PROGRESS REPORT – 15
1 Introduction 1
7 Organization Chart 22
8 HSE 23-25
9 Project Contacts 26
10 Site Visitors 27
13 Proposed Subcontractors 31
16 Approved Samples 46
17 Invoicing Status 47
Brief Description :- The above project was awarded to M/S Ali Amin Ramdhan Trad Co
for a total value of R.O 1,000,000.000 (One Million Only) & duration of 18 months.
The Project is funded by The Petroleum Development Oman (P.D.O).
The Project is Under the Supervision of the Consultant Ms/ Simon Engineering &
Partners LLC & the Directorate General of Projects & Engineering Affairs –Ministry of
Health.
The project consists of the following area as mentioned below.
Project Description: - The project consists of a Main Health Center Building &
Maternity Building with Various Health Care Facilities. Including also the below.
2. Maternity Unit
a. Civil – Structural & Architectural Works
b. Electrical Works including Fire Alarm System, Nurse Call System, BHU,
Structured Cabling Works & Lightning Protection System etc.
c. HVAC – Centralized Ducted Package Unit System
d. Mechanical – Drainage, Water Supply & Fire Fighting System
3. Guard Room
a. Civil – Structural & Architectural Works
b. Electrical Works including Fire Alarm System, Structured Cabling Works &
Lightning Protection System etc.
c. HVAC
d. Mechanical – Drainage, Water Supply & Fire Fighting System
1
[Type text]
HYHHH
CONSTRUCTION OF MUQSHIN HEALTH CENTER
Contract Details
1 Mobilization Start Date 15.01.2020
2 Mobilization Complete 15.02.2020
3 Construction start Date 16.02.2020
4 Completion of Project 15.08.2021
5 Project Duration 18 Months
6 Completion of Maintenance 15.08.2022
Financial Summary
S.No. DESCRIPTION AMOUNT IN RIYAL OMANI
1 Contract Amount 1,000,000.000
2 Preliminaries & General Requirements Included
3 Provisional Sum Nil
4 Health Center Building 500,676.140
5 Maternity Building 170,949.220
6 Guard House 12,934.540
7 Road Works 5,129.300
8 External Works 251,776.750
9. External Services. 52,235.100
10. Water Tank 6,299.560
2
PROJECT:-CONSTRUCTION OF MUQSHIN HEALTH CENTER
PROJECT CUMULATIVE WORK PROGRESS as of 31-05-2021
As PER CASH FLOW CHART.
3
PROJECT:-CONSTRUCTION OF MUQSHIN HEALTH CENTER
JOB DESCRIPTION
S.NO Delay as per the Time Schedule.
4
Project:- Muqshin Health Center.
Progress As Per Time Schedule
Project Start Date 16.02.2019
Project Completion Date 15.08.2021
Project Duration 547 days
Current Date 31.05.2021
Total Days Elapsed as per Planned 470
Total Actutal Progress Achieved in Days 286
Delay as per Time Schedule. 33.638%
470
0.00 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00 500.00
(Delay:- 33.63 %)
286
0.00 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00 500.00
4A
PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER
WORK STATUS as of 31-05-2021 (Main Health Center, Maternity Building, GUARD
HOUSE, COMPOUND WALL, HOLDING TANK & EXTERNAL GRP WATER TANK)
10 16 Main Bldg. - Curing of Stub Column 04/10/2020 10/10/2020 16/10/2020 28/10/2020 12 Days 18 Days
5
Main Bldg. - Curing for External
12 18 06/10/2020 08/10/2020 23/10/2020 01/11/2020 18 Days 25 Days
Solid Block Work PCC
Main Bldg. - External Perimeter Solid
13 19 06/10/2020 17/10/2020 25/10/2020 12/11/2020 19 Days 26 Days
Block Work
6
Delayed 140
25 40 Starter Column marking & Concrete 12.01.2021 13.01.2021 Not Started
days
Ground floor Column Foam work & Delayed 138
26 41 14.01.2021 27.01.2021 Not Started
Concrete. days.
Ground floor slab foam work & Delayed 124
27 43 28.01.2021 03.03.2021 Not Started
Reinforcement. days
Concealed conduiting in roof slab for Delayed 109
28 44 12.02.2021 03.03.2021 Not Started
electric & HVAC works. days
Delayed 89
29 45 Ground floor roof slab concrete 04.03.2021 06.03.2021 Not started
days
Roof slab curing & deshuttering Delayed 86
30 46,47 07.03.2021 25.03.2021 Not started
works. days.
Plant room Column & roof slab foam Delayed 67
31 48,49 26.03.2021 13.04.2021 Not started
work & concrete works. days
Roof parapet foam work Delayed 48
32 50 14.04.2021 27.04.2021 Not started
reinforcement & concrete. days
Ground floor block work till lintel Delayed 67
33 54 26.03.2021 22.04.2021 Not started
bottom. days
Ground floor Lintel Reinforcement Delayed 39
34 55 23.04.2021 29.04.2021 Not started
shuttering & Concrete. days
35 56 Ground floor Block work above lintel 30.04.2021 06.05.2021 Not started Delayed 32 day
Provision of all Concealed wall Delayed 39
36 57 23.04.2021 22.05.2021 Not started
electrical, ELV system, data. days
Provision of all concealed UPVC soil Delayed 39
37 58 23.04.2021 22.05.2021 Not started
waste vent piping works days
Provision of all concealed & main Delayed 39
38 59 23.04.2021 22.05.2021 Not started
copper piping for water supply. days
Provision for Wall Cut out Openings Not started
Delayed 32
39 60 including Lintel above it for Block 30/04.2021 09.05.2021
days
work for HVAC Ducts
Not started Delayed 25
40 61 Installation of Steel Door Frames. 07.05.2021 16.05.2021
days
Not started Delayed 15
41 62 Internal Wall Plaster. 17.05.2021 15.06.2021
days
Not started Delayed 15
42 63 X-Ray Lead Lining & plastering 17.05.2021 25.06.2021
days
7
43 64 HVAC Main Ducting & branches. 17.05.2021 25.06.2021 Not started Delayed 15 days
44 65 Above False ceiling GI Trunking. 17.05.2021 05.06.2021 Not started Delayed 15 days
45 69 Roof parapet Wall internal plaster. 05.05.2021 16.05.2021 Not started Delayed 27 days
"Casting of all foundation plinths for Not started
46 70 17.05.2021 21.05.2021 Delayed 15 days
HVAC package units, water tanks
47 71 Roof
etc." Claustra Block Enclosure 22.05.2021 05.06.2021 Not started Delayed 10 days
Roof Plant Room Block work & Not started
48 72 22.05.2021 05.06.2021 Delayed 10 days
Plaster Finishes
49 109 External Wall Plastering 17.05.2021 10.06.2021 Not started Delayed 15 days
External Drainage works including Not started
50 110 27.05.2021 20.06.2021 Delayed 5 days
Manholes & Gully Traps.
External Main cable duct pipe, sand Not started
51 111 27.05.2021 20.06.2021 Delayed 5 days
bed, caution tape, backfilling.
External Fire Fighting, Hydrant, Fire Not started
52 112 27.05.2021 20.06.2021 Delayed 5 days
Pump Installation works
External Telephone data ducting, Not started
53 113 27.05.2021 20.06.2021 Delayed 5 days.
Encasement, backfilling.
Excavation for Boundary Wall
54 136 23/08/2020 02/09/2020 23/08/2020 02/09/2020 Nil Nil
(Phase-1) Plot Ref. Pt.-2 to Ref Pt.-5
Phase-1 Boundary Wall – Foundation In Progress
55 138 13/09/2020 19/09/2020 28/10/2020 45 Days 255 days
PCC 93% Complete
Phase-1 Boundary Wall – Foundation
In Progress
56 140 Form Work, Reinforcement & 20/09/2020 24/10/2020 10/11/2020 51 Days 220 days
87% Complete
Concrete
Phase-1 Boundary Wall –
Substructure RCC Wall & Column In Progress
57 142 25/10/2020 28/11/2020 07.12.2020 43 days 245 days
Form Work, Reinforcement Work & 93 % Complete
Concrete Work
Phase-1 Boundary Wall – Super
Delayed 184
58 145 Structure Column - Form & 29/11/2020 07/01/2021 Not Started
days
Reinforcement Work & Concrete (
Phase-1 Boundary wall super Not Started Delayed 144
59 146 08.01.2021 06.02.2021
structure block work + Top Coaping. days
Not Started Delayed 114
60 147 Phase-1 Boundary Wall plastering. 07.02.2021 18.03.2021
days
8
Excavation for Boundary Wall In Progress
61 147 03/09/2020 27/09/2020 12/09/2020 10 Days 245 days
(Phase-2) Plot Ref. Pt.-5 to Ref Pt.-2 60% Complete
Phase-2 Boundary Wall – Foundation In Progress
62 149 13/10/2020 26/10/2020 22/12/2020 70 Days 161 days
PCC 50% Complete
Phase-2 Boundary Wall – Foundation
In Progress
63 152 Form Work, Reinforcement & 27/10/2020 15/12/2020 08.11.2020 12 days. 154 days
31% Complete.
Concrete
Phase-2 Boundary wall Substructure In Progress
64 154 16/12/2020 29/01//2021 09/01/2021 24 days 122 days
RCC Columns 26% Complete
In Progress
65 155 Substructure Solid Block work. 30.01.2021 21.02.2021 31.01.2021 2 day 84 days
26% Complete
Phase-2 Boundary wall-Super Not Started Delayed 99
66 156 22.02.2021 12.04.2021
structure RCC Columns days
Phase-2 Boundary wall-Super Not Started Delayed 49
67 157 13.04.2021 01.06.2021
structure Block work & Coaping. days
17/10/2020
(Holding Tank
Excavation for Holding Tank & 1 Day in 1 Day in
68 161 28/09/2020 18/10/2020 27/09/2020 Excavation
External GRP Water Tank Advance Advance
Upto 4mtr
Depth)
(18/01/21 )
Holding Tank & GRP Water Tank –
69 162 19/10/2020 28/10/2020 27/09/2020 Completed only 188 days
Soil Leveling & Compaction
GRP Tank Rm
162
Holding Tank & External GRP Tank Delayed 215
70 to 29.10.2020 23.12.2020 Not Started
foundations. days
166
167
Water Tank Works & RCC Holding Delayed 166
71 to 17.12.2020 07.05.2021 Not Started
Tank Top Cover Slab days
179
9
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH CENTER.
LIST OF ACTIVITIES PLANNED FOR THE Month of JUNE -2021 (Main Health Center, Maternity
Building, GUARD HOUSE, COMPOUND WALL, HOLDING TANK & EXTERNAL GRP TANK)
Variance Variance
Baseline
Task Baseline between between
No. Task Name Finish Actual Start Actual Finish
ID Start Date Start Finish
Date
Dates Dates
11
MUQSHIN HEALTH CENTER
120 PROGRAMMED S-CURVE
110
(Original Baseline Program) Planned Progress %
100
80
Actual Acheived Progress %
70
60
50
40
30
20
10
0
Aug-20
Nov-20
Aug-21
Apr-20
Apr-21
Feb-20
Mar-20
Jun-20
Jul-20
Sep-20
Oct-20
Dec-20
Jan-21
Feb-21
Mar-21
Jun-21
Jul-21
May-20
May-21
Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21
(Original Baseline Program) Planned Progress % 0.000 1.111 2.222 3.333 6.950 10.672 14.450 18.339 22.061 28.006 33.528 41.472 49.639 58.417 71.228 84.261 89.261 94.261 100.000
(Recovery Program) Planned Progress % 0.000 0.743 1.354 1.853 2.369 3.244 4.188 6.962 10.845 16.116 22.630 32.228 42.048 54.809 68.713 84.153 90.256 95.249 100.000
Actual Acheived Progress % 0.000 0.743 1.354 1.853 2.369 3.244 4.188 6.407 7.167 8.532 10.524 11.234 11.739 12.194 12.769 13.845
MONTH
19
PROJECT :- MUQSHIN HEALTH CENTER
PLANNED RECOVERY PROJECT CASH FLOW
(Original
(Recovery
Original Baseline Actual
Original Recovery Recovery Value Actual Value Actual Value Program)
S.NO. MONTHS Baseline Program) Acheived
Baseline Baseline Cumm. Acheived Acheived Cumm. Planned
Cumm. Value Planned Progress %
Progress %
Progress %
1 Feb-20 100,000.000 100,000.00 100,000.000 100,000.000 100,000.000 100,000.000 0.000 0.000 0.000
2 Mar-20 10,000.000 110,000.00 5,500.000 105,500.000 5,500.000 105,500.000 1.111 0.743 0.743
3 Apr-20 10,000.000 120,000.00 5,500.000 111,000.000 5,500.000 111,000.000 2.222 1.354 1.354
4 May-20 10,000.000 130,000.00 4,500.000 115,500.000 4,500.000 115,500.000 3.333 1.853 1.853
5 Jun-20 32,550.000 162,550.00 4,645.586 120,145.586 4,645.586 120,145.586 6.950 2.369 2.369
6 Jul-20 33,500.000 196,050.00 7,892.212 128,037.798 7,892.212 128,037.798 10.672 3.244 3.244
7 Aug-20 34,000.000 230,050.00 8,500.000 136,537.798 8,500.000 136,537.798 14.450 4.188 4.188
8 Sep-20 35,000.000 265,050.00 25,000.000 161,537.798 20,000.000 156,537.798 18.339 6.962 6.407
9 Oct-20 33,500.000 298,550.00 35,000.000 196,537.798 6,849.462 163,387.260 22.061 10.845 7.167
10 Nov-20 53,500.000 352,050.00 47,500.000 244,037.798 12,300.000 175,687.260 28.006 16.116 8.532
11 Dec-20 49,700.000 401,750.00 58,700.000 302,737.798 17,956.000 193,643.260 33.528 22.630 10.524
12 Jan-21 71,500.000 473,250.00 86,500.000 389,237.798 6,398.000 200,041.260 41.472 32.228 11.234
13 Feb-21 73,500.000 546,750.00 88,500.000 477,737.798 4,550.000 204,591.260 49.639 42.048 11.739
14 Mar-21 79,000.000 625,750.00 115,000.000 592,737.798 4,100.000 208,691.260 58.417 54.809 12.194
15 Apr-21 115,300.000 741,050.00 125,300.000 718,037.798 5,180.000 213,871.260 71.228 68.713 12.769
16 May-21 117,300.000 858,350.00 139,150.000 857,187.798 9,700.000 223,571.260 84.261 84.153 13.845
17 Jun-21 45,000.000 903,350.00 55,000.000 912,187.798 89.261 90.256
18 Jul-21 45,000.000 948,350.00 45,000.000 957,187.798 94.261 95.249
19 Aug-21 51,650.000 1,000,000.00 42,812.202 1,000,000.00 100.000 100.000
20
PROJECT :- MUQSHIN HEALTH CENTRE
Feb Mar Aprl May Jun July Aug Sept Oct Nov Dec Jan Feb Mar Aprl May Jun July Aug
Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act
CARPENTER 2 1 2 2 2 2 2 2 4 5 12 2 12 2 12 2 12 6 14 4 12 4 10 5 10 3 9 4 2 3 2 4 2 2 2
STEEL FITTER 1 1 1 1 1 1 1 1 8 6 10 7 10 6 10 7 10 4 12 4 10 4 8 5 8 4 6 4 1 3 4
MASONS 3 2 3 3 3 3 3 3 3 2 6 2 5 6 5 6 6 6 12 6 12 6 16 4 16 3 16 2 20 2 22 2 18 13 10
PAINTERS 5 7 7
PLUMBERS 1 1 1 1 1 1 1 1 1 2 1 2 2 2 2 2 2
ELECTRICIANS 1 1 1 1 1 1 1 1 1 4 4 2 6 6 6 6 6 6 6
SUBCONTRACTORS 2 2 1 2 3 2 2 2 2 2 2 2 2 6 8 8 10 10
HELPERS 1 1 1 1 1 1 2 3 1 5 5 5 3 5 3 5 6 5 9 7 6 5 5 5 5 3 3 5 5 5 5 5
TOTAL 11 7 11 10 10 11 10 12 18 14 33 13 34 16 34 20 33 21 48 22 43 23 44 20 47 16 44 15 40 11 45 15 46 45 42
5
5
5
5 5
4 5
T 40 5 7
6 5
O 1 3
8
T 4 2 6 8
1 2 10
A 6
5 5 12 2 10
L 5 5 6
1 1 6
1 1 12 6
6
M 16 16 2
6 5 5 6 2
A 2 6
16 5 2
N
20 3 12 2
P 3 6 9 7 HELPERS
1 10 10 10 10 2 10 6
O 2 2 SUBCONTRACTORS
2 2 7
W 3 1 8 8 5
6 5 20 22 5 ELECTRICIANS
E 2 2 6 4 6
1 1 1 3 6 1 6 6 18
R 1 1 2 3 PLUMBERS
2 2 1 3 2 3 2 2 13
1 1 1 2 2 8 6 4 5
1 1 1 1 1 1 2 1 14 2 10 PAINTERS
1 12 7 12 12 7 12 4 12 4 4 4
3 1 3 3 3 3 3 3 6 10 10 4 9 3
2 6 MASONS
1 1 1 1 1 1 1 4 5 4 4 5 4 1 4
2 1 2 2 2 2 2 2 2 2 2 3 2 3 2 2 2 2 STEEL FITTER
0 1
Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act
CARPENTER
Feb Mar Aprl May Jun July Aug Sept Oct Nov Dec Jan Feb Mar Aprl May Jun July Aug
HELPERS 1 1 1 1 1 1 2 3 1 5 5 5 3 5 3 5 6 5 9 7 6 5 5 5 5 3 3 5 5 5 5 5
SUBCONTRACTORS 2 2 1 2 3 2 2 2 2 2 2 2 2 6 8 8 10 10
ELECTRICIANS 1 1 1 1 1 1 1 1 1 4 4 2 6 6 6 6 6 6 6
PLUMBERS 1 1 1 1 1 1 1 1 1 2 1 2 2 2 2 2 2
PAINTERS 5 7 7
MASONS 3 2 3 3 3 3 3 3 3 2 6 2 5 6 5 6 6 6 12 6 12 6 16 4 16 3 16 2 20 2 22 2 18 13 10
STEEL FITTER 1 1 1 1 1 1 1 1 8 6 10 7 10 6 10 7 10 4 12 4 10 4 8 5 8 4 6 4 1 3 4
CARPENTER 2 1 2 2 2 2 2 2 4 5 12 2 12 2 12 2 12 6 14 4 12 4 10 5 10 3 9 4 2 3 2 4 2 2 2
MONTH
PROJECT :- Construction of Muqshin Health Center
ALI AMIN RAMADHAN TRADING CO. LLC
PROJECT ORGANIZATION CHART
GENERAL MANAGER
Mr. RAMDAS
GSM :- 99315548
CIVIL FOREMAN
Mr. SIKDAR ELECTRICAL TECHNICIANS
GSM :- 99242298
PLUMBING FOREMAN
Mr. ABDUL SALAM
22
HEALTH SAFETY & THE ENVIRONMENT (HSE) POLICY
Ali Amin Ramdhan Trad. Co. LLC (AART) committed to providing a safe healthy workplace and
ensuring that our business activities are conducted in a manner that protects the environment.
We believe that the health and safety of our employees, subcontractors and environment are
essential to the successful conduct and future growth of our business and are in the best interest
of our management and clients.
Our corporate Health, Safety & Environmental (HSE) policy is based on the following principles:
Identification and evaluation of all HSE hazards
or aspects and the management of their risks or
impacts to acceptable levels.
Compliance with all applicable HSE legislation.
Prevention of accidents, injuries and pollution.
Intolerance of the conditions and behaviors that
contribute to incidents or injuries.
Reduction of waste and conservation or resources.
Recording and communicating HSE performance
throughout the Company Continual improvement
of HSE performance.
The General Manager and senior management shall visibly uphold these principles and the
management and supervisory personnel at each business unit and location shall be responsible
for implementing and maintaining a compliance with these principles.
AART is committed to educate and train each employee in safe work practices and will provide
supplies, tools, equipment and to the maximum extent, a hazard-free environment to ensure all
tasks can be safely completed. No person shall be required or instructed to work in surroundings
or under conditions that are unsafe or dangerous to his or her health. Each individual employed
must take responsibility to become aware of the hazards associated with their workplace and tasks
they are to perform. Each worker is responsible to complying with applicable safety requirements,
wearing prescribed safety equipment and preventing avoiding accidents. Each employee has
a duty to report workplace conditions or practices that pose a safety hazard or threaten the
environment and to take reasonable actions to alleviate such risks.
P. RAMDAS
General Manager
Ali Amin Ramadhan Trad. Co. LLC
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH CENTER
24
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH CENTER.
1. PPE
a. Wear protective Equipment.
b. Pay Attention to Personal Hygiene.
c. Do not play in the workplace.
d. Report to your Supervisor if you notice any Unsafe Conditions.
2. Safety Measures:-
a. Before you operate any Machine ensure that the dangerous part of the
machine has been installed with a Guard.
b. Avoid Going to any area with insufficient lighting as there may be some
dangerous place which has not been provided with fencing.
c. Keep vigilant at all time & watch for Moving Cranes, Hooks or other
lifting Equipment.
d. Before Use of any Electrical Installation or Tools check the Condition of
the Electrical Cables.
e. Avoid Dragging the Cables on the Ground or allowing the cables in
contact with Water.
f. Use Electrical Tools with only Earth Leakage Circuit Breaker.
g. Use & Handle Chemicals with care.
25
Project:- Construction of Muqshin Health Center
Client:- Ministry of Health
Sponsored By:- Petroleum Development Oman
Consultant:- Simon Engineering & Partners
Contractor:- Ali Amin Ramadan Trad Co LLC
Project Contacts
S.No Name Designation Organization Contact No E-mail
1 Mr. Ramesh Naidu Sr Project Engineer Simon Eng & Partners 95634310 ramesh@sepoman.com
2 Mr. Ranjith Architetural & Civil Designer Simon Eng & Partners 79863734 ranjith@sepoman.com
3 Nouf Harib Al Alwai Architetural & Civil Designer Simon Eng & Partners nouf@sepoman.com
4 Mr. Ganesh M.H Resident Engineer Simon Eng & Partners 92003659 ganesh@sepoman.com
26
CONSTRUCTION OF MUQSHIN HEALTH CENTER
Plants & Equipment Load Schedule MAY -2021
Excavator Roller Concrete Wood Steel Electric Drilling Mixer Air Blower
DATE Rock Breaker Jcb Bobcat Tipper Compactor Vibrator Cutting Cutter Electric Hammer Hilt-T Pickup Machine Machine Auto Level Theodolite
Machine
01-05-2021 1 3 2 3 2 1 2 3 1 1 1
02-05-2021 1 3 2 3 2 1 2 3 1 1 1
03-05-2021 1 3 2 3 2 1 2 3 1 1 1
04-05-2021 1 3 2 3 2 1 2 3 1 1 1
05-05-2021 1 3 2 3 2 1 2 3 1 1 1
06-05-2021 1 3 2 3 2 1 2 3 1 1 1
07-05-2021 Friday
08-05-2021 1 3 2 3 2 1 2 3 1 1 1
09-05-2021
10-05-2021 1 3 2 3 2 1 2 3 1 1 1
11-05-2021 1 3 2 3 2 1 2 3 1 1 1
12-05-2021 1 3 2 3 2 1 2 3 1 1 1
13-05-2021 Eid Holiday
14-05-2021 Friday
15-05-2021 Eid Holiday
16-05-2021
17-05-2021 1 3 3 3 2 1 2 3 1 1 1
18-05-2021 1 3 3 3 2 1 2 3 1 1 1
19-05-2021 1 3 3 3 2 1 2 3 1 1 1
20-05-2021 1 3 3 3 2 1 2 3 1 1 1
21-05-2021 Friday
22-05-2021 1 3 3 3 2 1 2 3 1 1 1
23-05-2021 1 3 2 3 2 1 2 3 1 1 1
24-05-2021 1 3 3 3 2 1 2 3 1 1 1
25-05-2021 1 3 3 3 2 1 2 3 1 1 1
26-05-2021 1 3 3 3 2 1 2 3 1 1 1
27-05-2021 1 3 3 3 2 1 2 3 1 1 1
28-05-2021 Friday
29-05-2021 1 3 3 3 2 1 2 3 1 1 1
30-05-2021 1 3 2 3 2 1 2 3 1 1 1
31.05.2021 1 3 2 3 2 1 2 3 1 1 1
28
CONSTRUCTION OF MUQSHIN HEALTH CENTER
DAILY SITE ATTENDANCE REPORT MAY -2021
Date Project Carpenters Steel Fitter Masons Painters Electrician Plumbers Others Operators Helpers Total
Engineer
01-05-2021 1 5 4 2 5 17
02-05-2021 1 5 4 2 5 17
03-05-2021 1 5 4 2 5 17
04-05-2021 1 5 4 2 5 17
05-05-2021 1 4 4 2 4 15
06-05-2021 1 4 4 2 4 15
07-05-2021 Friday
08-05-2021 1 5 4 2 4 16
09-05-2021 1 5 4 2 5 17
10-05-2021 1 5 4 2 5 17
11-05-2021 1 4 4 2 5 16
12-05-2021 1 4 4 2 5 16
13-05-2021 Eid Holiday
14-05-2021 Friday
15-05-2021 Eid Holiday
16-05-2021 1 2 2 2 5 12
17-05-2021 1 4 4 2 5 16
18-05-2021 1 4 4 2 5 16
19-05-2021 1 4 4 2 5 16
20-05-2021 1 4 4 2 5 16
21-05-2021 Friday
22-05-2021 1 4 4 2 5 16
23-05-2021 1 4 4 2 5 16
24-05-2021 1 4 4 2 5 16
25-05-2021 1 4 4 2 5 16
26-05-2021 1 4 4 2 5 16
27-05-2021 1 4 4 2 5 16
28-05-2021 Friday
29-05-2021 1 2 2 2 3 10
30-05-2021 1 2 2 2 3 10
31.05.2021 1 4 4 2 5 16
29
ALI AMIN RAMADHAN TRAD.CO.L.L.C
PROJECT: HEALTH CENTER AT MUQSHIN MANPOWER STRENGTH
Month: MAY 2021
SL.NO CATEGORY DATE TOTAL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 25
Friday Holiday
Friday Holiday
Friday Holiday
Friday Holiday
2 Steel fitter 4 4 4 4 4 4 4 4 4 4 4 2 4 4 4 4 4 4 4 4 4 4 2 2 4 94
Eid Holiday
Eid Holiday
3 Carpenter 5 5 5 5 4 4 5 5 5 4 4 2 4 4 4 4 4 4 4 4 4 4 2 2 4 101
4 Mason 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 50
5 Plumber
6 Helper
7 Others 5 5 5 5 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 3 5 118
Total Per Day 17 17 17 17 15 15 16 17 17 16 16 12 16 16 16 16 16 16 16 16 16 16 0 10 10 16 388
18
16
Project Engineer
14
Steel fitter
12
Carpenter
10
Mason
8 Plumber
6 Helper
4 Others
2 Total Per Day
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
30
PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER
2 Water Proofing Works Ms/ Abou Nabil LLC AWC 06.06.2021 29.06.2021
31
MATERIAL APPROVAL STATUS AS ON 06/06/2021 Total MAS 70 Nos.
Project Construction of Muqshin Health Centre Total MAS Submitted 58 Nos.
Submitted for Approval (SFA) / Resubmitted for
Client Ministry of Health Approval (RSFA)
18 Nos.
35
DATE
MAS NO MATERIAL DESCRIPTION MANUFACTURER SUPPLIER STATUS
Planned Submitted Approval
PL-18 Medical Mixer Delabie-France M.H.D 30.08.2020 11.02.2021 RSFA
PL-19 Stainless Steel Sink. Blanco M.H.D 30.08.2020 11.02.2021 RSFA
PL-20 Sink Mixer Vidima Ideal Standard M.H.D 30.08.2020 11.02.2021 RSFA
PL-21 Cleaners Sink Armitage shanks M.H.D 30.08.2020 11.02.2021 RSFA
PL-22A Tissue dispenser GStyle M.H.D 30.08.2020 11.02.2021 RSFA
PL-22B Tissue dispenser Tork M.H.D 30.08.2020 11.02.2021 RSFA
PL-23 Liquid soap dispenser GStyle M.H.D 30.08.2020 11.02.2021 RSFA
PL-24 Medical soap dispenser Nofer M.H.D 30.08.2020 11.02.2021 RSFA
PL-25 Bib Taps Grohe M.H.D 30.08.2020 11.02.2021 RSFA
PL-26 Bottle Traps Veiga M.H.D 30.08.2020 11.02.2021 RSFA
PL-27 GRP Water Tank-5000 Lits Muscat Fiber Glass Muscat Fiber Glass 30.08.2020 15.09.2020 To Resubm
PL-28
(Option-2)
GRP Sectional Water Tank- 120m3 PIPECO Al Ansari Trad. 30.10.2020 24.11.2020 21.12.2020 AWC
PL-29 200 USG Polyethylene water tank. Darwish Polycon M.H.D 30.08.2020 15.09.2020 To Resubm
PL-30 Shower Tray Porcher(Ideal Standard) M.H.D 30.08.2020 11.02.2021 RSFA
PL-31 Shower Mixer Vidima Ideal Standard M.H.D 30.08.2020 11.02.2021 RSFA
PL-34 Water Cooler 16.06.2021
PL-35 Hot Water Recirculation pump- 0.5 L/S Grundfos Gulf Services 30.10.2020 24.11.2020 15.03.2021 AWC
PL-36 Booster Pump- 3lps @ 2 Bar Grundfos Gulf Services 30.10.2020 24.11.2020 15.03.2021 AWC
PL-37 Fire Fighting System 16.06.2021
36
MATERIAL APPROVAL STATUS AS ON 06/06/2021 Total MAS 53 Nos.
Project Construction of Muqshin Health Centre Total MAS Submitted 47 Nos.
Submitted for Approval (SFA) /
Client Ministry of Health Resubmitted for Approval 00 Nos.
(RSFA)
Consultant M/s. Simon Eng Consultants. Approved 0 Nos
Contractor M/s Ali Amin Ramadhan Trad. Co. LLC Approved with Com(AWC) 20 Nos
Withheld Pending 0 Nos
ELECTRICAL WORKS To Resubmit 26 Nos.
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
EL.01 PVC Conduits HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.02 PVC Conduit Accessories HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.03 G.I Conduits HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.04 G.I Conduit Accessories HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.05 G.I Boxes Spectra M/s. Tri-Spectrum Co. 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.06
PVC Insulated Single Core Wire OCI M/s. BEC / M/s. Al Khalili United En20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.06
PVC Insulated Single Core Wire NUHAS M/s. Al Khalili United Ent. 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.07 M/s. BEC / M/s. Al Khalili
XLPE Insulated Armoured Cable OCI 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio United Ent.
EL.07
XLPE Insulated Armoured Cable NUHAS M/s. Al Khalili United Ent. 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.08 Fire Proof Cable for Fire Alarm System PRYSMIAN M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
EL.09 Switches & Sockets MK M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
EL.10
Weather Proof Switches MK M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.11 13A Unswitched Twin UPS Socket ELECTRAK M/s. Al Dastoor Trad. Co. LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.12 Weather Proof Isolators Schneider M/s. Al Khalili United Ent. 20/08/2020 04/10/2020 21.12.2020 AWC
(Optio
EL.13 Lightning Protection System ABB M/s. BEC 20/08/2020 18/08/2020 21.12.2020 AWC
EL.14 300 Ltrs Glass Lined Storage Water Heater A.O Smith M/s. Al Ansari Trad. 30/10/2020 24/11/2020 14.03.2021 AWC
37
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
EL.15 Bed Head Units Statics M/s. OHI 30/10/2020 01/11/2020 21.12.2020 AWC
EL.16 Plug in Ceiling Rose MK M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
EL.17 Distribution Boards 21/05/2021
EL.18 Nurse Call System Statics M/s. OHI 30/10/2020 01/11/2020 21.12.2020 AWC
EL.19 50 Ltrs Water Heater 16.06.2021
EL.20 Fire Alarm System 16.06.2021
EL.22 Automatic Sliding Door Operator Assa Abloy M/s. International Ent. 18/08/2020 18/08/2020 26/10/2020 AWC
4x18W Recessed Light Fitting with M/s. Bahwan Building
EL.23 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP40 (Type-1) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.24 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-1E) Materials
4x18W Recessed Light Fitting with M/s. Bahwan Building
EL.25 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP54 (Type-2) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.26 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-2E) Materials
4x18W Recessed Light with Prismatic
M/s. Bahwan Building
EL.27 Diffuser and Dimmable Control Gear, IP40 Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
(Type-3)
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.28 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-3E) Materials
4x18W Recessed Light Fitting with
M/s. Bahwan Building
EL.29 Aluminium Double Parabolic Louver, IP20 Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
(Type-4)
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.30 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-4E) Materials
4x18W Recessed Light Fitting with M/s. Bahwan Building
EL.31 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP64 (Type-5) Materials
EL.32 Ditto of above + 3hrs Emergency Pack Thorn M/s. Bahwan Building 30/01/2021 22.03.2021 To Resubmit
(Type-5E) Materials
38
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
M/s. Bahwan Building
EL.33 1x16W Recessed Downlight, IP54 (Type-6) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
2x36W Recessed Light Fitting with M/s. Bahwan Building
EL.34 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP40 (Type-8) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.35 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-8E) Materials
2x36W Surface Mtd. Light with Prismatic M/s. Bahwan Building
EL.36 Thorn 30/01/2021 22.03.2021 To Resubmit
Diffuser, IP20 (Type-9) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.37 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-9E) Materials
2x36W Surface Mtd. Light with Prismatic M/s. Bahwan Building
EL.38 Thorn 30/01/2021 22.03.2021 To Resubmit
Diffuser, IP65 (Type-17) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.39 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-10E) Materials
1x7W, Recessed Down Light Night Lamp, M/s. Bahwan Building
EL.40 Thorn 30/01/2021 22.03.2021 To Resubmit
IP40 (Type-14) Materials
39
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
2x9W, Surface Mtd.External Wall Light M/s. Bahwan Building
EL.42 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-K) Materials
M/s. Bahwan Building
EL.43 2x26W Surface Mtd. Wall Light (Type-Q) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
M/s. Bahwan Building
EL.44 1x9W, X-Ray Warning Light (Type-P) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
M/s. Bahwan Building
EL.45 1x18W, Mirror Light (Type-ML) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
M/s. Bahwan Building
EL.46 1x8W, Maintained Type Exit Light Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
100W, Metal Halide Pole Light, IP54 + M/s. Bahwan Building
EL.47 Thorn 30/01/2021 22.03.2021 To Resubmit
4mtr G.I Pole (Type-T1) Materials
23W, Round Globe Gate light, IP54 (Type- M/s. Bahwan Building
EL.48 Thorn 30/01/2021 22.03.2021 To Resubmit
GL) Materials
EL.49 G.I Trunking & Cable Tray Hotex Steel
M/s. National Heaters Indus. 30/11/2020 18/08/2020 26/10/2020 AWC
Co. LLC
EL.50 LV Panels 16.06.2021
EL.51 Weatherproof Sockets Schneider M/s. Al Khalili United Ent. 31/10/2020 04/10/2020 21.12.2020 AWC
EL.52 Weatherproof Metal Clad Sockets LEWDEN M/s. Al Sabbagh Trad. LLC 31/10/2020 04/10/2020 21.12.2020 AWC
AC-01 Roof Top Package AC Units Daikin M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-02 Split AC Units Daikin M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-03 Wall Mounted Extract Fans System Air M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-04 Roof Mounted Extract Fans System Air M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-05 Air Curtains Mitsubitshi M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-06 Copper Refrigerant Pipe Lawton M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-07 Refrigerant Pipe Insulation Gulf-O-Flex M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-08 G.I Sheets Jindal, India M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-09 Thermal Insulation for HVAC Ducts Thermobreak M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-10 Acoustic Insulation Thermobreak M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-11 Hammered Aluminium sheet. Garmco M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-12 Fire Dampers Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-13 Volume Control Dampers. Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-14 Diffusers, Sand Trap Louver, Louver Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
AC-15 Sound Attenuator Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA
41
SHOP DRAWING STATUS AS ON 06/06/2021 Total shop drawings 21 Nos.
Project Muqshin Health Center Total Submitted 14 Nos.
Client Ministry of Health Submitted / Resubmitted for Approval 00 Nos
Consultant Simon Engineering & Partners Approved / Approved with comments 14 Nos.
Contractor M/s. Ali Amin Ramadhan Trad. Co. LLC For Resubmission 00 Nos.
CIVIL WORKS
DATE
SI. Approval
DRAWING TITLE DRAWING NO. Comments Approval
NO Planned Submitted Resubmitted Status
Received Received
1 Project Sign Board AARAMCO/J79/MOH-PDO/Muqshin/C-01 14.09.2019 14.09.2019 28.10.2019 AWC
3 Site Spot Levels & Excavation AARAMCO/J79/MOH-PDO/Muqshin/C-03 02.03.2020 02.03.2020 24.03.2020 AWC
4 Site Set out Marking & Excavation AARAMCO/J79/MOH-PDO/Muqshin/C-04 12.02.2020 12.02.2020 27.02.2020 AWC
5 Site Boundry Wall Plan AARAMCO/J79/MOH-PDO/Muqshin/C-05 15.04.2020 15.04.2020 08.10.2020 AWC
6 Boundry Wall Typical Sections AARAMCO/J79/MOH-PDO/Muqshin/C-06 15.04.2020 15.04.2020 08.10.2020 AWC
7 Boundry Wall Front Side Elevations-A AARAMCO/J79/MOH-PDO/Muqshin/C-07 15.04.2020 15.04.2020 08.10.2020 AWC
8 Boundry Wall Left Side Elevations-D AARAMCO/J79/MOH-PDO/Muqshin/C-08 15.04.2020 15.04.2020 08.10.2020 AWC
9 Boundry Wall Rear Side Elevations-C AARAMCO/J79/MOH-PDO/Muqshin/C-09 15.04.2020 15.04.2020 08.10.2020 AWC
10 Boundry Wall Right Side Elevations-B AARAMCO/J79/MOH-PDO/Muqshin/C-10 15.04.2020 15.04.2020 08.10.2020 AWC
11 External Site Development Interlocking & Storm Water AARAMCO/J79/MOH-PDO/Muqshin/C-11 15.12.2020 27.12.2020 03.01.2021 05.01.2021 24.02.2021 AWC
12 Ground Beam & Slab Plan AARAMCO/J79/MOH-PDO/Muqshin/C-11A 29.12.2020 30.12.2020 12.01.2021 AWC
13 Ground Beam & Slab -Sections. AARAMCO/J79/MOH-PDO/Muqshin/C-11B 29.12.2020 30.12.2020 12.01.2021 AWC
14 Boundary Wall Rear Side Elevation-C (Setback Location) AARAMCO/J79/MOH-PDO/Muqshin/C-12 18.02.2021 21.02.2021 17.03.2021 23.03.2021 04.04.2021 AWC
15 Roof Finishes Layout AARAMCO/J79/MOH-PDO/Muqshin/C-13 16.06.2021
16 Schedule of Doors & Windows. AARAMCO/J79/MOH-PDO/Muqshin/C-14 16.06.2021
17 Layout of Floor & Wall Finishes. AARAMCO/J79/MOH-PDO/Muqshin/C-15 16.06.2021
18 False Ceiling Layout AARAMCO/J79/MOH-PDO/Muqshin/C-16 16.06.2021
19 Built in Furniture AARAMCO/J79/MOH-PDO/Muqshin/C-17 16.06.2021
20 Layout for Guard Rail & Corner Guards. AARAMCO/J79/MOH-PDO/Muqshin/C-18 16.06.2021
21 Layout for Cubicle Curtains. AARAMCO/J79/MOH-PDO/Muqshin/C-19 16.06.2021
42
SHOP DRAWING STATUS AS ON 06/06/2021 Total shop drawings: 09 Nos
Contractor M/s. Ali Amin Ramadhan Trad. Co. LLC For Resubmission 00 Nos
MECHANICAL WORKS
DATE
SI. Approval
DRAWING TITLE DRAWING NO. Comments Approval
NO Planned Submitted Resubmitted Status
Received Received
Internal & External Drainage Services Layout - Health
1 AARAMCO/J79/MOH-PDO/Muqshin/PL-01(R3) 30.09.2020 15.09.2020 01/11/2020 03.01.2021 17.01.2021 AWC
Center, Maternity Building & Guard Room
Roof Drainage Layout - Health Center & Maternity
2 AARAMCO/J79/MOH-PDO/Muqshin/PL-02 16.06.2021
Building
Ground Floor Water Supply Layout - Health Center &
3 AARAMCO/J79/MOH-PDO/Muqshin/PL-03 16.06.2021
Maternity Building
4 Roof Water Supply- Health Center & Maternity Building AARAMCO/J79/MOH-PDO/Muqshin/PL-04 16.06.2021
43
SHOP DRAWING STATUS AS ON 06/06/2021 Total shop drawings: 13 Nos.
Contractor : M/s. Ali Amin Ramadhan Trad. Co. LLC For Resubmission 02 Nos.
ELECTRICAL WORKS
DATE
SI.
DRAWING TITLE DRAWING NO. Comments Approval Approval Status
NO Planned Submitted Resubmitted
Received Received
For
1 Cutouts In Floor Slab for all Cable Entries from External Areas. AARAMCO/J79/MOH-PDO/Muqshin/EL-01A 30/10/2020 11.02.2021 23.02.2021
Resubmission
2 Site Plan - External Electrical Lighting & Power Layout AARAMCO/J79/MOH-PDO/Muqshin/EL-02 16.06.2021
Ground Floor Lighting Layout - Health Centre, Maternity Unit &
3
Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-03 16.06.2021
Ground Floor Small Power & SMATV Layout - Health Centre,
4
Maternity Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-04 16.06.2021
5 Ground Floor UPS Power Layout - Health Centre & Maternity Unit AARAMCO/J79/MOH-PDO/Muqshin/EL-05 16.06.2021
Ground Floor Structured Cabling Layout - Health Centre, Maternity
6
Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-06 16.06.2021
Ground Floor Nurse Call System Layout - Health Centre & Maternity
7
Unit
AARAMCO/J79/MOH-PDO/Muqshin/EL-07 16.06.2021
Roof Electrical Services Layout - Health Centre, Maternity Unit &
8
Guard House Building
AARAMCO/J79/MOH-PDO/Muqshin/EL-08 16.06.2021
Roof Lightning Protection Layout - Health Centre, Maternity Unit & For
9 AARAMCO/J79/MOH-PDO/Muqshin/EL-09 23.11.2020 24/11/2020 07.01.2021
Guard House Resubmission
10 DB Schedule - Health Centre, Maternity Unit & Guard House AARAMCO/J79/MOH-PDO/Muqshin/EL-10 16.06.2021
Main Power Supply Schematic Diagram - Health Centre, Maternity
11
Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-11 16.06.2021
Ground Floor Fire Alarm System Layout - Health Centre, Maternity
12
Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-12 16.06.2021
44
SHOP DRAWING STATUS AS ON 06/06/2021
Contractor : M/s. Ali Amin Ramadhan Trad. Co. LLC Approved 00 Nos.
HVAC WORKS
DATE
SI.
DRAWING TITLE DRAWING NO. Approval Status
NO Comments Approval
Planned Submitted Resubmitted
Received Received
Ground Floor HVAC Layout - Health Centre, Maternity Unit & Guard
1
House Building
AARAMCO/J79/MOH-PDO/Muqshin/AC-01 16.06.2021
Roof HVAC Layout - Health Centre, Maternity Unit & Guard House
2
Building
AARAMCO/J79/MOH-PDO/Muqshin/AC-02 16.06.2021
45
PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER
46
PROJECT: - CONSTRUCTION OF MUQSHIN
HEALTH CENTRE
INVOICING STATUS
AMOUNT CERTIFIED
DATE OF PAYMENT
SI.NO. INVOICE DETAILS CLAIMED AMOUNT
SUBMISSION STATUS
(R.O) (R.O )
47
Project:- Construction of Proposed Muqshin Health Center.
48
Project:- Construction of Proposed Muqshin Health Center.
49
Project:- Construction of Proposed Muqshin Health Center.
50
Project:- Construction of Proposed Muqshin Health Center.
51
Project:- Construction of Proposed Muqshin Health Center.
52
Project:- Construction of Proposed Muqshin Health Center.
53
Project:- Construction of Proposed Muqshin Health Center.
54
Project:- Construction of Proposed Muqshin Health Center.
55
Project:- Construction of Proposed Muqshin Health Center.
Main Health Center Building Plinth Beam Steel works checking & Inspection.
56
Project:- Construction of Proposed Muqshin Health Center.
57
Project:- Construction of Proposed Muqshin Health Center.
58