorities
if applicable,
• material test certificates,
• calibration certificates for PWHT chart recorders, Hydrotest gauges etc.,
• legible photograph or rubbing of nameplate or stampings.

Note: All documents handed over to QGPC shall firstly be accepted by


CONTRACTOR/S concerned. Documents not clearly legible or reproducible will not
be accepted. The acceptance of equipment may be withheld by QGPC, where reports
have not been presented for acceptance.

CONTRACTOR shall clearly instruct SUB-CONTRACTORS that data report shall be


compiled as production is progressing and is subject to review by CONTRACTOR
and QGPC at any stage during the manufacture of an item. CONTRACTOR shall also
ensure that at the time of their acceptance or witnessing of tests of any equipment,
parts, materials and units: that the SUB-CONTRACTORS data reports, are complete

DOC. NO.: QSP-QAC-09 Page 19 of 39


QUALITY REQUIREMENT

and presented to the CONTRACTOR and the Third Party inspection agency where
applicable for their acceptance.

11.2 COMMISSIONING AND HAND OVER

CONTRACTOR shall develop procedures for this Project Phase by evaluating the
requirements for commissioning and hand over as defined by Contract, see (Appendix
04 sample only: Mechanical Completion Sheets). These procedures shall be
developed taking into account the issues noted below and the precise terms and
conditions of the Contract including applicable specifications:

• evaluate punchlist and test documentation to determine status,


• clear outstanding items required for functional testing,
• carry out detailed functional testing on plant/equipment,
• raise additional punchlist/modification as required,
• complete finalise documentation,
• carry out additional testing as required,
• handover as determined by Contract,
• warranty spares ongoing servicing technical assistance determined as per Contract.

11.3 OPERATION AND MAINTENANCE INSTRUCTIONS

CONTRACTOR shall describe in a procedure the control receipt, checking and


submission of operating and maintenance instructions if applicable or required by
Contract. (Refer to Appendix 3 Essential Project Documentation).

DOC. NO.: QSP-QAC-09 Page 20 of 39


QUALITY REQUIREMENT

APPENDIX 1

SELF ASSESSMENT PROFORMA

Design Process Requirements

QGPC Specify Controls 9 = Control Required X = Control not Required


Required

Contract review including amendments,


Planning the workscope,
Use of units and symbols,
Discipline, interdiscipline and multidiscipline checks,
DOC. NO.: QSP-QAC-09 Page 21 of 39
QUALITY REQUIREMENT

Design reviews and verifications,


Use of computer software and hardware,
Basis of design documentation,
Calculations and alternative calculations,
Technical audits,
Technical library including: specifications, standards, codes,
vendor data etc
Technical and change control,
Production of specifications including amendments,
Production of drawings including revisions,
Safety design assessments (SAFOPS),
Hazard design assessments (HAZOP),
Operability design assessment,
Constructability design assessment,
Maintainability design assessment,
Criticality rating,
Identification of project essential documentation
Quality audits as required by internal schedule or certification,
Interface management including QGPC, SUB-CONTRACTORS
etc,
Communications and document control.

DOC. NO.: QSP-QAC-09 Page 22 of 39


QUALITY REQUIREMENT

APPENDIX 2

EXAMPLE OF A CRITICALITY RATING SCHEME

INTRODUCTION

Criticality Evaluation is a formalised technique for assessing the importance of an installation


or piece of equipment with respect to is design, manufacture/ construction and installation and
the consequences of failure during use.

The Criticality Evaluation can be used to control the allocation of quality resources by
minimising the over-specification, cross-checking, review and inspection on those items
which are judged to be less critical and increasing these activities on the critical items.

A typical model of a Criticality Evaluation is given overleaf. However this scheme is not
intended to be compulsory. Should the CONTRACTOR or SUB-CONTRACTOR already
DOC. NO.: QSP-QAC-09 Page 23 of 39
QUALITY REQUIREMENT

have an established system in place or wish to propose an alternative system, they can submit
the details to the Q.G.P.C Project Manager for evaluation .

EVALUATION GUIDELINES

Criticality Evaluations shall normally be determined at an assessment meeting attended by all


specialist technical staff concerned with the discipline or disciplines involved with the
installation or equipment. Points are awarded against a Criticality Category which are
weighed against the following items:

• Design Maturity - This considers the availability of established design information . What
percentage is already known and proven from tests or experience with similar equipment .
The commercial availability and the capabilities of PROSPECTIVE SUB-
CONTRACTORS should also be considered.
• Design complexity - The difficulty of completing the design, the number of man hours that
are needed, the amount of specialist input involved, how much interface there has to be
between disciplines and whether any literature surveys / research will be required, should
all be reviewed.
• Fluid characteristics - This is self explanatory.
• Safety - Both product and service safety need to be considered in terms of the probability
of failure occurring and the consequences of that failure. The safety impact of failure has to
be considered both for operating personnel and the public. This criterion will usually be
subject to separate SAFOP and HAZOP studies.
• Environmental Impact - Again self explanatory and again will usually be subject to
separate studies.
• Manufacturing Complexity - This considers the difficulty of manufacture, the number of
different and possibly specialised processes involved, the number and co ordination of
disciplines required and the verification of each stage during manufacture.
• Economics - This is tied in with safety and environmental considerations but specifically
addresses the difficulties that would be created and the loss of revenue that would occur in
the event of the plant or item of equipment being unavailable due to failure or unplanned
repairs.
• Construction / Installation - Considers the difficulty of installation of equipment including
any special lifting and movement requirements and the disruption to operations that would
be caused if there was a need to shut down existing processes to allow installation.
• The foregoing list is not comprehensive and is provided as an example. Once the
allocation of points is awarded then the Criticality Category can be chosen (see page 4 &
5).

NOTE: Various companies operate schemes based on Criticality Detailed guidelines are
available for most Institutions that issue Standards e.g. (CSA).

DOC. NO.: QSP-QAC-09 Page 24 of 39


QUALITY REQUIREMENT

DOC. NO.: QSP-QAC-09 Page 25 of 39


QUALITY REQUIREMENT

QGPC: PROJECT QUALITY REQUIREMENT

EQUIPMENT/SYSTEM DESCRIPTION (Identify precisely what is included):


Rate the following criteria (A to J) in accordance with one of the four listed numerical degrees of significance 1 to 4
ITEM CRITERIA POINTS EVALUATION
A DESIGN - PROCESS COMPLEXITY
--Design effort is minimal and simple 1
--Design effort is significant and simple 2
--Design effort is significant with some complexity 3
--Design effort is extensive and/or complex 4
B DESIGN MATURITY
--Proven design used frequently 1
--Modification to proven design 2
--Redesign of existing item for different application 3
--New design from first principles 4
C MANUFACTURING COMPLEXITY PROCESS:-
--Few simple processes Manufacturing, Inspection, 1
--Many simple processes Testing, Assembly, Cons- 2
--At least one complex process truction etc. 3
--Large number of complex processes 4
D ENVIRONMENTAL IMPACT, FAILURE EFFECT WOULD BE:-
--Limited to immediate location 1
--To spread to adjacent surroundings within the plant 2
--To spread beyond the plant upto the site/public boundary 3
--To spread beyond the site/public boundary 4
E FLUID CHARACTERISTICS
--Innocuous 1
--Low hazard/toxicity/temperature/pressure 2
--Medium hazard/toxicity/temperature/pressure 3
--High hazard/toxicity/temperature/pressure 4
F PRODUCT OR SERVICE SAFETY - FAILURES WOULD RESULT
IN 1
--No risk to health and safety 2
--Limited risk to health and safety of operators 3
--Significant risk to health and safety of operators 4
--Undue risk to operator and/or public
G ECONOMICS - FAILURE WOULD RESULT IN
--Negligible inconvenience and/or costs 1
--Downgrades service to limited extent and limited costs 2
--Seriously downgrades service with serious costs 3
--Total loss of service and extreme costs 4
H REPLACEMENT/REPAIR - FAILURE WOULD RESULT IN
--No difficulty 1
--Minimum difficulty 2
--Serious difficulty 3
--Extremely serious difficulty 4
J INSTALLATION
--Is simple and in line with general industrial practice 1
--Is moderate and in line with general industrial practice 2
--Is difficult and/or has significant impact on plant performance or safety 3
--Is very difficult and/or critical to plant performance and safety and must not 4

DOC. NO.: QSP-QC-09 Page 26 of 39


QUALITY REQUIREMENT

be compromised
EQUIPMENT/SYSTEM EVALUATION TOTALS =

APPENDIX 3

ESSENTIAL PROJECT DOCUMENTS

DOC. NO.: QSP-QC-09 Page 27 of 39


QUALITY REQUIREMENT

GENERAL NOTES

1. This document must be read in conjunction with the applicable contractual conditions.
2. All contractual documents must be in ENGLISH unless otherwise agreed.
3. Documents may be presented in electronic or hard copy format as required by the contract
agreement.
4. All documents must be identified with the Q.G.P.C. project number. Other identifiers will be
stipulated as per contract.
5. All documents must be legible and of a suitable quality for photocopying.
6. The precise number of copies required and the presentation format will be as required by the
contract agreement.
7. All documents, irrespective of the project phase shall be produced concurrently with the activity
sequence.
8. The preferred document sizes are A0, A1, A2, A3 and A4 as appropriate. Drawing sheets larger
than A0 shall not be used.

DOC. NO.: QSP-QC-09 Page 28 of 39


QUALITY REQUIREMENT

APPENDIX 4

EXAMPLES OF MECHANICAL COMPLETION CHECK SHEETS

DOC. NO.: QSP-QC-09 Page 29 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET

MECHANICAL GAS TURBINE

EQUIPMENT TITLE: REFERENCE No.:

EQUIPMENT TAG:

MANUFACTURER: SHEET 1 OF 2

LOCATION

CHECKS TO BE PERFORMED RESULTS INITIALS


1. Verify that Certification Documentation has been received
2. Verify that air intake filters are correctly installed and that a good seal exists between
filter frames and plenum chamber bulkhead
3. Check that air intake silencer splitters are correctly fitted and located and that splitters
skin-sheets are securely fixed to their frames with no skin panels damaged or joined
standing proud in the air system
4. Check all that fixing e.g. nuts, bolts, screws, clamps etc inside the plenum chamber and
downstream of the air intake filters are secure and permanently locked
5. Check integrity of the blow in door seals
6. Check all joins of the air intake housing for integrity and seal (weather proofness)
7. Check that the coupling guard is installed and securely bolted
8. Check that alternator anti-condensation heaters are connected to a temporary supply and
are in operation
9. Verify completeness of all paintwork and that damaged areas of paintwork have been
made good
10. Verify that the installation of the floor plating and support paintwork is in accordance
with approved drawings
11. Verify that all handrails are installed in accordance with approved drawings
12. Verify that all access platforms are installed in accordance with approved drawings
13. Verify that all ladders are complete with cages, step offs are at the correct elevation and
safety chains are fitted
Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.
CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 30 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET

MECHANICAL GAS TURBINE (continued)

EQUIPMENT TITLE: REFERENCE No.:

EQUIPMENT TAG:

MANUFACTURER: SHEET 2 OF 2

LOCATION

CHECKS TO BE PERFORMED RESULTS INITIALS


14. Verify that all windows, external doors and housing have been hose tested for
tightness
15. Verify that reference dimensions to exhaust stack location pads and pins are as per
approved drawings
16. Check that proof-test documentation and certification for lifting and handling
equipment has been received.
17. Check that lifting equipment is complete as per Bill of material and stored for use as
per Project instructions.
18. Check that fire and gas detection and protection is complete and installed as per
approved drawings
19. Verify that “Work Approval” documents for the alternator rotor platform are complete
and that the platform is stored as per instructions
20. Verify that mechanical completion verification check sheets have been completed for
the ancillaries
21. Verify that all necessary bonding of metal to earthed structural steel
22. Verify alignment
23. Verify lubrication flush *
24. Verify lubrication first fill *

* Items for mandatory witnessing by QGPC operations


Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.
CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 31 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET

MECHANICAL PUMP

EQUIPMENT TITLE: REFERENCE No.:

EQUIPMENT TAG:

MANUFACTURER: SHEET 1 OF 1

LOCATION

CHECKS TO BE PERFORMED RESULTS INITIALS


1. Verify that Certification Documentation has been received
2. Check nameplates for correctness and that they are securely attached
3. Verify storage requirements have been adhered to
4. Check pump and skid are not distorted by holding down bolts or mis-aligned piping.
If necessary pack out skid with stainless steel shims and correct piping alignment.
Check pump vertical horizontal
5. Verify alignment has been checked if required on MCR and that results are recorded.
6. Verify Mechanical seal gland and piping harness has been checked out if required.
7. Verify lube seal oil system has been checked out if required
8. Check lubrication of pump and motor bearings
9. Check pump vent is clean
10. Check pump vent is valved
11. Check pump drain is clean
12. Check pump drain is valved
13. Check free rotation of pump and motor by hand
14. Check suction strainer for correct installation as per specification
15. Check coupling replaced and all guards etc. fitted
16. Check ambient protection on unpainted internal and external machined parts is
adequate
17. Check all damaged areas of paint work have been made good
Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.

CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC


COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 32 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET

ELECTRICAL MAIN HV SWITCHGEAR

EQUIPMENT TITLE: REFERENCE No.:

EQUIPMENT TAG:

MANUFACTURER: SHEET 1 OF 7

LOCATION

EQUIPMENT DETAILS

Type _________________ Busbar Rating ________ Amps Fault Rating ____________


Voltage _______________ System __________________ Duty__________________

CAUTION REMOTE FEEDER PANEL (Feeding Equipment Under Inspection)


Circuit Breaker Withdrawn ______________ Bus-bar/Cable Shutters Locked OFF ____________________
Cable Earthed ___________ Permit to Work Issued ___________________________________________
CHECKS TO BE PERFORMED RESULTS INITIALS
1.0 GENERAL CHECKS
1.1 Equipment undamaged
1.2 All holding down bolts used and tightened
1.3 Switchgear is level
1.4 General alignment is satisfactory
1.5 All labels correct
1.6 Equipment erected as shown on GA
1.7 No dust in compartments and insulation surfaces clean
1.8 Correct phase relationship throughout bushars
*1.9 Bushar connections correct and tightened
1.10 Electrical connections on incoming 240V supplies correct & tightened
1.11 Electrical connections on tripping battery supplies correct & tightened
1.12 Fuse rating on incoming auxiliary supplies correct
1.13 Interlocks between feeders and bus-section circuit breakers.
Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.

* Items for mandatory witnessing by QGPC Operations


CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 33 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET SHEET 2 OF 7

CHECKS TO BE PERFORMED RESULTS INITIALS


1.14 All covers replaced and fastened
1.15 Switchboard earthing
1.16 Voltmeters checked
1.17 Ammeters checked
* 1.18 6.6 kV feeder circuit breaker tested
1.19 Power transformers tested
1.20 Emergency generator tested
1.21 Feeder cables tested
1.22 Battery/Charger unit tested
1.23 Busbar HV test
1.24 Busbar IR test
1.25 Busbar Ducter Test (where Total Length of Busbar exceeds 6 metres)
1.26 Control supplies IR test
1.27 Control Cables tested

2.0 BUS-BAR DUCTER TESTS

Main Bus-bars Results Initials

R
Y
B
Earth

* 3.0 INSULATION RESISTANCE TEST

Results Megohms

Test Phase Before HV Test After HV Test Test Date Initials

R to YBNE
Y to RBNE
B to RYNE
N to E
Secondary
Wiring
Note: Any outstanding Technical requirements should be raised to Punch-List Level and a
copy attached to this sheet.

DOC. NO.: QSP-QC-09 Page 34 of 39


QUALITY REQUIREMENT

* Items for mandatory witnessing by QGPC Operations


CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET SHEET 3 OF 7

* 4.0 HIGH VOLTAGE TEST

Test Phases Test Volts Duration Test Date Initials

R to YBNE 2000 60 secs


Y to RBNE 2000 60 secs
B To RYNE 2000 60 secs
N To E 2000 60 secs
Secondary Wiring 2000 60 secs
Note: If the Switchboard is not energised within one day of the HV Test being carried out then a
further IR Test shall be done.
Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.

* Items for mandatory witnessing by QGPC Operations


CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 35 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET SHEET 4 OF 7

2.0 L.V. CIRCUIT BREAKER CHECKS


Duty _____________________________________________________ Tag No. ________________

Panel No. __________________________________________________ Rating _________________

C/T Ratios _________________________________ Instrumentation


_________________________________ Protection
__________________________________ Metering

CHECKS TO BE PERFORMED RESULTS INITIALS


1.0 GENERAL CHECKS (CIRCUIT BREAKER)
1.1 Visual inspection of circuit breaker
1.2 Operation of all moving parts and mechanisms
1.3 Circuit breakers easily withdrawn and re-inserted
1.4 Automatic safety shutters operate correctly
1.5 Mechanical interlock to prevent circuit breaker being withdrawn with
isolator in “on position”
1.6 All dust seals undamaged
1.7 Electrical connections correct and tightened
1.8 Fuse raring correct and fuses and links inserted
1.9 Correct phase relationship with busbars
1.10 Shrouds intact on control wiring “live” terminals
1.11 Operations of all selector switches
1.12 Circuit breaker closing in withdrawn position
1.13 Operation of mechanical trip
1.14 Operation of mechanical indicator on circuit breaker
1.15 Cubicle heater (500 V Megger. Min. 10 megohm)
1.16 Cable core connections correct and identified
1.17 Cable terminations satisfactory
1.18 Cables identified correctly
1.19 Test single core cables terminated in non-magnetic gland plate
1.20 Power cables tested
1.21 Control cable tested
1.22 CB HV test
1.23 CB IR test
1.24 Control circuit IR test

DOC. NO.: QSP-QC-09 Page 36 of 39


QUALITY REQUIREMENT

1.25 Voltmeter operations/indication


1.26 Voltmeter selector switch
1.27 Frequency meter operation
1.28 Protective Relays checked

Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.
CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET SHEET 5 OF 7

* 2.0 INSULATION RESISTANCE TESTS

Test Phases Results Test Date Initials


Megohms
R to YBE
Y to RBE
B To RYE

3.0 HIGH VOLTAGE TESTS

Test Phases Test Volts Duration Test Date Initials

R To YBE 2000 60 secs


Y To RBE 2000 60 secs
B To RYE 2000 60 secs

NOTE: Above test only required if omitted at the time of General Switchboard tests
Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.
CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 37 of 39


QUALITY REQUIREMENT

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET SHEET 6 OF 7

3.0 FUSED SWITCH/ISOLATOR CHECKS

Equipment Tag _________________________________ Compartment Ref. ___________________

Circuit _________________________________________ Current Rating ______________________

Type __________________________________________

CHECKS TO BE PERFORMED RESULTS INITIALS


1.0 GENERAL CHECKS (FUSED SWITCH ISOLATOR)
1.1 Visual Inspection of switch
1.2 Operation of all moving parts
1.3 Mechanical interlock between switch handle and panel doors
1.4 All dust seals undamaged
1.5 Electrical connections correct and tightened
1.6 Fuse rating correct and fuses and links inserted
1.7 Correct phase relationship with busbars
1.8 Shrouds intact on “live” incoming supplies
1.9 Cable core connections correct and identified correctly
1.10 Cable terminations satisfactory
1.11 Cables identified correctly
1.12 Power cables tested
1.13 Switch IR test

2.0 INSULATION RESISTANCE TESTS

Test Phaes Results Megohms Test Date Initials

R To YBNE
Y To RBNE
B To RYNE
N To E

DOC. NO.: QSP-QC-09 Page 38 of 39


QUALITY REQUIREMENT

Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.
CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

QATAR PETROLEUM
MECHANICAL COMPLETION RECORD SHEET SHEET 7 OF 7

3.0 M.C.C. BKR. - PROTECTION TESTS

Instantaneous O/C & EF Thermal O/C Undervoltage


Panel Ref Setting Trip Current Setting Trip Time (Secs) Pick-up Drop Off vale
Value
Stated Actual Curve Actual

DOC. NO.: QSP-QC-09 Page 39 of 39


QUALITY REQUIREMENT

Note: Any outstanding Technical requirements should be raised to Punch-List Level and a copy attached to this sheet.
CHECKED BY MANUFACTURER CONTRACTOR THIRD PARTY QGPC
COMPANY
NAME
SIGNATURE

DOC. NO.: QSP-QC-09 Page 40 of 39