Sr.No Area Task Required Resource Activity Time Start Date End Date Remarks
Branding work - Pre requisites

1 Reception right wall Power outlet box to close and Electrical & painter 2 hrs 19th jun 2021 19th jun 2021 In house team work
finish in wall level

2 Reception Counter Glass to remove and surface finish Carpenter and Painter 1 hr 19th jun 2021 19th jun 2021 In house team work

Glass to remove and surface finish Carpenter and Painter 4 hrs 19th jun 2021 19th jun 2021 In house team work
3 Lift Side wall
Lift call panels to level with wall Electrical 1hr 19th jun 2021 19th jun 2021 In house team work

Removal of bamboo design & land


Labour 3 hrs 19th jun 2021 19th jun 2021 In house team work
scaping

4 Reception front corner Wall surface finish work Painter 2 hrs 19th jun 2021 19th jun 2021 In house team work

C.C floor level 12 mm below


Floor concreting work Mason + Labour 2 days 19th jun 2021 20th jun 2021
the the existing tile level.
Design removal Carpenter 1 hr 19th jun 2021 19th jun 2021 In house team work
5 1st floor - logo design Emulsion paint requisition
Paint Work as per new color Painter + procurement 6 to 8 hrs 19th jun 2021 20th jun 2021 raised as per color code
provided.
Removal of polish Painter 4 hrs 19th jun 2021 20th jun 2021 In house team work
6 1st floor - Lift wall Emulsion paint requisition
Paint Work as per new color Painter + procurement 4 hrs 19th jun 2021 20th jun 2021 raised as per color code
provided.
Emulsion paint requisition
Paint work on return grill as per
7 Excellence Center Painter + procurement 3 hrs 20th jun 2021 20th jun 2021 raised as per color code
new color
provided.
Notice board to remove Carpenter .5 hrs 20th jun 2021 20th jun 2021 Need to inform to HR/Admin
8 1st floor - Landing area
surface finish work Painter .5 hr 20th jun 2021 20th jun 2021 In house team work