15.06.

2023
VIP/EXECUTIVE ROOM
Internal Scheme for VIP Room – BOI status

False Ceiling work (Gypsum) in Room Sample fixing in progress, material available for room.
3 TRACK SLIDING DOOR Materials for aluminium frame arriving at site on 15/6, sample ready by 19th June
Balcony Railing work Material available, fixing in progress.
Wall painting To be done at last
WALLPAPER
WOODEN PANELLING FINISHED WITH LAMINATE AS PER SELECTION
A team for Interior Design – Wooden panelling, Flooring, Wallpaper of Guest house
DECORATIVE MDF GRILL BOARD NS-W.4 Rooms is visiting Guest house on 16/6/23. Materials and Work progress will be
Wooden flooring finalized with the team and shared on 16/6/23
Completed upto 2nd floor, bathroom tiles not yet procured (order placed with NITCO).
Floor Tiles work All balance tiles procured by BHEL/BP
Main door with Lamina Flush door available, Lamina shade to be communicated from PE-Infra by 17/6/23
False Ceiling work in Toilet Toilet False Ceiling : New item (moisture resistant) in 3rd deviation
Sanitary Fixtures Not yet procured. List shared with BHEL/BPC.
CORRIDOR
GYPSUM BOARD FALSE CEILING WITH LED STRIP COVE LIGHTING False ceiling material available, cove light not yet procured
Wall Painting work Last work (Shades already approved)

GLO METAL WALL DECOR BOARD PANELLING Not yet procured, Interior design team to finalize design by
DECORATIVE GRILL JALI PATTERN WITH BACKLIGHTING FOR 17/6/23
CORRIDOR CEILING
EXTERNAL FINISH
ACP CLADDING - AS PER APPROVED BRAND AND SHADE
To be done along with structural glazing work from 21.06.2023
TILE CLADDING AS /APPROVAL
Not yet approved
Structural glazing (toughen and Fixed clear glazing)
Work start from 21.06.2023
Steel pergola at terrace level
Material not yet procured
External Paint
External Paint completed , tiles, cladding, glazing, ACP work balance
Periphery

• Compound wall area clearance by 18/6/23, work start from 20/6/23


• Road/Paver block/Drain work to start along with compound wall
Pending/ Critical Issues

1) HVAC- Firefighting- Electrical Points Interface Fouling (Engineering to resolve the


issue)
2) Additional lighting fixtures is not in scope of BHEL/BPC.
3) Many Bought out items to be procured by PVUN-HR as per finishing schedule
already provided for Guest house.