GABON ROAD PROJECT

SATURDAY
MAY 2021

01

REHABILITATION & UPGRADATION OF 2 LANE NATIONAL ROAD RN1 FROM PK24+000 TO PK


105+000 ON EPC BASIS IN GABON
WEEKLY PROGRESS REPORT 14

 NAVIGATOR
93
DAY
OF
547
DURATION
SATURDAY
MAY 2021

01

SAFETY QUALITY STATUS SCHEDULE LOOK AHEAD KEY HIGHLIGHTS

1. SAFETY 4. SCHEDULE
2. QUALITY 5. LOOK AHEAD
3. PROJECT STATUS 6. KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE GABON ROAD PROJECT LAYOUT 

Building
B

Building
A

 NAVIGATOR
WEEKLY UPDATE SAFETY STATISTICS 
159,900 NCR ISSUED : 00
NCR OPEN : 00
ACCIDENT FREE MAN HOURS
OBSERVATION ISSUED : 00
OBSERVATION OPEN : 00
TOTAL SAFE MANHOURS SAFETY
Achieved on Project AVERAGE NUMBER OF MANDAYS DURING WEEK:180 NOS

159,900 HRS NUMBER OF LOST TIME INJURIES : NIL


NUMBER OF ACCIDENTS : NIL
WORKMEN INDUCTION STATISTICS :180 NOS
SAFETY BULLETIN/ TOPICS ISSUED : NIL

 NAVIGATOR
WEEKLY UPDATE PROJECT STATUS 
START
Monday SURVEY WORKS GEO TECHNICAL MOBILISATION
FINISH
Monday

COMPLETED FOR PK50- INVESTIGATION FOR


JAN 2021 PK75. PK50-PK75. JUL 2022

22 100 % 100 % 40 % 22

STATUS

COMPLETION FOR
NTP FOR SEGMENT 4
PROJECT NTP FOR NTP FOR
CONSTRUCTION 22 FEB 2022
COMMENCEMENT CONSTRUCTION CONSTRUCTION
FOR SEGMENT 4 FOR SEGMENT 5 &6 FOR SEGMENT 1 &3
DATE- 22 JAN OVERALL PROJECT
22 MAR 2021 22 JUN 2021 22 SEP 2021
2021 COMPLETION DATE-
22 JUL 2022
NTP FOR
NTP FOR
DETAILED
DETAILED
DESIGN FOR
DESIGN FOR
SEGMENT 4,5 & 6
SEGMENT 1, 2 & 3
- 22 JAN 2021
22 APR 2021

2021 2022
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18

 NAVIGATOR
WEEKLY UPDATE EMPLOYER’S ACCOMODATION EXCAVATION STARTED 

KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE EMPLOYER’S OFFICE WORK COMPLETED UPTO DPC 

KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE WEIGHBRIDGE CABIN WORK COMPLETED 

KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE CLIENT TEAM VISIT AT SITE 

KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE SAFETY PROTOCOLS AT SITE 
PAINTING ON DIESEL TANKER

TOOL BOX TALKS SAFETY DELINEATOR

KEY HIGHLIGHTS

NOISE MOINTORING

 NAVIGATOR
WEEKLY UPDATE CAMP WORKS IS IN PROGRESS 
ENGINEER ACCOMODATION INTERNAL DRAIN

KEY HIGHLIGHTS

FOOTPATH LAYING

 NAVIGATOR
WEEKLY UPDATE ACCESS ROAD WORKS COMPLETED FOR BASE CAMP 2 

KEY HIGHLIGHTS

 NAVIGATOR
WEEKLY UPDATE KEY HIGHLIGHTS OF THIS WEEK 
KEY HIGHLIGHTS :

 ICO Office work is Almost completed.


 Employer Office completed upto DPC.
 Client Team Visit at Camp and Site on 30/04/2021
 Employer’s Accommodation excavation work started
 STP Installation Works completed.
 Access Road to Base Camp 2 at PK 95 is completed.
 Material Testing and Sampling, Concrete Design Mix, is in progress.
 Pole Erection of 630 KVA Substation works is in progress.
KEY HIGHLIGHTS
 Cabin for Weighbridge is completed.
 Crusher Operation Workforce Arrived in Gabon

 NAVIGATOR
WEEKLY UPDATE KEY STAFF PERSONNEL - ORGANIZATION CHART 
Mr. Appa Rao
(Sr. Manager Execution)
Mr. Sisir
(Manager Admin)
Mr. Anand V (Sr.
Manager CPE)

Mr. Rajeshwar Sao


(Sr. Manager QA/QC)
Mr. Muneesh
(Manager Finance)
Mr. Aneesh
(Manager HSE) STATUS
Sujit Kr. Jha
(Project Manager)
Mr. Santhosh
(Manager Planning)
Mr. Srikanth
(Manager Logistics)
Mr. Subanna
(Manager Highway)

Mr. Ravindra
(Manager Structure)
Mr. Kailash
(Office Store)
Mr. P Balram
(Manager Design)

Mr. Ange
(Manager Environment)

 NAVIGATOR
WEEKLY UPDATE MANDAYS STATUS 
Workmen Mandays till After Commencement
Months
Skilled Unskilled Skilled Unskilled
Sep-20 12 4
Oct-20 265 250
Nov-20 286 546
STATUS
Dec-20 666 469
Jan-21 994 881 368 472
Feb-21 3,420 2,790 3,420 2,790
Mar-21 1,200 900 1,200 900
Apr-21 3,000 2,310 3,000 2,310
Total 9,843 8,150 7,988 6,472

 NAVIGATOR
WEEKLY UPDATE MOBILISATION STATUS 
SL. NO. MANPOWER EXPATS NATIONAL TOTAL

1 ENVIRONMENT ENGINEER 2 2

2 HEALTH & SAFETY ENGINEER 1 4 5

3 MALE NURSE 1 1

4 DOCTOR 1 1 2

5 QA/QC ENGINEER 2 2 4 SCHEDULE

6 SURVEY 2 2 4

7 EXECUTION TEAM 31 31

8 SKILLED/UNSKILLED WORKFORCE 20 168 188

TOTAL 57 180 237

 NAVIGATOR
WEEKLY UPDATE
PLANT AND MACHINERY MOBILISATION STATUS
AND SCHEDULE 

May-21

May-22
Aug-21

Nov-21
Sep-21

Dec-21

Mar-22
Jun-21

Feb-22

Jun-22
Jan-22
Oct-21
Apr-21

Apr-22
Jul-21

Jul-22
Description of Assets Cap. Plan. Avl.

Excavator 20/30T 9 4 6 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Crawler Bull Dozer D6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Motor Grader 120 k 5 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4
Soil Compactors 10T 6 2 5 6 6 6 6 6 6 6 6 6 6 6 6 5 5 4
Tractor Dozer 75 HP 4 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Dumpers 25/40T 66 18 58 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66
Wheel Loader 2.1 Cum 7 3 3 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Backhoe Loader 0.3 Cum 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Water Tanker 10 KLit 8 0 1 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Trailer 50 TON 3 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
SCHEDULE
Generator 82.5 to 500 KVA 8 8 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Weigh Bridge 100 TON 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Concrete Batching Plant 30 cum/Hr 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Transit Mixer 6 Cum 10 0 1 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
HOT Mix Plant 260 / 160 TPH 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
9/10m
Asphalt Paver 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Width
Tandem Rollers 14T 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
PTR 24T 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Cement Bulker 30T 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Stone Crusher 250TPH 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 144 53 107 145 146 146 146 146 146 146 146 146 146 146 146 145 145 142

 NAVIGATOR
WEEKLY UPDATE WEATHER REPORT 

STATUS

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 

LOOK AHEAD

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 

LOOK AHEAD

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 

LOOK AHEAD

 NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS 

LOOK AHEAD

 NAVIGATOR
WEEKLY UPDATE SUPPORT REQUIRED 
SUPPORT REQUIRED:

 Permission from administration for operation in curfew hours/other received through Laissez
passer. However, these passes couldn’t be used as vehicles and drivers still pending as we are
able to operate at 50% efficiency.
 Expediting of Euro payments against 2nd and 3rd Payment Milestone.
 Intervention in expediting VISA process for expats.
 Facilitation for royalty exemption for the earth, laterite and sand being project of national
importance as per taxation rules of Gabon and precedence of earlier projects executed in
Gabon.
 Expediting land handing over for construction operation at site.
 Requesting for partial drawing clearance for starting physical works at site.
 Variation instruction regarding Ministry approved drawings awaited. KEY HIGHLIGHTS

 NAVIGATOR
Thank You

www.afcons.com

 NAVIGATOR