Republic of the Philippines

Office of the President


National Irrigation Administration
(PAMBANSANG PANGASIWAAN NG PATUBIG)
SURIGAO DEL SUR IRRIGATION MANAGEMENT OFFICE

PLANNING AND DESIGN UNIT WORKPLAN 2022

WHAT RESOURCES WILL BE WHEN IT WILL BE COMPLETED


WHAT WILL BE DONE WHO WILL BE RESPONSIBLE HOW THE RESULT ARE EVALUATED
REQUIRED (DURATION)

FEASIBILITY STUDY PRE-FEASIBILITY STUDY PLANNING TEAM JANUARY 2022-DECEMBER 2022 FINAL FEASIBILITY STUDY REPORT

COMPLETE SURVEY DATA VALIDATED


LISTING OF PRE-IDENTIFIED AREA
SURVEY WORKS PLANNING TEAM/SURVEY TEAM JANUARY 2022-JUNE 2022 BY THE PLANNING HEAD & DESIGN
FOR PROJECT ID
ENGINEER
DETAILED DESIGN SURVEY DATA DESIGN TEAM FEBRUARY 2022-SEPTEMBER 2022 APPROVED GFC/STATUS OF PLANS
APPROVED BUDGET ALLOCATION BUDGET PROPOSAL PLANNING TEAM MARCH 2022-SEPTEMBER 2022 NEP 2022
APPROVED PLANS, ESTIMATES
PROGRAM OF WORKS PROGRAMMING TEAM AUGUST 2022-SEPTEMBER 2022 APPROVED POW
AND CANVASS
STATUS OF PROJECT
STATUS OF IRRIGATION
IRRIGATION DEVELOPMENT IMPLEMENTATION AND PLANNING TEAM JANUARY 2022-DECEMBER 2022 DEVELOPMENT
INVENTORY OF AREA

IRRIGATION MASTERPLAN APPROVED NEP PLANNING TEAM JANUARY 2022-DECEMBER 2022 UPDATED IRRIGATION MASTERPLAN

MONTHLY DISCHARGE DATA


WATER DISCHARGE CALIBRATION PLANNING TEAM JANUARY 2022-DECEMBER 2022
SUBMITTED MONTHLY

Prepared by: Checked by: Reviewed by: Approved by:

AIMEE R. GOZON YCEL A. CORPUZ EMILDA C. NERMAL DEXTER A. SABLAON


Engineer A Sup. Engineer A Sr. Engineer A Division Manager
Republic of the Philippines
Office of the President
National Irrigation Administration
(PAMBANSANG PANGASIWAAN NG PATUBIG)
SURIGAO DEL SUR IRRIGATION MANAGEMENT OFFICE

PLANNING & DESIGN UNIT WORKPLAN


C Y 2 0 2 2
NO. ACTIVITY JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER

1 FEASIBILITY STUDY

2 SURVEY WORKS

3 DETAILED DESIGN

4 APPROVED BUDGET ALLOCATION

5 PROGRAM OF WORKS

6 IRRIGATION DEVELOPMENT

7 IRRIGATION MASTERPLAN

8 WATER DISCHARGE CALIBRATION

Prepared by: Checked by: Reviewed by: Approved by:

AIMEE R. GOZON YCEL A. CORPUZ EMILDA C. NERMAL DEXTER A. SABLAON


Engineer A Sup. Engineer A Sr. Engineer A Division Manager
SURVEY TEAM WORKPLAN
C Y 2 0 2 2
NO. PROJECT AREA MUNICIPALITY DISTRICT JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Panaosawon SIP 67.72 Bayabas I
3 Cabas-an CIS 9.33 Cantilan I
4 Bugsukan Creek - Tapi PIP (CANTIS) 137.32 Cantilan I
5 Alamio River - Magasang PIP (CANTIS) 342.21 Cantilan I
6 Calagdaan GIP(CANTIS) 71.46 Cantilan I
7 Patong-Patong/Parang GIP(CANTIS) 216.13 Cantilan I
8 Anibongan CIS 69.10 Lianga I
9 Payasan CIS 47.65 Lianga I
10 Buyaan II CIS (San Roque) 52.16 Madrid I
11 Mag-uyon GIP(CANTIS) 107.78 Madrid I
12 Sta. Cruz SIS 52.37 Marihatag I
13 Amontay GIP 44.87 Marihatag I
14 Hubo Left Main 16.04 San Agustin I
15 Hubo Right Main 107.53 San Agustin I
16 Salvacion CIS 78.08 San Agustin I
17 Taguibo River - Janipaan-Pong-on SIP 185.79 San Agustin I
18 Bolhoon CIS 608.35 San Miguel I
19 Catabadan CIS 112.77 San Miguel I
20 Mabuhay CIS 354.89 San Miguel I
21 Camagtong CIP 211.00 San Miguel I
22 Haguimitan SIP 91.66 San Miguel I
23 Marga SIP 15.80 San Miguel I
24 Bitaugan Creek - Bitaugan SIP 104.84 San Miguel I
25 Cayale CIS 124.45 Tago I
26 Banacan GIP 18.72 Tago I
27 Rosario-VictoriaGIP 62.06 Tago I
28 Maticdum CIP 52.61 Tandag I
29 San Isidro CIS 81.46 Tandag I
30 Maitum CIS 11.18 Tandag I
31 Pangi 32.69 Tandag I
32 Mabog SIS 85.87 Bislig II
33 Tidman CIS 82.98 Hinatuan II
34 Portlamon GIP 19.84 Hinatuan II
35 Tagbina GIP 48.00 Tagbina II
36 Manambia GIP 28.30 Tagbina II
37 Anislagan GIP 15.22 Tagbina II

LEGEND:
TEAM 1 PEDROZO
TEAM 2 PACHECO
TEAM 3 OLACO

Prepared by: Checked by: Reviewed by: Approved by:


GILBERT A. MALINAO YCEL A. CORPUZ EMILDA C. NERMAL DEXTER A. SABLAON
Sr. Engineer A Sup. Engineer A Sr. Engineer A Division Manager