CONSTRUCTION OF

MUQSHIN HEALTH CENTER


FOR THE MONTH OF 16 JULY 2015 TO 15 AUGUST 2015

PROGRESS REPORT – 15

FOR THE MONTH OF MAY -2021


CLIENT : MINISTRY OF HEALTH
CONSULTANT : AZRI ARCHITECTS
CONTRACTOR : ALI AMIN RAMADHAN TRADING CO. LLC
HEALTH CENTER AT MUQSHIN
INDEX
SI.NO. DESCRIPTION PAGE NO.

1 Introduction 1

2 Contract Details & Bonds 2

3 Project Progress Overview 3-11

4 Construction Program 12-18

5 Project Progress S-Curve 19

5 Project Cash Flow 20


6 Labor Histogram 21

7 Organization Chart 22

8 HSE 23-25

9 Project Contacts 26

10 Site Visitors 27

11 Plant & Machinery Report 28

12 Manpower Status 29-30

13 Proposed Subcontractors 31

14 Material Approval Status 32-41

15 Shop Drawing Approval Status 42-45

16 Approved Samples 46

17 Invoicing Status 47

18 Progress Photographs 48- 59


PROJECT:
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH
CENTER

Brief Description :- The above project was awarded to M/S Ali Amin Ramdhan Trad Co
for a total value of R.O 1,000,000.000 (One Million Only) & duration of 18 months.
The Project is funded by The Petroleum Development Oman (P.D.O).
The Project is Under the Supervision of the Consultant Ms/ Simon Engineering &
Partners LLC & the Directorate General of Projects & Engineering Affairs –Ministry of
Health.
The project consists of the following area as mentioned below.

Project Description: - The project consists of a Main Health Center Building &
Maternity Building with Various Health Care Facilities. Including also the below.

1. Main Health Center Building


a. Civil – Structural & Architectural Works
b. Electrical Works including Fire Alarm System, Nurse Call System, BHU,
Structured Cabling Works & Lightning Protection System etc.
c. HVAC – Centralized Ducted Package Unit System
d. Mechanical – Drainage, Water Supply & Fire Fighting System

2. Maternity Unit
a. Civil – Structural & Architectural Works
b. Electrical Works including Fire Alarm System, Nurse Call System, BHU,
Structured Cabling Works & Lightning Protection System etc.
c. HVAC – Centralized Ducted Package Unit System
d. Mechanical – Drainage, Water Supply & Fire Fighting System

3. Guard Room
a. Civil – Structural & Architectural Works
b. Electrical Works including Fire Alarm System, Structured Cabling Works &
Lightning Protection System etc.
c. HVAC
d. Mechanical – Drainage, Water Supply & Fire Fighting System

4. External Boundary Wall


5. External Works & Services

1
[Type text]
HYHHH
CONSTRUCTION OF MUQSHIN HEALTH CENTER

General Project Detail


1 Project Construction of Muqshin Health Center
2 Client Ministry of Health
3 Sponsored By Petroleum Development Oman
3 Consultant Simon Engineering & Partners LLC
4 Contractor Ali Amin Ramadhan Trading Co. LLC

Contract Details
1 Mobilization Start Date 15.01.2020
2 Mobilization Complete 15.02.2020
3 Construction start Date 16.02.2020
4 Completion of Project 15.08.2021
5 Project Duration 18 Months
6 Completion of Maintenance 15.08.2022

Financial Summary
S.No. DESCRIPTION AMOUNT IN RIYAL OMANI
1 Contract Amount 1,000,000.000
2 Preliminaries & General Requirements Included
3 Provisional Sum Nil
4 Health Center Building 500,676.140
5 Maternity Building 170,949.220
6 Guard House 12,934.540
7 Road Works 5,129.300
8 External Works 251,776.750
9. External Services. 52,235.100
10. Water Tank 6,299.560

Bond & Insurance


S.No. DESCRIPTION BOND NO. AMOUNT VALIDITY
1 Performance Bond No. LG190378 R.O 50,000.000 30.09.2022
2 Advance Payment No. LG190377 R.O 100,000.00 30.06.2021
3 Project Insurance Policy No. No:-91895194470642 R.0 1,000,000.0 30.06.2022

Ali Amin Ramadhan Trading Company

2
PROJECT:-CONSTRUCTION OF MUQSHIN HEALTH CENTER
PROJECT CUMULATIVE WORK PROGRESS as of 31-05-2021
As PER CASH FLOW CHART.

Works Commencement Date : 16/02/2020

Project Completion Date : 15/08/2021

Total Project Duration : 18 Months (547 Days)

Present Date : 31/05/2021

Total Days Elapsed : 470 Days

Elapsed Time (%) : 85.92 %

Total Contract Value (A) : OMR 1,000,000.000

Received Advance Payment (B) : OMR 98,800.000

Contract Value less Advance Payment (C) : OMR 901,200.000

Cumulative Targeted / Planned Work Value (D) : OMR 857,187.798

Cumulative Achieved / Earned Work Value (E) : OMR 223,571.260

% of Targeted / Planned Work Progress (F) : ((D - B) / C) * 100 = 84.153%

% of Achieved / Earned Work Progress (G) : ((E - B) / C) * 100 = 13.845 %

JOB DESCRIPTION Percentage Percentage REMARKS


S.NO
Programmed Achieved (DELAY %)

Main Health Center + Maternity Building + Guard


House + Compound Wall + External Underground
1. 84.153 % 13.845 % 70.308 %
Holding Tank + GRP Water Tank.
(As per Cash Flow)

3
PROJECT:-CONSTRUCTION OF MUQSHIN HEALTH CENTER

PROJECT CUMULATIVE WORK PROGRESS as of 31-05-2021


AS PER TIME SCHEDULE.

Works Commencement Date : 16/02/2020

Project Completion Date : 15/08/2021

Total Project Duration : 18 Months (547 Days)

Present Date : 31/05/2021

Total Days Elapsed : 470 Days

Elapsed Time (%) : 85.92 %

Delay : - 85.92 % - 286/547 *100= 33.63 %

JOB DESCRIPTION
S.NO Delay as per the Time Schedule.

Main Health Center + Maternity Building + Guard


House + Compound Wall + External Underground
2. 33.63 %
Holding Tank + GRP Water Tank.
(As per Time Schedule)

4
Project:- Muqshin Health Center.
Progress As Per Time Schedule
Project Start Date 16.02.2019
Project Completion Date 15.08.2021
Project Duration 547 days
Current Date 31.05.2021
Total Days Elapsed as per Planned 470
Total Actutal Progress Achieved in Days 286
Delay as per Time Schedule. 33.638%

(Total days Elapsed as per Planned Schedule=470 days)

470
0.00 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00 500.00

(Delay:- 33.63 %)

286
0.00 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00 500.00

(Total Actual Progress Achieved in days=286)

4A
PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER
WORK STATUS as of 31-05-2021 (Main Health Center, Maternity Building, GUARD
HOUSE, COMPOUND WALL, HOLDING TANK & EXTERNAL GRP WATER TANK)

Baseline Variance Variance


Task Baseline Actual
No. Task Name Finish Actual Finish between between
ID Start Date Start
Date Start Dates Finish Dates

1 2 Balance Mobilization Works 15/01/2020 15/02/2020 16/02/2020 29/02/2020 30 Days 14 Days


Excavation & Breaking out Hard
Rock for the foundations Including
2 8 16/02/2020 02/06/2020 16/03/2020 02/06/2020 Nil Nil
Disposal of all Material (Health
Centre + Maternity + Guard House)
Plate Load Test & Test Report 3 Days in
3 9 03/06/2020 12/07/2020 05/07/2020 08/07/2020 33 Days
Submission & Approval Advance
Formation Layer 150mm Filling,
4 10 13/07/2020 03/08/2020 20/07/2020 03/08/2020 8 Days Nil
Leveling, Compaction & Soil Test
5 11 Foundation PCC 04/08/2020 27/08/2020 25/08/2020 29/08/2020 22 days 3 Days
2 Days in
6 12 Curing for the foundation PCC 28/08/2020 03/09/2020 26/08/2020 08/09/2020 6 Days
Advance
Main Bldg. - Footing steel & foam
7 13 04/09/2020 21/09/2020 04/09/2020 01/10/2020 Nil 11 Days
work & concrete
2 Days in
8 14 Main Bldg. - Curing for the footings 22/09/2020 28/09/2020 20/09/2020 08/10/2020 10 Days
Advance
Main Bldg. - Stub column
9 15 22/09/2020 03/10/2020 03/10/2020 21/10/2020 12 Days 18 Days
reinforcement, form work & concrete

10 16 Main Bldg. - Curing of Stub Column 04/10/2020 10/10/2020 16/10/2020 28/10/2020 12 Days 18 Days

Main Bldg. - External Perimeter Solid


11 17 04/10/2020 05/10/2020 22/10/2020 23/10/2020 18 Days 18 Days
Block Work PCC

5
Main Bldg. - Curing for External
12 18 06/10/2020 08/10/2020 23/10/2020 01/11/2020 18 Days 25 Days
Solid Block Work PCC
Main Bldg. - External Perimeter Solid
13 19 06/10/2020 17/10/2020 25/10/2020 12/11/2020 19 Days 26 Days
Block Work

14 20 Provision of Apron Wall Cutout 11/10/2020 17/10/2020

Curing of Substructure Solid Block


15 21 18/10/2020 20/10/2020 26/10/2020 19/11/2020 8 Days 30 Days
Work
Coal Tar Epoxy Coating - Solid Block
16 22 21/10/2020 24/10/2020 10/11/2020 22/11/2020 20 Days 29 Days
Work
Backfilling & Compaction till the
17 23 25/10/2020 11/11/2020 28/11/2020 10/01/2021 34 Days 60 days
bottom of Plinth Beam PCC
Internal Drainage piping Works &
18 24 12/11/2020 18/11/2020 13.02.2021 15.03.2021 94 days 117 days
cable ducting provisions
19 25 Plinth Beam PCC Works 19/11/2020 20/11/2020 16/03/2021 04/04/2021 117 days 135 days
Maternity-
Completed
Rebar & Foam
27,28, Plinth Beam Steel & foam work, MEP
29
21/11/2021 05/12/2020 05/04/2021 works. 135 days
Concealed work, Concrete works.
Health Center-
Rebar in
progress.
Delayed 168
20 32 Backfill till the Bottom of Floor Slab 15/12/2020 26/12/2020 Not Started
days
Electrical Floor Conduiting Works &
Delayed 156
21 33 Drainage Piping Including Floor Trap 27.12.2020 02.01.2021 Not Started
days
Provision Works
Delayed 149
22 34 Anti Termite Treatment. 03.01.2021 03.01.2021 Not Started
days
Delayed 148
23 35 Floor Slab Reinforcement & concrete. 04.01.2021 09.01.2021 Not Started
days.
Delayed 142
24 39 Ground Floor Column steel works. 10.01.2021 11.01.2021 Not Started
days.

6
Delayed 140
25 40 Starter Column marking & Concrete 12.01.2021 13.01.2021 Not Started
days
Ground floor Column Foam work & Delayed 138
26 41 14.01.2021 27.01.2021 Not Started
Concrete. days.
Ground floor slab foam work & Delayed 124
27 43 28.01.2021 03.03.2021 Not Started
Reinforcement. days
Concealed conduiting in roof slab for Delayed 109
28 44 12.02.2021 03.03.2021 Not Started
electric & HVAC works. days
Delayed 89
29 45 Ground floor roof slab concrete 04.03.2021 06.03.2021 Not started
days
Roof slab curing & deshuttering Delayed 86
30 46,47 07.03.2021 25.03.2021 Not started
works. days.
Plant room Column & roof slab foam Delayed 67
31 48,49 26.03.2021 13.04.2021 Not started
work & concrete works. days
Roof parapet foam work Delayed 48
32 50 14.04.2021 27.04.2021 Not started
reinforcement & concrete. days
Ground floor block work till lintel Delayed 67
33 54 26.03.2021 22.04.2021 Not started
bottom. days
Ground floor Lintel Reinforcement Delayed 39
34 55 23.04.2021 29.04.2021 Not started
shuttering & Concrete. days
35 56 Ground floor Block work above lintel 30.04.2021 06.05.2021 Not started Delayed 32 day
Provision of all Concealed wall Delayed 39
36 57 23.04.2021 22.05.2021 Not started
electrical, ELV system, data. days
Provision of all concealed UPVC soil Delayed 39
37 58 23.04.2021 22.05.2021 Not started
waste vent piping works days
Provision of all concealed & main Delayed 39
38 59 23.04.2021 22.05.2021 Not started
copper piping for water supply. days
Provision for Wall Cut out Openings Not started
Delayed 32
39 60 including Lintel above it for Block 30/04.2021 09.05.2021
days
work for HVAC Ducts
Not started Delayed 25
40 61 Installation of Steel Door Frames. 07.05.2021 16.05.2021
days
Not started Delayed 15
41 62 Internal Wall Plaster. 17.05.2021 15.06.2021
days
Not started Delayed 15
42 63 X-Ray Lead Lining & plastering 17.05.2021 25.06.2021
days
7
43 64 HVAC Main Ducting & branches. 17.05.2021 25.06.2021 Not started Delayed 15 days
44 65 Above False ceiling GI Trunking. 17.05.2021 05.06.2021 Not started Delayed 15 days
45 69 Roof parapet Wall internal plaster. 05.05.2021 16.05.2021 Not started Delayed 27 days
"Casting of all foundation plinths for Not started
46 70 17.05.2021 21.05.2021 Delayed 15 days
HVAC package units, water tanks
47 71 Roof
etc." Claustra Block Enclosure 22.05.2021 05.06.2021 Not started Delayed 10 days
Roof Plant Room Block work & Not started
48 72 22.05.2021 05.06.2021 Delayed 10 days
Plaster Finishes
49 109 External Wall Plastering 17.05.2021 10.06.2021 Not started Delayed 15 days
External Drainage works including Not started
50 110 27.05.2021 20.06.2021 Delayed 5 days
Manholes & Gully Traps.
External Main cable duct pipe, sand Not started
51 111 27.05.2021 20.06.2021 Delayed 5 days
bed, caution tape, backfilling.
External Fire Fighting, Hydrant, Fire Not started
52 112 27.05.2021 20.06.2021 Delayed 5 days
Pump Installation works
External Telephone data ducting, Not started
53 113 27.05.2021 20.06.2021 Delayed 5 days.
Encasement, backfilling.
Excavation for Boundary Wall
54 136 23/08/2020 02/09/2020 23/08/2020 02/09/2020 Nil Nil
(Phase-1) Plot Ref. Pt.-2 to Ref Pt.-5
Phase-1 Boundary Wall – Foundation In Progress
55 138 13/09/2020 19/09/2020 28/10/2020 45 Days 255 days
PCC 93% Complete
Phase-1 Boundary Wall – Foundation
In Progress
56 140 Form Work, Reinforcement & 20/09/2020 24/10/2020 10/11/2020 51 Days 220 days
87% Complete
Concrete
Phase-1 Boundary Wall –
Substructure RCC Wall & Column In Progress
57 142 25/10/2020 28/11/2020 07.12.2020 43 days 245 days
Form Work, Reinforcement Work & 93 % Complete
Concrete Work
Phase-1 Boundary Wall – Super
Delayed 184
58 145 Structure Column - Form & 29/11/2020 07/01/2021 Not Started
days
Reinforcement Work & Concrete (
Phase-1 Boundary wall super Not Started Delayed 144
59 146 08.01.2021 06.02.2021
structure block work + Top Coaping. days
Not Started Delayed 114
60 147 Phase-1 Boundary Wall plastering. 07.02.2021 18.03.2021
days

8
Excavation for Boundary Wall In Progress
61 147 03/09/2020 27/09/2020 12/09/2020 10 Days 245 days
(Phase-2) Plot Ref. Pt.-5 to Ref Pt.-2 60% Complete
Phase-2 Boundary Wall – Foundation In Progress
62 149 13/10/2020 26/10/2020 22/12/2020 70 Days 161 days
PCC 50% Complete
Phase-2 Boundary Wall – Foundation
In Progress
63 152 Form Work, Reinforcement & 27/10/2020 15/12/2020 08.11.2020 12 days. 154 days
31% Complete.
Concrete
Phase-2 Boundary wall Substructure In Progress
64 154 16/12/2020 29/01//2021 09/01/2021 24 days 122 days
RCC Columns 26% Complete
In Progress
65 155 Substructure Solid Block work. 30.01.2021 21.02.2021 31.01.2021 2 day 84 days
26% Complete
Phase-2 Boundary wall-Super Not Started Delayed 99
66 156 22.02.2021 12.04.2021
structure RCC Columns days
Phase-2 Boundary wall-Super Not Started Delayed 49
67 157 13.04.2021 01.06.2021
structure Block work & Coaping. days
17/10/2020
(Holding Tank
Excavation for Holding Tank & 1 Day in 1 Day in
68 161 28/09/2020 18/10/2020 27/09/2020 Excavation
External GRP Water Tank Advance Advance
Upto 4mtr
Depth)
(18/01/21 )
Holding Tank & GRP Water Tank –
69 162 19/10/2020 28/10/2020 27/09/2020 Completed only 188 days
Soil Leveling & Compaction
GRP Tank Rm
162
Holding Tank & External GRP Tank Delayed 215
70 to 29.10.2020 23.12.2020 Not Started
foundations. days
166
167
Water Tank Works & RCC Holding Delayed 166
71 to 17.12.2020 07.05.2021 Not Started
Tank Top Cover Slab days
179

9
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH CENTER.
LIST OF ACTIVITIES PLANNED FOR THE Month of JUNE -2021 (Main Health Center, Maternity
Building, GUARD HOUSE, COMPOUND WALL, HOLDING TANK & EXTERNAL GRP TANK)

Variance Variance
Baseline
Task Baseline between between
No. Task Name Finish Actual Start Actual Finish
ID Start Date Start Finish
Date
Dates Dates

1 27 Balance Plinth Beam Steel & Form Work 21/11/2020 02/12/2020

All Electrical, Drainage, Water Supply,


2 28 HVAC Drain Concealed Provisions in 26/11/2020 02/12/2020
Plinth Beam
Plinth Beam Concrete Activity Maternity
3 29 03/12/2020 05/12/2020
Health Center & Guard Room.

4 30 Plinth beam curing work 06/12/2020 12/12/2020

Balance - Phase-1 Compound Wall –


5 138 13/09/2020 19/09/2020
Foundation PCC
6 139 Phase-1 Compound Wall - PCC Curing 20/09/2020 26/09/2020

Phase-1 Compound Wall – Foundation


7 140 20/09/2020 24/10/2020
Form Work, Reinforcement & Concrete
Phase-1 Compound Wall – Foundation
8 141 25/10/2020 31/10/2020
Curing
Phase-1 Compound Wall – Substructure
9 142 RCC Wall & Column Form Work, 25/10/2020 28/11/2020
Reinforcement Work & Concrete Work
10
Phase-1 Compound Wall – Substructure
10 143 29/11/2020 05/12/2020
RCC Column Curing
Phase-2 Compound Wall – Excavation
11 147 03/09/2020 27/09/2020
Works
Balance- Phase-2 Compound Wall – Soil
12 148 28/09/2020 12/10/2020
Leveling & Compaction
Phase-2 Compound Wall – Foundation
13 149 13/10/2020 26/10/2020
PCC

14 150 Phase-2 Compound Wall – PCC Curing 27/10/2020 02/11/2020

Phase-2 Compound Wall – Foundation


15 151 27/10/2020 15/12/2020
Form Work, Reinforcement & Concrete

Phase-2 Compound Wall – Foundation


16 152 16/12/2020 22/12/2020
Curing

Holding Tank– Soil Leveling &


17 162 19/10/2020 28/10/2020
Compaction
Holding Tank & GRP Water Tank –
18 163 29/10/2020 09/11/2020
Foundation PCC
Holding Tank & GRP Water Tank – PCC
19 164 10/11/2020 16/11/2020
Curing
Holding Tank & GRP Water Tank –
20 165 Foundation Foam work, Reinforcement & 17/11/2020 16/12/2020
Concrete
Holding Tank & GRP Water Tank –
21 166 17/12/2020 23/12/2020
Foundation Curing

Holding Tank:- RCC -Walls (Foam work


22 167 24/12/2020 16/02/2020
Reinforcement & Concrete)

11
MUQSHIN HEALTH CENTER
120 PROGRAMMED S-CURVE
110
(Original Baseline Program) Planned Progress %
100

(Recovery Program) Planned Progress %


90
PROGRESS %

80
Actual Acheived Progress %

70

60

50

40

30

20

10

0
Aug-20

Nov-20

Aug-21
Apr-20

Apr-21
Feb-20

Mar-20

Jun-20

Jul-20

Sep-20

Oct-20

Dec-20

Jan-21

Feb-21

Mar-21

Jun-21

Jul-21
May-20

May-21
Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21
(Original Baseline Program) Planned Progress % 0.000 1.111 2.222 3.333 6.950 10.672 14.450 18.339 22.061 28.006 33.528 41.472 49.639 58.417 71.228 84.261 89.261 94.261 100.000
(Recovery Program) Planned Progress % 0.000 0.743 1.354 1.853 2.369 3.244 4.188 6.962 10.845 16.116 22.630 32.228 42.048 54.809 68.713 84.153 90.256 95.249 100.000
Actual Acheived Progress % 0.000 0.743 1.354 1.853 2.369 3.244 4.188 6.407 7.167 8.532 10.524 11.234 11.739 12.194 12.769 13.845

MONTH

19
PROJECT :- MUQSHIN HEALTH CENTER
PLANNED RECOVERY PROJECT CASH FLOW
(Original
(Recovery
Original Baseline Actual
Original Recovery Recovery Value Actual Value Actual Value Program)
S.NO. MONTHS Baseline Program) Acheived
Baseline Baseline Cumm. Acheived Acheived Cumm. Planned
Cumm. Value Planned Progress %
Progress %
Progress %
1 Feb-20 100,000.000 100,000.00 100,000.000 100,000.000 100,000.000 100,000.000 0.000 0.000 0.000
2 Mar-20 10,000.000 110,000.00 5,500.000 105,500.000 5,500.000 105,500.000 1.111 0.743 0.743
3 Apr-20 10,000.000 120,000.00 5,500.000 111,000.000 5,500.000 111,000.000 2.222 1.354 1.354
4 May-20 10,000.000 130,000.00 4,500.000 115,500.000 4,500.000 115,500.000 3.333 1.853 1.853
5 Jun-20 32,550.000 162,550.00 4,645.586 120,145.586 4,645.586 120,145.586 6.950 2.369 2.369
6 Jul-20 33,500.000 196,050.00 7,892.212 128,037.798 7,892.212 128,037.798 10.672 3.244 3.244
7 Aug-20 34,000.000 230,050.00 8,500.000 136,537.798 8,500.000 136,537.798 14.450 4.188 4.188
8 Sep-20 35,000.000 265,050.00 25,000.000 161,537.798 20,000.000 156,537.798 18.339 6.962 6.407
9 Oct-20 33,500.000 298,550.00 35,000.000 196,537.798 6,849.462 163,387.260 22.061 10.845 7.167
10 Nov-20 53,500.000 352,050.00 47,500.000 244,037.798 12,300.000 175,687.260 28.006 16.116 8.532
11 Dec-20 49,700.000 401,750.00 58,700.000 302,737.798 17,956.000 193,643.260 33.528 22.630 10.524
12 Jan-21 71,500.000 473,250.00 86,500.000 389,237.798 6,398.000 200,041.260 41.472 32.228 11.234
13 Feb-21 73,500.000 546,750.00 88,500.000 477,737.798 4,550.000 204,591.260 49.639 42.048 11.739
14 Mar-21 79,000.000 625,750.00 115,000.000 592,737.798 4,100.000 208,691.260 58.417 54.809 12.194
15 Apr-21 115,300.000 741,050.00 125,300.000 718,037.798 5,180.000 213,871.260 71.228 68.713 12.769
16 May-21 117,300.000 858,350.00 139,150.000 857,187.798 9,700.000 223,571.260 84.261 84.153 13.845
17 Jun-21 45,000.000 903,350.00 55,000.000 912,187.798 89.261 90.256
18 Jul-21 45,000.000 948,350.00 45,000.000 957,187.798 94.261 95.249
19 Aug-21 51,650.000 1,000,000.00 42,812.202 1,000,000.00 100.000 100.000

20
PROJECT :- MUQSHIN HEALTH CENTRE

LABOUR HISTOGRAM - PLANNED Vs ACTUAL

Feb Mar Aprl May Jun July Aug Sept Oct Nov Dec Jan Feb Mar Aprl May Jun July Aug
Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act
CARPENTER 2 1 2 2 2 2 2 2 4 5 12 2 12 2 12 2 12 6 14 4 12 4 10 5 10 3 9 4 2 3 2 4 2 2 2
STEEL FITTER 1 1 1 1 1 1 1 1 8 6 10 7 10 6 10 7 10 4 12 4 10 4 8 5 8 4 6 4 1 3 4
MASONS 3 2 3 3 3 3 3 3 3 2 6 2 5 6 5 6 6 6 12 6 12 6 16 4 16 3 16 2 20 2 22 2 18 13 10
PAINTERS 5 7 7
PLUMBERS 1 1 1 1 1 1 1 1 1 2 1 2 2 2 2 2 2
ELECTRICIANS 1 1 1 1 1 1 1 1 1 4 4 2 6 6 6 6 6 6 6
SUBCONTRACTORS 2 2 1 2 3 2 2 2 2 2 2 2 2 6 8 8 10 10
HELPERS 1 1 1 1 1 1 2 3 1 5 5 5 3 5 3 5 6 5 9 7 6 5 5 5 5 3 3 5 5 5 5 5
TOTAL 11 7 11 10 10 11 10 12 18 14 33 13 34 16 34 20 33 21 48 22 43 23 44 20 47 16 44 15 40 11 45 15 46 45 42

LABOUR HISTOGRAM - PLANNED Vs ACTUAL

5
5
5
5 5
4 5
T 40 5 7
6 5
O 1 3
8
T 4 2 6 8
1 2 10
A 6
5 5 12 2 10
L 5 5 6
1 1 6
1 1 12 6
6
M 16 16 2
6 5 5 6 2
A 2 6
16 5 2
N
20 3 12 2
P 3 6 9 7 HELPERS
1 10 10 10 10 2 10 6
O 2 2 SUBCONTRACTORS
2 2 7
W 3 1 8 8 5
6 5 20 22 5 ELECTRICIANS
E 2 2 6 4 6
1 1 1 3 6 1 6 6 18
R 1 1 2 3 PLUMBERS
2 2 1 3 2 3 2 2 13
1 1 1 2 2 8 6 4 5
1 1 1 1 1 1 2 1 14 2 10 PAINTERS
1 12 7 12 12 7 12 4 12 4 4 4
3 1 3 3 3 3 3 3 6 10 10 4 9 3
2 6 MASONS
1 1 1 1 1 1 1 4 5 4 4 5 4 1 4
2 1 2 2 2 2 2 2 2 2 2 3 2 3 2 2 2 2 STEEL FITTER
0 1
Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act Plan Act
CARPENTER
Feb Mar Aprl May Jun July Aug Sept Oct Nov Dec Jan Feb Mar Aprl May Jun July Aug
HELPERS 1 1 1 1 1 1 2 3 1 5 5 5 3 5 3 5 6 5 9 7 6 5 5 5 5 3 3 5 5 5 5 5
SUBCONTRACTORS 2 2 1 2 3 2 2 2 2 2 2 2 2 6 8 8 10 10
ELECTRICIANS 1 1 1 1 1 1 1 1 1 4 4 2 6 6 6 6 6 6 6
PLUMBERS 1 1 1 1 1 1 1 1 1 2 1 2 2 2 2 2 2
PAINTERS 5 7 7
MASONS 3 2 3 3 3 3 3 3 3 2 6 2 5 6 5 6 6 6 12 6 12 6 16 4 16 3 16 2 20 2 22 2 18 13 10
STEEL FITTER 1 1 1 1 1 1 1 1 8 6 10 7 10 6 10 7 10 4 12 4 10 4 8 5 8 4 6 4 1 3 4
CARPENTER 2 1 2 2 2 2 2 2 4 5 12 2 12 2 12 2 12 6 14 4 12 4 10 5 10 3 9 4 2 3 2 4 2 2 2
MONTH
PROJECT :- Construction of Muqshin Health Center
ALI AMIN RAMADHAN TRADING CO. LLC
PROJECT ORGANIZATION CHART

GENERAL MANAGER
Mr. RAMDAS
GSM :- 99315548

PURCHASE / ACCOUNTS PROJECT MANAGER MEP MANAGER


Mr. HARIHARAN Mr. VICKY Mr. ABISHEK
GSM :- 92830203 GSM :- 92830010 GSM :- 92830014

HVAC, FIRE FIGHTING


SITE ENGINEER ELECTRICAL SUPERVISOR
Mr. Martin Tom Mr. VIJAYAN
SUB CONTRACTORS
GSM :- 96930379 GSM :- 99504201

CIVIL FOREMAN
Mr. SIKDAR ELECTRICAL TECHNICIANS
GSM :- 99242298

PLUMBING FOREMAN
Mr. ABDUL SALAM

CIVIL & PLUMBING TECHNICIANS

22
HEALTH SAFETY & THE ENVIRONMENT (HSE) POLICY

Ali Amin Ramdhan Trad. Co. LLC (AART) committed to providing a safe healthy workplace and
ensuring that our business activities are conducted in a manner that protects the environment.
We believe that the health and safety of our employees, subcontractors and environment are
essential to the successful conduct and future growth of our business and are in the best interest
of our management and clients.

Our corporate Health, Safety & Environmental (HSE) policy is based on the following principles:


Identification and evaluation of all HSE hazards
or aspects and the management of their risks or
impacts to acceptable levels.

Compliance with all applicable HSE legislation.

Prevention of accidents, injuries and pollution.

Intolerance of the conditions and behaviors that
contribute to incidents or injuries.

Reduction of waste and conservation or resources.

Recording and communicating HSE performance
throughout the Company Continual improvement
of HSE performance.

The General Manager and senior management shall visibly uphold these principles and the
management and supervisory personnel at each business unit and location shall be responsible
for implementing and maintaining a compliance with these principles.

AART is committed to educate and train each employee in safe work practices and will provide
supplies, tools, equipment and to the maximum extent, a hazard-free environment to ensure all
tasks can be safely completed. No person shall be required or instructed to work in surroundings
or under conditions that are unsafe or dangerous to his or her health. Each individual employed
must take responsibility to become aware of the hazards associated with their workplace and tasks
they are to perform. Each worker is responsible to complying with applicable safety requirements,
wearing prescribed safety equipment and preventing avoiding accidents. Each employee has
a duty to report workplace conditions or practices that pose a safety hazard or threaten the
environment and to take reasonable actions to alleviate such risks.
P. RAMDAS
General Manager
Ali Amin Ramadhan Trad. Co. LLC
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH CENTER

SAFETY STATUS –MAY- 2021.

S.No Total Man-Hours Worked During the Month 3880


1. Cumulative Man Hours Worked 57710
2. Safe Man hours Worked Since Last LTI 57710
3. Total Number of First Aid Cases (FAC). 0
4. Total Number of Restricted Work Cases (RWC) 0
5. Total Number of Lost Time Injuries. (LTI) 0
6. Last LTI On. 0
7. Safety Seminars Conducted in the Month. 0
8. Total Safety Seminars Conducted 0

24
PROJECT: - CONSTRUCTION OF MUQSHIN HEALTH CENTER.

1. PPE
a. Wear protective Equipment.
b. Pay Attention to Personal Hygiene.
c. Do not play in the workplace.
d. Report to your Supervisor if you notice any Unsafe Conditions.

2. Safety Measures:-

a. Before you operate any Machine ensure that the dangerous part of the
machine has been installed with a Guard.
b. Avoid Going to any area with insufficient lighting as there may be some
dangerous place which has not been provided with fencing.
c. Keep vigilant at all time & watch for Moving Cranes, Hooks or other
lifting Equipment.
d. Before Use of any Electrical Installation or Tools check the Condition of
the Electrical Cables.
e. Avoid Dragging the Cables on the Ground or allowing the cables in
contact with Water.
f. Use Electrical Tools with only Earth Leakage Circuit Breaker.
g. Use & Handle Chemicals with care.

3. Tidy Up Construction Site:-

a. Keep passages Clear at all time.


b. Sort out material & pile them up safely. The Stacks to not be too high.
c. Beware of Floor Openings Ensure they are Properly Fenced.
d. Provide with Proper Lighting.
e. Familiarize with Locations & Operation of Fire Fighting Equipment.

5. Covid Pandemic Safety.

a. The Use of Face Masks.


b. Washing of Hands & Personal Hygiene.
c. Encourage Social Distancing.

25
Project:- Construction of Muqshin Health Center
Client:- Ministry of Health
Sponsored By:- Petroleum Development Oman
Consultant:- Simon Engineering & Partners
Contractor:- Ali Amin Ramadan Trad Co LLC

Project Contacts
S.No Name Designation Organization Contact No E-mail

Client :- Ministry of Health

1 Engr. Malik Al Hinai HOE & FU Ministry of Health 96146995 mailik.alhinai@moh.gov.om

2 Engr. Boy Project Coordinator Ministry of Health 97073652

3 Engr. Alalaa MEP Coordinator Ministry of Health 93988289

Consultant :- Simon Engineering & Partners LLC

1 Mr. Ramesh Naidu Sr Project Engineer Simon Eng & Partners 95634310 ramesh@sepoman.com

2 Mr. Ranjith Architetural & Civil Designer Simon Eng & Partners 79863734 ranjith@sepoman.com

3 Nouf Harib Al Alwai Architetural & Civil Designer Simon Eng & Partners nouf@sepoman.com

4 Mr. Ganesh M.H Resident Engineer Simon Eng & Partners 92003659 ganesh@sepoman.com

Main Contractor :- Ali Amin Ramadhan Trad Co. LLC

1 Mr. Ramdas General Manager AART 99315548 ramdas10@hotmail.com

2 Mr. Vicky Project Manager AART 92830010 dropbox30@zoho.com

3 Mr. Jain Anthony MEP Engr AART 92830014 jain.antony.aart@gmail.com

4 Mr. Martin Tom Site Engineer AART 96930379 martinaartc@gmail.com

5 Mr. Sreekanth Vijayan Draftsman AART 94149425 sreekanthvijayan08@gmail.com

26
CONSTRUCTION OF MUQSHIN HEALTH CENTER
Plants & Equipment Load Schedule MAY -2021
Excavator Roller Concrete Wood Steel Electric Drilling Mixer Air Blower
DATE Rock Breaker Jcb Bobcat Tipper Compactor Vibrator Cutting Cutter Electric Hammer Hilt-T Pickup Machine Machine Auto Level Theodolite
Machine
01-05-2021 1 3 2 3 2 1 2 3 1 1 1
02-05-2021 1 3 2 3 2 1 2 3 1 1 1
03-05-2021 1 3 2 3 2 1 2 3 1 1 1
04-05-2021 1 3 2 3 2 1 2 3 1 1 1
05-05-2021 1 3 2 3 2 1 2 3 1 1 1
06-05-2021 1 3 2 3 2 1 2 3 1 1 1
07-05-2021 Friday
08-05-2021 1 3 2 3 2 1 2 3 1 1 1
09-05-2021
10-05-2021 1 3 2 3 2 1 2 3 1 1 1
11-05-2021 1 3 2 3 2 1 2 3 1 1 1
12-05-2021 1 3 2 3 2 1 2 3 1 1 1
13-05-2021 Eid Holiday
14-05-2021 Friday
15-05-2021 Eid Holiday
16-05-2021
17-05-2021 1 3 3 3 2 1 2 3 1 1 1
18-05-2021 1 3 3 3 2 1 2 3 1 1 1
19-05-2021 1 3 3 3 2 1 2 3 1 1 1
20-05-2021 1 3 3 3 2 1 2 3 1 1 1
21-05-2021 Friday
22-05-2021 1 3 3 3 2 1 2 3 1 1 1
23-05-2021 1 3 2 3 2 1 2 3 1 1 1
24-05-2021 1 3 3 3 2 1 2 3 1 1 1
25-05-2021 1 3 3 3 2 1 2 3 1 1 1
26-05-2021 1 3 3 3 2 1 2 3 1 1 1
27-05-2021 1 3 3 3 2 1 2 3 1 1 1
28-05-2021 Friday
29-05-2021 1 3 3 3 2 1 2 3 1 1 1
30-05-2021 1 3 2 3 2 1 2 3 1 1 1
31.05.2021 1 3 2 3 2 1 2 3 1 1 1

28
CONSTRUCTION OF MUQSHIN HEALTH CENTER
DAILY SITE ATTENDANCE REPORT MAY -2021
Date Project Carpenters Steel Fitter Masons Painters Electrician Plumbers Others Operators Helpers Total
Engineer
01-05-2021 1 5 4 2 5 17
02-05-2021 1 5 4 2 5 17
03-05-2021 1 5 4 2 5 17
04-05-2021 1 5 4 2 5 17
05-05-2021 1 4 4 2 4 15
06-05-2021 1 4 4 2 4 15
07-05-2021 Friday
08-05-2021 1 5 4 2 4 16
09-05-2021 1 5 4 2 5 17
10-05-2021 1 5 4 2 5 17
11-05-2021 1 4 4 2 5 16
12-05-2021 1 4 4 2 5 16
13-05-2021 Eid Holiday
14-05-2021 Friday
15-05-2021 Eid Holiday
16-05-2021 1 2 2 2 5 12
17-05-2021 1 4 4 2 5 16
18-05-2021 1 4 4 2 5 16
19-05-2021 1 4 4 2 5 16
20-05-2021 1 4 4 2 5 16
21-05-2021 Friday
22-05-2021 1 4 4 2 5 16
23-05-2021 1 4 4 2 5 16
24-05-2021 1 4 4 2 5 16
25-05-2021 1 4 4 2 5 16
26-05-2021 1 4 4 2 5 16
27-05-2021 1 4 4 2 5 16
28-05-2021 Friday
29-05-2021 1 2 2 2 3 10
30-05-2021 1 2 2 2 3 10
31.05.2021 1 4 4 2 5 16

29
ALI AMIN RAMADHAN TRAD.CO.L.L.C
PROJECT: HEALTH CENTER AT MUQSHIN MANPOWER STRENGTH
Month: MAY 2021
SL.NO CATEGORY DATE TOTAL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 25

Friday Holiday

Friday Holiday

Friday Holiday

Friday Holiday
2 Steel fitter 4 4 4 4 4 4 4 4 4 4 4 2 4 4 4 4 4 4 4 4 4 4 2 2 4 94

Eid Holiday

Eid Holiday
3 Carpenter 5 5 5 5 4 4 5 5 5 4 4 2 4 4 4 4 4 4 4 4 4 4 2 2 4 101
4 Mason 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 50
5 Plumber
6 Helper
7 Others 5 5 5 5 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 3 5 118
Total Per Day 17 17 17 17 15 15 16 17 17 16 16 12 16 16 16 16 16 16 16 16 16 16 0 10 10 16 388

MANPOWER STRENGTH HISTOGRAM MAY-2021

18

16
Project Engineer
14
Steel fitter
12
Carpenter
10
Mason
8 Plumber
6 Helper
4 Others
2 Total Per Day

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

30
PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER

LIST OF APPROVED SUBCONTRACTORS

Planned Work Planned


S.No Description of Work. Proposed Subcontractor Status
Commencement Completion.
1 Anti termite treatment. Al Sahaba Pest Control- Salalah AWC 10.02.2021 10.02.2021

2 Water Proofing Works Ms/ Abou Nabil LLC AWC 06.06.2021 29.06.2021

3 HVAC Works Muscat Electronics AWC 17.05.2021 13.08.2021

4 Structured Cabling Works OHI / MEDCO / MUSCAT MIST 21.06.2021 11.08.2021

5 Fire Fighting Works AL SAIDI / ADDHIA / INTISAR CORPORATION 27.05.2021 12.08.2021

31
MATERIAL APPROVAL STATUS AS ON 06/06/2021 Total MAS 70 Nos.
Project Construction of Muqshin Health Centre Total MAS Submitted 58 Nos.
Submitted for Approval (SFA) / Resubmitted for
Client Ministry of Health Approval (RSFA)
18 Nos.

Consultant M/s. Simon Eng Consultants. Approved 00 Nos


Contractor M/s. Ali Amin Ramadhan Trad. Co. LLC Approved with Comments (AWC) 39 Nos
Withheld/Pending 1 Nos
CIVIL WORKS For Resubmission 00 Nos
MAS DATE
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER STATUS
NO Planned Submitted Approval
C01A Material Testing Lab M/S Wimpey Laboratory M/S Wimpey Laboratory 21/11/2019 22.12.2019 27.02.2020 AWC
C-01B Material Testing Lab Lonestar Alpha Labs Lonestar Alpha Labs 21/11/2019 22.12.2019 27.02.2020 AWC
C02A OPC Cement. Oman Cement Khimji Ramdas 21/11/2019 22.12.2019 27.02.2020 AWC
C02B OPC Cement. Raysut Cement Khimji Ramdas 21/11/2019 22.12.2019 27.02.2020 AWC
C3A Washed Sand Wadi Dahaboon Crusher Naeem Dofar Trad & Cont 21/11/2019 22.12.2019 27.02.2020 AWC
C3B Washed Sand Wadi Dahaboon Crusher Gulf Readymix Co 21/11/2019 22.12.2019 27.02.2020 AWC
C 04A 10mm & 20mm Aggregate Wadi Dahaboon Crusher Naeem Dofar Trad & Cont 21/11/2019 22.12.2019 27.02.2020 AWC
C04B 10mm & 20mm Aggregate Wadi Dahaboon Crusher Gulf Readymix Co 21/11/2019 22.12.2019 27.02.2020 AWC
C05 Imported Backfilling Material Wadi Dahaboon Crusher Naeem Dofar Trad & Cont 21/11/2019 22.12.2019 27.02.2020 AWC
C06 Site Mix Concrete Ali Amin Ramadan Trad Co Ali Amin Ramadan Trad Co 21/11/2019 22.12.2019 27.02.2020 AWC
C07 (A) Reinforcements Sohar Steel Group The Middle East Trad 21/11/2019 22.12.2019 27.02.2020 AWC
C07 (B) Reinforcements Jindal Shadeed Iron Steel LLC Al Ansari Trad LLC 21/11/2019 22.12.2019 27.02.2020 AWC
C08 1200 gauge polythene sheet Promax Sterling International Trad 21/11/2019 22.12.2019 27.02.2020 AWC
C08(B) 1200 gauge polythene sheet Advanced Plastics Ind Isam Kabbaini & Partners LLC 15.07.2020 16.07.2020 28.07.2020 AWC
C09 GeoGrid Geosynthethics Tech Co MHD. 21/11/2019 22.12.2019 27.02.2020 AWC
C10A Coal Tar Epoxy Resin Resigard ETSF(M)-Conmix MHD 21/11/2019 22.12.2019 27.02.2020 AWC
C10B Coal Tar Epoxy Resin Tufcote CT G.I.C 21/11/2019 22.12.2019 27.02.2020 AWC
C11A Bituminious Coating Moyashield RBE-Conmix MHD 21/11/2019 22.12.2019 27.02.2020 AWC
C11B Bituminious Coating Tufguard -RBE G.I.C 21/11/2019 22.12.2019 27.02.2020 AWC
C12 Anti termite Treatment MAC-Agro Chemicals Al Sahaba Pest Control 21/11/2019 22.12.2019 27.02.2020 AWC
C13 ReadyMix Concrete Gulf Readymix Company Gulf Readymix Company 30.12.2020 07.04.2021 21.04.2021 AWC
C14 Flexcial Board Hunton Khimji Ramdas 21/11/2019 22.12.2019 27.02.2020 AWC
C15A Solid & Hollow Blocks Gulf Readymix Company Gulf Readymix Company 21/11/2019 22.12.2019 27.02.2020 AWC
C15B Solid & Hollow Blocks Al Badi Cement Products Al Badi Cement Products 21/11/2019 22.12.2019 27.02.2020 AWC
32
MAS DATE
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER STATUS
NO Planned Submitted Approval
C16 Claustra Blocks National Cement Products LLC National Cement Products LLC 15.02.2021 25.04.2021 SFA
C17 Plaster Sand Wadi Dahaboon Crusher Naeem Dofar Trad & Cont 21/11/2019 22.12.2019 27.02.2020 AWC
C18 Cavity wall Insulation. Mutrah Insofoam Co Mutrah Insofoam Co 21/11/2019 22.12.2019 27.02.2020 AWC
C19 Light weight Screed Concrete Deufoam Abou Nabil LLC 21/11/2019 22.12.2019 27.02.2020 AWC
C20 Damp Proof Course Polyshield HD Henkel Polybit Industries. 21/11/2019 22.12.2019 27.02.2020 AWC
C21 Roof water proofing works Henkel Polybit Industries. Abou Nabil LLC 21/11/2019 22.12.2019 27.02.2020 AWC
C22 Geotextile membrane Bitumat Abou Nabil LLC 21/11/2019 22.12.2019 27.02.2020 AWC
C23 Roof Insulation Board Al Khaleej Insulation Co Mutrah Insofoam Co 21/11/2019 22.12.2019 27.02.2020 AWC
C24 Wet Area Waterproofing -Cementitious Conmix LTD Conmix LTD 21/11/2019 22.12.2019 27.02.2020 AWC
C25 Roof Tiles -500mmx500mm x 40mm Automatic Terrazzo Tiles. Automatic Terrazzo Tiles. 30.03.2021 07.04.2021 SFA
C26 Block & Plastering Accessories. Unitec Issam Kabbanni & Partners 21/11/2019 22.12.2019 27.02.2020 AWC
C27 Polysulphide sealant. Tuflex PS-250 Gulf International Chemicals 21/11/2019 22.12.2019 27.02.2020 AWC
C28 Grouting compound. NanoGrout -Conmix Conmix LTD 21/11/2019 22.12.2019 27.02.2020 AWC
C29 Metal Doors & Frames Mechanical & Techical Solutions Building Supplies & Services 21/11/2019 22.12.2019 27.02.2020 AWC
C30 Aluminium Doors & Windows NAPCO-Oman Ali Amin Ramadan Trad Co 21/11/2019 22.12.2019 27.02.2020 AWC
C31 Iron Mongeries 16.06.2021
C32 GRC Screens 16.06.2021
C33 Carpentary Works Ali Amin Ramadan Trad Co Ali Amin Ramadan Trad Co 21/11/2019 22.12.2019 Witheld
C34 Fire Rated Door Shutters Al Dhab Techical Services LLC Al Dhab Techical Services LLC 30.03.2021 07.04.2021 SFA
C35 Lead Lined Door Shutter Al Dhab Techical Services LLC Al Dhab Techical Services LLC 30.03.2021 07.04.2021 SFA
C36 Lead Lined Glass Mahn Medizinprodukte-Germany M/s Waleed Pharmacy LLC 30.03.2021 07.04.2021 SFA
C37 Lead Sheet Rayprotec M/s Al Amana Building Material 30.03.2021 07.04.2021 SFA
C38 Aluminium Corner Guards Mohammed Riaz & Partners LLC M/s Golden Arena 30.03.2021 07.04.2021 SFA
C39 Guard Hand Rail Arfen Building Supplies & Services 30.03.2021 07.04.2021 SFA
C40 Door Frame & shutter protection. Arfen Building Supplies & Services 30.03.2021 07.04.2021 SFA
C41 Key Cabinet 16.06.2021
C42 Internal Signage 16.06.2021
C43 Omani Marble Tiles & skirting 16.06.2021
C44 Granite Tiles & Skirting. 16.06.2021
C45 200 x300 Glazed Ceramic Wall Tiles. R.A.K Ceramics Bahwan Building Materials 30.03.2021 07.04.2021 SFA
33
MAS DATE
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER STATUS
NO Planned Submitted Approval
C46 300 x 300 Vetrified Ceramic Floor Tile & CoveR.A.K Ceramics Bahwan Building Materials 30.03.2021 07.04.2021 SFA
C49 PVC Flooring & Skirting. Tarkett M/s Al Amana Building Material 30.03.2021 07.04.2021 SFA
C50 Floor Hardener TekniFloor Plus-E-Conmix MHD 21/11/2019 22.12.2019 27.02.2020 AWC
C51 Manhole Covers RBAC-RBA-India Buildex International LLC 21/11/2019 22.12.2019 27.02.2020 AWC
C52A Repair Mortar Conmix LTD MHD 21/11/2019 22.12.2019 27.02.2020 AWC
C52B Repair Mortar Tufbuild HS Gulf International Chemicals 21/11/2019 22.12.2019 27.02.2020 AWC
C53 Tile Grout Tilex LM -Conmix Conmix LTD 30.03.2021 07.04.2021 SFA
C54 600x600mm x 0.7mm false ceiling. 16.06.2021
C55 Static Shelving 16.06.2021
C56 Pharmacy Shelving. Herman Miller S.F.O 30.03.2021 07.04.2021 SFA
C57 Paint system Permoglaze Khimji Ramdas 30.03.2021 07.04.2021 SFA
C58 Cubical Curtains 16.06.2021
C59 Built In Lab furniture. 16.06.2021
C60 Pin Boards 16.06.2021
C61 Kerb stone Gulf Readymix Company Gulf Readymix Company 30.03.2021 07.04.2021 SFA
C62 Interlock Tiles Gulf Readymix Company Gulf Readymix Company 30.03.2021 07.04.2021 SFA
C63 Flag Pole-12m Harrisons-U.K Muscat Horizons Int LLC 30.03.2021 07.04.2021 SFA
C64 Main Entrance GRP Sign Board 16.06.2021
C65 Water For Construction Muqshin Local Suppliers Muqshin Local Suppliers 15.07.2020 16.07.2020 28.07.2020 AWC
C66 Anti Corrosive Steel Primer Conmix LTD Conmix LTD 15.07.2020 16.07.2020 28.07.2020 AWC
C67A Concrete Curing Agent Conmix LTD Conmix LTD 26.08.2020 30.08.2020 30.12.2020 AWC
C68 Binding Wire Dingzhou Shengxin Metal Prod Al Khalili Ent/ Talent Building 01.09.2020 02.09.2020 27.09.2020 AWC
C69 Water Stopper SCP Concrete Sealing-U.K M.H.D 07.10.2020 26.10.2020 05.11.2020 AWC
C70 Holding Tank Steps STGS028-India M/s Khurshid Technical Trad 07.10.2020 26.10.2020 05.11.2020 AWC
C71 Concrete Bonding Agent Fosroc-Nitobond M/s Al Amana Building Material 16.11.2020 17.11.2020 01.12.2020 AWC
C72(R1) Rust Remover Conmix -RR M.H.D 07.04.2021 11.04.2021 14.04.2021 AWC
34
MATERIAL APPROVAL STATUS AS ON 06/06/2021 Total MAS 34 Nos.
Project Construction of Muqshin Health Centre Total MAS Submitted 32 Nos.
Submitted for Approval (SFA) / Resubmitted for
Client Ministry of Health Approval (RSFA)
20 Nos.

ConsultanM/s. Simon Eng Consultants. Approved (Appvd) 00 Nos.


ContractorM/s Ali Amin Ramadhan Trad. Co. LLC Approved with Comments (AWC) 07 Nos
Witheld/Pending 00 Nos
PLUMBING WORKS
For Resubmission 05 Nos.
DATE
MAS NO MATERIAL DESCRIPTION MANUFACTURER SUPPLIER STATUS
Planned Submitted Approval
PL-01(B) UPVC Pipes & fittings Hepworth Corys Pipe Ind LLC 30.08.2020 15.09.2020 18.10.2020 AWC
PL-03 Polyproplene Pipes & Fitiings. Vulcathene Corys Pipe Ind LLC 30.08.2020 15.09.2020 18.10.2020 AWC
PL-04 UPVC Floor trap & Stainless steel Grating. Hepworth Corys Pipe Ind LLC 30.08.2020 15.09.2020 18.10.2020 AWC
PL-05 Nickel Bronze Cleanout Mifab Corys Pipe Ind LLC 30.08.2020 15.09.2020 To Resubm
PL-06(A) UPVC Gully Trap Hunter Corys Pipe Ind LLC 30.08.2020 15.09.2020 18.10.2020 AWC
PL-07(A) Copper Pipes & Fittings Yorkshire Ahmed Mohsin Trad 30.08.2020 11.02.2021 RSFA
PL-07(B) Copper Pipes & Fittings Crane M.H.D 30.08.2020 11.02.2021 RSFA
PL-08 G.I Pipes. Al Jazeera Pipes Al Khalili LLC 30.08.2020 15.09.2020 18.10.2020 AWC
PL-09 Gate Valves Peglar Ahmed Mohsin Trad 30.08.2020 15.09.2020 18.10.2020 AWC
PL-10 Angle Valves Pex M.H.D 30.08.2020 15.09.2020 To Resubm
PL-11 Rain Water Outlet Hepworth Corys Pipe Ind LLC 30.08.2020 15.09.2020 To Resubm
PL-12 European water closet Armitage shanks M.H.D 30.08.2020 11.02.2021 RSFA
PL-13 Ablution faucet Ideal Standard M.H.D 30.08.2020 11.02.2021 RSFA
PL-14 Disabled Toilet Set Armitage shanks M.H.D 30.08.2020 11.02.2021 RSFA
PL-15 Wash hand basin Armitage shanks M.H.D 30.08.2020 11.02.2021 RSFA
PL-16 Wash basin Mixer Ideal Standard M.H.D 30.08.2020 11.02.2021 RSFA
PL-17 Medical Wash hand basin Armitage shanks M.H.D 30.08.2020 11.02.2021 RSFA

35
DATE
MAS NO MATERIAL DESCRIPTION MANUFACTURER SUPPLIER STATUS
Planned Submitted Approval
PL-18 Medical Mixer Delabie-France M.H.D 30.08.2020 11.02.2021 RSFA
PL-19 Stainless Steel Sink. Blanco M.H.D 30.08.2020 11.02.2021 RSFA
PL-20 Sink Mixer Vidima Ideal Standard M.H.D 30.08.2020 11.02.2021 RSFA
PL-21 Cleaners Sink Armitage shanks M.H.D 30.08.2020 11.02.2021 RSFA
PL-22A Tissue dispenser GStyle M.H.D 30.08.2020 11.02.2021 RSFA
PL-22B Tissue dispenser Tork M.H.D 30.08.2020 11.02.2021 RSFA
PL-23 Liquid soap dispenser GStyle M.H.D 30.08.2020 11.02.2021 RSFA
PL-24 Medical soap dispenser Nofer M.H.D 30.08.2020 11.02.2021 RSFA
PL-25 Bib Taps Grohe M.H.D 30.08.2020 11.02.2021 RSFA
PL-26 Bottle Traps Veiga M.H.D 30.08.2020 11.02.2021 RSFA
PL-27 GRP Water Tank-5000 Lits Muscat Fiber Glass Muscat Fiber Glass 30.08.2020 15.09.2020 To Resubm
PL-28
(Option-2)
GRP Sectional Water Tank- 120m3 PIPECO Al Ansari Trad. 30.10.2020 24.11.2020 21.12.2020 AWC

PL-29 200 USG Polyethylene water tank. Darwish Polycon M.H.D 30.08.2020 15.09.2020 To Resubm
PL-30 Shower Tray Porcher(Ideal Standard) M.H.D 30.08.2020 11.02.2021 RSFA
PL-31 Shower Mixer Vidima Ideal Standard M.H.D 30.08.2020 11.02.2021 RSFA
PL-34 Water Cooler 16.06.2021
PL-35 Hot Water Recirculation pump- 0.5 L/S Grundfos Gulf Services 30.10.2020 24.11.2020 15.03.2021 AWC
PL-36 Booster Pump- 3lps @ 2 Bar Grundfos Gulf Services 30.10.2020 24.11.2020 15.03.2021 AWC
PL-37 Fire Fighting System 16.06.2021

36
MATERIAL APPROVAL STATUS AS ON 06/06/2021 Total MAS 53 Nos.
Project Construction of Muqshin Health Centre Total MAS Submitted 47 Nos.
Submitted for Approval (SFA) /
Client Ministry of Health Resubmitted for Approval 00 Nos.
(RSFA)
Consultant M/s. Simon Eng Consultants. Approved 0 Nos
Contractor M/s Ali Amin Ramadhan Trad. Co. LLC Approved with Com(AWC) 20 Nos
Withheld Pending 0 Nos
ELECTRICAL WORKS To Resubmit 26 Nos.
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
EL.01 PVC Conduits HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.02 PVC Conduit Accessories HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.03 G.I Conduits HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.04 G.I Conduit Accessories HOTACE M/s. National Plastic Factory LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.05 G.I Boxes Spectra M/s. Tri-Spectrum Co. 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.06
PVC Insulated Single Core Wire OCI M/s. BEC / M/s. Al Khalili United En20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.06
PVC Insulated Single Core Wire NUHAS M/s. Al Khalili United Ent. 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.07 M/s. BEC / M/s. Al Khalili
XLPE Insulated Armoured Cable OCI 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio United Ent.
EL.07
XLPE Insulated Armoured Cable NUHAS M/s. Al Khalili United Ent. 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.08 Fire Proof Cable for Fire Alarm System PRYSMIAN M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC

EL.09 Switches & Sockets MK M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
EL.10
Weather Proof Switches MK M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
(Optio
EL.11 13A Unswitched Twin UPS Socket ELECTRAK M/s. Al Dastoor Trad. Co. LLC 20/08/2020 18/08/2020 26/10/2020 AWC
EL.12 Weather Proof Isolators Schneider M/s. Al Khalili United Ent. 20/08/2020 04/10/2020 21.12.2020 AWC
(Optio
EL.13 Lightning Protection System ABB M/s. BEC 20/08/2020 18/08/2020 21.12.2020 AWC
EL.14 300 Ltrs Glass Lined Storage Water Heater A.O Smith M/s. Al Ansari Trad. 30/10/2020 24/11/2020 14.03.2021 AWC
37
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
EL.15 Bed Head Units Statics M/s. OHI 30/10/2020 01/11/2020 21.12.2020 AWC
EL.16 Plug in Ceiling Rose MK M/s. MHD 20/08/2020 18/08/2020 26/10/2020 AWC
EL.17 Distribution Boards 21/05/2021
EL.18 Nurse Call System Statics M/s. OHI 30/10/2020 01/11/2020 21.12.2020 AWC
EL.19 50 Ltrs Water Heater 16.06.2021
EL.20 Fire Alarm System 16.06.2021

EL.21 Automatic Hand Drier 16.06.2021

EL.22 Automatic Sliding Door Operator Assa Abloy M/s. International Ent. 18/08/2020 18/08/2020 26/10/2020 AWC
4x18W Recessed Light Fitting with M/s. Bahwan Building
EL.23 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP40 (Type-1) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.24 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-1E) Materials
4x18W Recessed Light Fitting with M/s. Bahwan Building
EL.25 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP54 (Type-2) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.26 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-2E) Materials
4x18W Recessed Light with Prismatic
M/s. Bahwan Building
EL.27 Diffuser and Dimmable Control Gear, IP40 Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
(Type-3)
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.28 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-3E) Materials
4x18W Recessed Light Fitting with
M/s. Bahwan Building
EL.29 Aluminium Double Parabolic Louver, IP20 Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
(Type-4)
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.30 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-4E) Materials
4x18W Recessed Light Fitting with M/s. Bahwan Building
EL.31 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP64 (Type-5) Materials
EL.32 Ditto of above + 3hrs Emergency Pack Thorn M/s. Bahwan Building 30/01/2021 22.03.2021 To Resubmit
(Type-5E) Materials
38
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
M/s. Bahwan Building
EL.33 1x16W Recessed Downlight, IP54 (Type-6) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
2x36W Recessed Light Fitting with M/s. Bahwan Building
EL.34 Thorn 30/01/2021 22.03.2021 To Resubmit
Prismatic Diffuser, IP40 (Type-8) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.35 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-8E) Materials
2x36W Surface Mtd. Light with Prismatic M/s. Bahwan Building
EL.36 Thorn 30/01/2021 22.03.2021 To Resubmit
Diffuser, IP20 (Type-9) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.37 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-9E) Materials
2x36W Surface Mtd. Light with Prismatic M/s. Bahwan Building
EL.38 Thorn 30/01/2021 22.03.2021 To Resubmit
Diffuser, IP65 (Type-17) Materials
Ditto of above + 3hrs Emergency Pack M/s. Bahwan Building
EL.39 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-10E) Materials
1x7W, Recessed Down Light Night Lamp, M/s. Bahwan Building
EL.40 Thorn 30/01/2021 22.03.2021 To Resubmit
IP40 (Type-14) Materials
39
DATE
MAS
MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Approval STATUS
NO Planned Submitted
Received
2x9W, Surface Mtd.External Wall Light M/s. Bahwan Building
EL.42 Thorn 30/01/2021 22.03.2021 To Resubmit
(Type-K) Materials
M/s. Bahwan Building
EL.43 2x26W Surface Mtd. Wall Light (Type-Q) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
M/s. Bahwan Building
EL.44 1x9W, X-Ray Warning Light (Type-P) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
M/s. Bahwan Building
EL.45 1x18W, Mirror Light (Type-ML) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
M/s. Bahwan Building
EL.46 1x8W, Maintained Type Exit Light Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
100W, Metal Halide Pole Light, IP54 + M/s. Bahwan Building
EL.47 Thorn 30/01/2021 22.03.2021 To Resubmit
4mtr G.I Pole (Type-T1) Materials
23W, Round Globe Gate light, IP54 (Type- M/s. Bahwan Building
EL.48 Thorn 30/01/2021 22.03.2021 To Resubmit
GL) Materials
EL.49 G.I Trunking & Cable Tray Hotex Steel
M/s. National Heaters Indus. 30/11/2020 18/08/2020 26/10/2020 AWC
Co. LLC
EL.50 LV Panels 16.06.2021

EL.51 Weatherproof Sockets Schneider M/s. Al Khalili United Ent. 31/10/2020 04/10/2020 21.12.2020 AWC

EL.52 Weatherproof Metal Clad Sockets LEWDEN M/s. Al Sabbagh Trad. LLC 31/10/2020 04/10/2020 21.12.2020 AWC

M/s. Bahwan Building


EL.53 150W, Flood Light, IP54 (Type-R) Thorn 30/01/2021 22.03.2021 To Resubmit
Materials
EL.54 Structured Cabling 16.06.2021
40
MATERIAL APPROVAL STATUS AS ON 06/06/2021 Total MAS 15 Nos.
Project Construction of Muqshin Health Centre Total MAS Submitted 15 Nos.
Submitted for Approval (SFA) / Resubmitted for
Client Ministry of Health Approval (RSFA)
15 Nos.

Consultant Simon Engineering & Partners LLC Approved 0 Nos.


Contractor M/s. Ali Amin Ramadhan Trad. Co. LLC Approved with Comments (AWC) 00 Nos.
Withheld/Pending 0 Nos
HVAC WORKS For Resubmission 00 Nos.
DATE
MAS NO MATERIAL DESCRIPTION MANUFACTURER SUPPLIER Comments Approval STATUS
Planned Submitted Resubmitted
Received Received

AC-01 Roof Top Package AC Units Daikin M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-02 Split AC Units Daikin M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-03 Wall Mounted Extract Fans System Air M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-04 Roof Mounted Extract Fans System Air M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-05 Air Curtains Mitsubitshi M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-06 Copper Refrigerant Pipe Lawton M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-07 Refrigerant Pipe Insulation Gulf-O-Flex M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-08 G.I Sheets Jindal, India M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-09 Thermal Insulation for HVAC Ducts Thermobreak M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-10 Acoustic Insulation Thermobreak M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-11 Hammered Aluminium sheet. Garmco M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-12 Fire Dampers Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-13 Volume Control Dampers. Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-14 Diffusers, Sand Trap Louver, Louver Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

AC-15 Sound Attenuator Excelair M/s. Muscat Electronics 30/12/2020 30.08.2020 22/10/2020 17.05.2021 RSFA

41
SHOP DRAWING STATUS AS ON 06/06/2021 Total shop drawings 21 Nos.
Project Muqshin Health Center Total Submitted 14 Nos.
Client Ministry of Health Submitted / Resubmitted for Approval 00 Nos

Consultant Simon Engineering & Partners Approved / Approved with comments 14 Nos.

Contractor M/s. Ali Amin Ramadhan Trad. Co. LLC For Resubmission 00 Nos.

CIVIL WORKS
DATE
SI. Approval
DRAWING TITLE DRAWING NO. Comments Approval
NO Planned Submitted Resubmitted Status
Received Received
1 Project Sign Board AARAMCO/J79/MOH-PDO/Muqshin/C-01 14.09.2019 14.09.2019 28.10.2019 AWC

2 Site Mobilization Plan AARAMCO/J79/MOH-PDO/Muqshin/C-02 13.10.2019 13.10.2019 28.10.2019 AWC

3 Site Spot Levels & Excavation AARAMCO/J79/MOH-PDO/Muqshin/C-03 02.03.2020 02.03.2020 24.03.2020 AWC
4 Site Set out Marking & Excavation AARAMCO/J79/MOH-PDO/Muqshin/C-04 12.02.2020 12.02.2020 27.02.2020 AWC
5 Site Boundry Wall Plan AARAMCO/J79/MOH-PDO/Muqshin/C-05 15.04.2020 15.04.2020 08.10.2020 AWC
6 Boundry Wall Typical Sections AARAMCO/J79/MOH-PDO/Muqshin/C-06 15.04.2020 15.04.2020 08.10.2020 AWC
7 Boundry Wall Front Side Elevations-A AARAMCO/J79/MOH-PDO/Muqshin/C-07 15.04.2020 15.04.2020 08.10.2020 AWC
8 Boundry Wall Left Side Elevations-D AARAMCO/J79/MOH-PDO/Muqshin/C-08 15.04.2020 15.04.2020 08.10.2020 AWC
9 Boundry Wall Rear Side Elevations-C AARAMCO/J79/MOH-PDO/Muqshin/C-09 15.04.2020 15.04.2020 08.10.2020 AWC
10 Boundry Wall Right Side Elevations-B AARAMCO/J79/MOH-PDO/Muqshin/C-10 15.04.2020 15.04.2020 08.10.2020 AWC
11 External Site Development Interlocking & Storm Water AARAMCO/J79/MOH-PDO/Muqshin/C-11 15.12.2020 27.12.2020 03.01.2021 05.01.2021 24.02.2021 AWC
12 Ground Beam & Slab Plan AARAMCO/J79/MOH-PDO/Muqshin/C-11A 29.12.2020 30.12.2020 12.01.2021 AWC
13 Ground Beam & Slab -Sections. AARAMCO/J79/MOH-PDO/Muqshin/C-11B 29.12.2020 30.12.2020 12.01.2021 AWC
14 Boundary Wall Rear Side Elevation-C (Setback Location) AARAMCO/J79/MOH-PDO/Muqshin/C-12 18.02.2021 21.02.2021 17.03.2021 23.03.2021 04.04.2021 AWC
15 Roof Finishes Layout AARAMCO/J79/MOH-PDO/Muqshin/C-13 16.06.2021
16 Schedule of Doors & Windows. AARAMCO/J79/MOH-PDO/Muqshin/C-14 16.06.2021
17 Layout of Floor & Wall Finishes. AARAMCO/J79/MOH-PDO/Muqshin/C-15 16.06.2021
18 False Ceiling Layout AARAMCO/J79/MOH-PDO/Muqshin/C-16 16.06.2021
19 Built in Furniture AARAMCO/J79/MOH-PDO/Muqshin/C-17 16.06.2021
20 Layout for Guard Rail & Corner Guards. AARAMCO/J79/MOH-PDO/Muqshin/C-18 16.06.2021
21 Layout for Cubicle Curtains. AARAMCO/J79/MOH-PDO/Muqshin/C-19 16.06.2021

42
SHOP DRAWING STATUS AS ON 06/06/2021 Total shop drawings: 09 Nos

Project Muqshin Health Center Total Submitted 02 Nos


Submitted for Approval (SFA) /
01 Nos
Client Ministry of Health Resubmitted for Approval (RSFA)

Consultant Simon Engineering & Partners Approved/Approved with Comments 01 Nos

Contractor M/s. Ali Amin Ramadhan Trad. Co. LLC For Resubmission 00 Nos

MECHANICAL WORKS
DATE
SI. Approval
DRAWING TITLE DRAWING NO. Comments Approval
NO Planned Submitted Resubmitted Status
Received Received
Internal & External Drainage Services Layout - Health
1 AARAMCO/J79/MOH-PDO/Muqshin/PL-01(R3) 30.09.2020 15.09.2020 01/11/2020 03.01.2021 17.01.2021 AWC
Center, Maternity Building & Guard Room
Roof Drainage Layout - Health Center & Maternity
2 AARAMCO/J79/MOH-PDO/Muqshin/PL-02 16.06.2021
Building
Ground Floor Water Supply Layout - Health Center &
3 AARAMCO/J79/MOH-PDO/Muqshin/PL-03 16.06.2021
Maternity Building

4 Roof Water Supply- Health Center & Maternity Building AARAMCO/J79/MOH-PDO/Muqshin/PL-04 16.06.2021

5 Guard Room Water Supply Layout AARAMCO/J79/MOH-PDO/Muqshin/PL-05 16.06.2021


External Water Supply & Sleeves for Health Center,
6 AARAMCO/J79/MOH-PDO/Muqshin/PL-06 30.04.2021 19.04.2021 25.05.2021 31.05.2021 RSFA
Maternity & Guard Room.
Ground Floor Fire Fighting Layout - Health Cente,
7 AARAMCO/J79/MOH-PDO/Muqshin/PL-07 16.06.2021
Maternity & Guard House Building
Roof Fire Fighting Layout - Health Center & Maternity
8 AARAMCO/J79/MOH-PDO/Muqshin/PL-08 16.06.2021
Buidling

9 External Fire Fighting Service Layout AARAMCO/J79/MOH-PDO/Muqshin/PL-09 16.06.2021

43
SHOP DRAWING STATUS AS ON 06/06/2021 Total shop drawings: 13 Nos.

Project : Muqshin Health Center Total Submitted 02 Nos.

Submitted for Approval (SFA) /


Client : Ministry of Health Resubmitted for Approval (RSFA)
00 Nos

Consultant : Simon Engineering & Partners Approved 00 Nos.

Contractor : M/s. Ali Amin Ramadhan Trad. Co. LLC For Resubmission 02 Nos.

ELECTRICAL WORKS
DATE
SI.
DRAWING TITLE DRAWING NO. Comments Approval Approval Status
NO Planned Submitted Resubmitted
Received Received
For
1 Cutouts In Floor Slab for all Cable Entries from External Areas. AARAMCO/J79/MOH-PDO/Muqshin/EL-01A 30/10/2020 11.02.2021 23.02.2021
Resubmission
2 Site Plan - External Electrical Lighting & Power Layout AARAMCO/J79/MOH-PDO/Muqshin/EL-02 16.06.2021
Ground Floor Lighting Layout - Health Centre, Maternity Unit &
3
Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-03 16.06.2021
Ground Floor Small Power & SMATV Layout - Health Centre,
4
Maternity Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-04 16.06.2021

5 Ground Floor UPS Power Layout - Health Centre & Maternity Unit AARAMCO/J79/MOH-PDO/Muqshin/EL-05 16.06.2021
Ground Floor Structured Cabling Layout - Health Centre, Maternity
6
Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-06 16.06.2021
Ground Floor Nurse Call System Layout - Health Centre & Maternity
7
Unit
AARAMCO/J79/MOH-PDO/Muqshin/EL-07 16.06.2021
Roof Electrical Services Layout - Health Centre, Maternity Unit &
8
Guard House Building
AARAMCO/J79/MOH-PDO/Muqshin/EL-08 16.06.2021
Roof Lightning Protection Layout - Health Centre, Maternity Unit & For
9 AARAMCO/J79/MOH-PDO/Muqshin/EL-09 23.11.2020 24/11/2020 07.01.2021
Guard House Resubmission
10 DB Schedule - Health Centre, Maternity Unit & Guard House AARAMCO/J79/MOH-PDO/Muqshin/EL-10 16.06.2021
Main Power Supply Schematic Diagram - Health Centre, Maternity
11
Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-11 16.06.2021
Ground Floor Fire Alarm System Layout - Health Centre, Maternity
12
Unit & Guard House
AARAMCO/J79/MOH-PDO/Muqshin/EL-12 16.06.2021

13 Site Plan - External Electrical Services Layout AARAMCO/J79/MOH-PDO/Muqshin/EL-13 16.06.2021

44
SHOP DRAWING STATUS AS ON 06/06/2021

Project : Muqshin Health Center Total shop drawings 03 Nos.

Client : Ministry of Health Total Submitted 00 Nos.

Submitted for Approval (SFA) /


Consultant : Simon Engineering & Partners Resubmitted for Approval (RSFA)
00 Nos

Contractor : M/s. Ali Amin Ramadhan Trad. Co. LLC Approved 00 Nos.

For Resubmission 00 Nos.

HVAC WORKS
DATE
SI.
DRAWING TITLE DRAWING NO. Approval Status
NO Comments Approval
Planned Submitted Resubmitted
Received Received

Ground Floor HVAC Layout - Health Centre, Maternity Unit & Guard
1
House Building
AARAMCO/J79/MOH-PDO/Muqshin/AC-01 16.06.2021

Roof HVAC Layout - Health Centre, Maternity Unit & Guard House
2
Building
AARAMCO/J79/MOH-PDO/Muqshin/AC-02 16.06.2021

3 HVAC Equipment Schedule & Details AARAMCO/J79/MOH-PDO/Muqshin/AC-03 16.06.2021

45
PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER

LIST OF APPROVED SAMPLES -Civil Works.

S.NO MAS Ref DESCRIPTION OF MATERIAL MANUFACTURER STATUS

1 C-08 1200 Gauge Polythene Sheet Promax Approved


2 C-18 Cavity Wall Insulation Mutrah Insofoam Co Approved
3 C-21 Water Proofing Membrane Henkel Polypit Ind Approved
4 C-22 Geotextile Membrane Bitumat Approved

5 C-23 Roof Insulation Board Cooltop. Approved

6 C-26 Block & Plastering Accessories. Unitec Approved


7 C-69 Water Stopper SCP Concrete Seal Tech Approved
8 C-70 Holding Tank Down Steps SRGS028 Approved

PROJECT :- CONSTRUCTION OF MUQSHIN HEALTH CENTER

LIST OF APPROVED SAMPLES -Plumbing Works

S.NO MAS Ref DESCRIPTION OF MATERIAL MANUFACTURER STATUS

1 PL-01B UPVC Pipes & Fittings Hepworth Approved

46
PROJECT: - CONSTRUCTION OF MUQSHIN
HEALTH CENTRE

INVOICING STATUS
AMOUNT CERTIFIED
DATE OF PAYMENT
SI.NO. INVOICE DETAILS CLAIMED AMOUNT
SUBMISSION STATUS
(R.O) (R.O )

1. ADVANCE PAYMENT 17.12.2019 100,000.000 98,800.000 Received

2. INTERIM BILL NO-1 26.07.2020 28,037.798 25,448.196 Received

3. INTERIM BILL NO-2 05.11.2020 26,826.191 26,751.580 Received

4. INTERIM BILL NO-3 14.02.2021 31,875.674 30,831.677


Awaited

5. INTERIM BILL NO-4

6. INTERIM BILL NO-5

7. INTERIM BILL NO-6

8. INTERIM BILL NO-7

9. INTERIM BILL NO-8

10. INTERIM BILL NO-9

11. INTERIM BILL NO-10

47
Project:- Construction of Proposed Muqshin Health Center.

Maternity Building Plinth Beam support works.

48
Project:- Construction of Proposed Muqshin Health Center.

Right Side Elevation Boundary wall plinth Beam Reinforcements.

Right Side Elevation Boundary wall plinth Beam Concrete works.

49
Project:- Construction of Proposed Muqshin Health Center.

Maternity Building Plinth Beam support works.

Main Health Center Building Plinth Beam Markings on PCC

50
Project:- Construction of Proposed Muqshin Health Center.

Maternity Building:- Polythene sheet protection to Plinth Beam Rebars.

Main Health Center plinth Beam Reinforcement works.

51
Project:- Construction of Proposed Muqshin Health Center.

Left side Elevation Boundary wall Foundation PCC Foam works.

Left side Elevation Boundary wall Foundation PCC Concrete.

52
Project:- Construction of Proposed Muqshin Health Center.

Main Health Center Building plinth Beam Reinforcement works.

53
Project:- Construction of Proposed Muqshin Health Center.

Left side Elevation Boundary wall Foundation PCC Foam works.

54
Project:- Construction of Proposed Muqshin Health Center.

Main Health Center Building plinth Beam Reinforcement works.

55
Project:- Construction of Proposed Muqshin Health Center.

Main Health Center Building plinth Beam Reinforcement works.

Main Health Center Building Plinth Beam Steel works checking & Inspection.

56
Project:- Construction of Proposed Muqshin Health Center.

Right Side Elevation Boundry wall Footing Concrete works.

Right side Boundary Wall Footing Curing works.

57
Project:- Construction of Proposed Muqshin Health Center.

Left Side Elevation Boundary Wall Footing markings.

Left Side Boundary Wall Foundation Foam works.

58