SATURDAY
MAY 2021
01
NAVIGATOR
93
DAY
OF
547
DURATION
SATURDAY
MAY 2021
01
1. SAFETY 4. SCHEDULE
2. QUALITY 5. LOOK AHEAD
3. PROJECT STATUS 6. KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE GABON ROAD PROJECT LAYOUT
Building
B
Building
A
NAVIGATOR
WEEKLY UPDATE SAFETY STATISTICS
159,900 NCR ISSUED : 00
NCR OPEN : 00
ACCIDENT FREE MAN HOURS
OBSERVATION ISSUED : 00
OBSERVATION OPEN : 00
TOTAL SAFE MANHOURS SAFETY
Achieved on Project AVERAGE NUMBER OF MANDAYS DURING WEEK:180 NOS
NAVIGATOR
WEEKLY UPDATE PROJECT STATUS
START
Monday SURVEY WORKS GEO TECHNICAL MOBILISATION
FINISH
Monday
22 100 % 100 % 40 % 22
STATUS
COMPLETION FOR
NTP FOR SEGMENT 4
PROJECT NTP FOR NTP FOR
CONSTRUCTION 22 FEB 2022
COMMENCEMENT CONSTRUCTION CONSTRUCTION
FOR SEGMENT 4 FOR SEGMENT 5 &6 FOR SEGMENT 1 &3
DATE- 22 JAN OVERALL PROJECT
22 MAR 2021 22 JUN 2021 22 SEP 2021
2021 COMPLETION DATE-
22 JUL 2022
NTP FOR
NTP FOR
DETAILED
DETAILED
DESIGN FOR
DESIGN FOR
SEGMENT 4,5 & 6
SEGMENT 1, 2 & 3
- 22 JAN 2021
22 APR 2021
2021 2022
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18
NAVIGATOR
WEEKLY UPDATE EMPLOYER’S ACCOMODATION EXCAVATION STARTED
KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE EMPLOYER’S OFFICE WORK COMPLETED UPTO DPC
KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE WEIGHBRIDGE CABIN WORK COMPLETED
KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE CLIENT TEAM VISIT AT SITE
KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE SAFETY PROTOCOLS AT SITE
PAINTING ON DIESEL TANKER
KEY HIGHLIGHTS
NOISE MOINTORING
NAVIGATOR
WEEKLY UPDATE CAMP WORKS IS IN PROGRESS
ENGINEER ACCOMODATION INTERNAL DRAIN
KEY HIGHLIGHTS
FOOTPATH LAYING
NAVIGATOR
WEEKLY UPDATE ACCESS ROAD WORKS COMPLETED FOR BASE CAMP 2
KEY HIGHLIGHTS
NAVIGATOR
WEEKLY UPDATE KEY HIGHLIGHTS OF THIS WEEK
KEY HIGHLIGHTS :
NAVIGATOR
WEEKLY UPDATE KEY STAFF PERSONNEL - ORGANIZATION CHART
Mr. Appa Rao
(Sr. Manager Execution)
Mr. Sisir
(Manager Admin)
Mr. Anand V (Sr.
Manager CPE)
Mr. Ravindra
(Manager Structure)
Mr. Kailash
(Office Store)
Mr. P Balram
(Manager Design)
Mr. Ange
(Manager Environment)
NAVIGATOR
WEEKLY UPDATE MANDAYS STATUS
Workmen Mandays till After Commencement
Months
Skilled Unskilled Skilled Unskilled
Sep-20 12 4
Oct-20 265 250
Nov-20 286 546
STATUS
Dec-20 666 469
Jan-21 994 881 368 472
Feb-21 3,420 2,790 3,420 2,790
Mar-21 1,200 900 1,200 900
Apr-21 3,000 2,310 3,000 2,310
Total 9,843 8,150 7,988 6,472
NAVIGATOR
WEEKLY UPDATE MOBILISATION STATUS
SL. NO. MANPOWER EXPATS NATIONAL TOTAL
1 ENVIRONMENT ENGINEER 2 2
3 MALE NURSE 1 1
4 DOCTOR 1 1 2
6 SURVEY 2 2 4
7 EXECUTION TEAM 31 31
NAVIGATOR
WEEKLY UPDATE
PLANT AND MACHINERY MOBILISATION STATUS
AND SCHEDULE
May-21
May-22
Aug-21
Nov-21
Sep-21
Dec-21
Mar-22
Jun-21
Feb-22
Jun-22
Jan-22
Oct-21
Apr-21
Apr-22
Jul-21
Jul-22
Description of Assets Cap. Plan. Avl.
Excavator 20/30T 9 4 6 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Crawler Bull Dozer D6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Motor Grader 120 k 5 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4
Soil Compactors 10T 6 2 5 6 6 6 6 6 6 6 6 6 6 6 6 5 5 4
Tractor Dozer 75 HP 4 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Dumpers 25/40T 66 18 58 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66
Wheel Loader 2.1 Cum 7 3 3 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Backhoe Loader 0.3 Cum 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Water Tanker 10 KLit 8 0 1 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Trailer 50 TON 3 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
SCHEDULE
Generator 82.5 to 500 KVA 8 8 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Weigh Bridge 100 TON 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Concrete Batching Plant 30 cum/Hr 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Transit Mixer 6 Cum 10 0 1 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
HOT Mix Plant 260 / 160 TPH 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
9/10m
Asphalt Paver 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Width
Tandem Rollers 14T 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
PTR 24T 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Cement Bulker 30T 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Stone Crusher 250TPH 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 144 53 107 145 146 146 146 146 146 146 146 146 146 146 146 145 145 142
NAVIGATOR
WEEKLY UPDATE WEATHER REPORT
STATUS
NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS
LOOK AHEAD
NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS
LOOK AHEAD
NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS
LOOK AHEAD
NAVIGATOR
WEEKLY UPDATE LOOK AHEAD PLAN- 4 WEEKS
LOOK AHEAD
NAVIGATOR
WEEKLY UPDATE SUPPORT REQUIRED
SUPPORT REQUIRED:
Permission from administration for operation in curfew hours/other received through Laissez
passer. However, these passes couldn’t be used as vehicles and drivers still pending as we are
able to operate at 50% efficiency.
Expediting of Euro payments against 2nd and 3rd Payment Milestone.
Intervention in expediting VISA process for expats.
Facilitation for royalty exemption for the earth, laterite and sand being project of national
importance as per taxation rules of Gabon and precedence of earlier projects executed in
Gabon.
Expediting land handing over for construction operation at site.
Requesting for partial drawing clearance for starting physical works at site.
Variation instruction regarding Ministry approved drawings awaited. KEY HIGHLIGHTS
NAVIGATOR
Thank You