CONSTRUCTION UPDATE ON

PNP MEDICAL PLAZA PROJECT

AS OF 20 AUGUST 2021
GANTT CHART
S-CURVE & CASH FLOW
SUMMARY:

TARGET TO-DATE: 0.956%


ACTUAL TO-DATE: 0.961%
VARIANCE: +0.005%

DAYS DELAYED / AHEAD: 0


REMARKS: ON-TIME
PAST ACTIVITIES

ACTIVITY TARGET START TARGET COMPLETION REMARKS

MOBILIZATION 23 JUN 2021 20 JUL 2021 COMPLETED

TARGET ACTIVITIES TO-DATE

ACTIVITY TARGET START TARGET COMPLETION REMARKS

OCCUPATIONAL HEALTH AND SAFETY 23 JUN 2021 14 MAR 2023 SHOULD BE ON-GOING

CLEARING, GRUBBING AND TEMFACIL 21 JUL 2021 17 AUG 2021 SHOULD BE COMPLETED

STRUCTURAL EXCAVATION ZONE 1 18 AUG 2021 09 NOV 2021 SHOULD BE ON-GOING

ACTUAL ACTIVITIES TO-DATE

ACTIVITY ACTUAL START ACTUAL COMPLETION REMARKS

OCCUPATIONAL HEALTH AND SAFETY 23 JUN 2021 ON-GOING

CLEARING, GRUBBING AND TEMFACIL 21 JUL 2021 ON-GOING

STRUCTURAL EXCAVATION ZONE 1 09 AUG 2021 STARTED EARLY

OVERDUE

ACTIVITY TARGET START TARGET COMPLETION REMARKS

CLEARING, GRUBBING AND TEMFACIL 21 JUL 2021 17 AUG 2021 NOT YET COMPLETED DUE TO BULK EXCAVATION
NOT INCLUDED IN THE CONTRACT
PROGRESS PHOTOS
CONTINUATION OF BULK EXCAVATION
HAUL-OUT OF EXCAVATED BULK
STRUCTURAL EXCAVATION
TRIMMING OF STRUCTURAL EXCAVATION
DELIVERY OF REBARS 2ND BATCH
FABRICATION OF REBARS
FABRICATINO OF CONCRETE COVER
PADUGO
TRIAL MIX
TRIAL MIX
TRIAL MIX
OBSTRUCTIONS
(ISSUES AND CONCERNS)
OVERVIEW
AGGREED GROUND FLOOR ELEVATION
LEVELED WITH REAR ROAD ELEVATION
RESULTING ELEVATION OF SOG
RESULTING ELEVATION OF TIE BEAMS
RESULTING STRUCTURAL EXCAVATION
PRESUMING THIS AS NGL
SHOWING BULK EXCAVATION NEEDED TO BE REMOVE FIRST
PRIOR TO STRUCTURAL EXCAVATION
BIM QUANTITY
BIM QUANTITY

Cost  1,188.4m3 x P400/m3 (as per contract) = P475,360.00


Time Extension  2 Months
REQUEST FOR APPROVAL
AND
REQUEST FOR INFOMATION
RUNNING RISKS
TO DELAY PROJECT
• PAST HEAVY RAINS
• SITE OBSTRUCTIONS (SCRAPS FROM PHASE 1)
• BULK EXCAVATION AND DISPOSAL NOT PART OF CONTRACT /
TIMELINE
• DIFFICULTIES IN SUPPLY OF MATERIALS DUE TO COVID 19
LOCKDOWN STARTED 06 AUGUST 2021