PRESSTECH (INDIA)

ADVANCED PRODUCT QUALITY PLANNING TIMING CHART


PART NAME : Spring Lock Washer CUSTOMER :- MAHLE ANAND Thermal Systems Private Limited

PART NO :- 6101797 Key Coordinator :- Mr. RK Gupta & Avijit Ajit Sen

Rev. No.:- Nil Rev. Dt - Nil


Period
Planned Activity Resp. Status Remarks
Start End

PART FEASIBILITY Planned 22.11.2021 26.11.2021 CFT ---


Done
Actual 26.11.2021 15.12.2021

RM ORDER Planned 05.12.2021 18.12.2021 Mr. RK GUPTA 16.12.2021:- Required raw material availability is released.
18.12.2021:- Raw Material is ordered. Done
Actual 16.12.2021

27.11.2021:- Proposed drawing is provided to tool developer.


TOOL / MOULD DESIGN Planned 26.11.2021 28.12.2021 VIJAY 14.12.2021:- CAD File of Blanking tool is made with required
specification & plates. Done
03.01.2021:- CAD File of Blanking tool is made with required
Actual 27.11.2021 03.01.2022
specification & plates.
04.01.2022:- Tool Material has been Ordered.
TOOL MANUFACTURING PROCESS Planned 30.12.2021 14.02.2022 VIJAY 18.01.2022:- Tool has been sent to Facing & Grinding operation.
31.01.2022:- Tool has been sent to Wire cut for Profile cutting.
22.02.2022:- Tool Tapping & Drilling done.
23.02.2022:- Tool has been sent for Heat Treatment.
05-03-2022:- Tool1 receievd from Heat treatment. Done

Actual 04.01.2022 18.03.2022


08-03-2022:- Tool 2 Recieved from Heat Treatment.
18-03-2022:- Left over Maching is done for both the Tools.

TOOL/MOULD ASSEBLY Planned 15.02.2022 16.02.2022 VIJAY 23.03.2022 :- Tool Assemblied & Ready for operations.
Actual 19.03.2022 23-0.3.2022
BLANKING Planned 17.02.2022 21.02.2021 AVIJIT
Actual
MACHINING Planned 22.02.2021 28.02.2022 AVIJIT
Actual
FORMING Planned 01.03.2022 04.03.2021 AVIJIT
Actual
AUSTEMPERING Planned 08.03.2022 10.03.2021 AVIJIT
Actual
TEMPERING Planned 11.03.2021 14.03.2022 AVIJIT
Actual
POLISHING Planned 14.03.2022 16.03.2022 AVIJIT
Actual
INORGANIC/Zn,Al COATING Planned 17.03.2022 23.03.2022 AVIJIT
Actual
LOAD TESTIN G Planned 24.03.2022 28.03.2022 AVIJIT
500000N ± 500N FOR 3.75 ± 0.2 mm
Actual
SST Report (480 hrs Red Rust) Planned 24.03.2022 13.04.2022 AVIJIT
Actual
READY FOR TRIAL T0 & SAMPLE SUBMISSION TO Mahle Planned 15.04.2022 20.04.2021 AVIJIT
Actual
MAHLE INSPECTION REPORT WITH FITMENT & TESTING Planned MAHLE CFT
Actual
CORRECTION & TRIAL T1 Planned AVIJIT
Actual
MAHLE INSPECTION REPORT Planned MAHLE CFT
Actual
TRIAL 2 Planned AVIJIT
Actual
MAHLE INSPECTION REPORT Planned MAHLE CFT
Actual
HANDOVER PART TO REGULAR PURCHASE Planned AVIJIT/ CFT

Actual ------