2023 (Thursday) Current days: 9 days Progress work: Dining Area Deliver ceiling and electrical materials Demolish kitchen walls Ceiling framing at Dining area Cove Ceiling at Dining Electrical for lighting of ceiling Progress work: Kitchen Area Demolish Kitchen walls Dismantle Kitchen Cabinet Demolish wall for refriferator Haul debris Electrical for lighting of kitchen Progress work: Tatami Demolish walls for continuous Tatami walls Progress work: Kid’s room Demolish wall to prepare for sliding door Relocation of switches Progress work: Master Bedroom Installation of cove ceiling Primer painting for ceiling Electrical for lighting Relocation of switches Progress work: Hallway Installation of ceiling at hallway Time Frame Timeframe (As per FIRST phase agreed signed contract) Design MOBILIZATION CEILING WORKS & WALL PARTITIONS (2 weeks) Kitchen Cabinets (3 weeks) Painting works at walls (2 weeks) Painting works at ceilings (2 weeks) Electrical works (2 weeks) Plumbing works (2 weeks) Glass and Mirror (2 weeks) Post construction (General Cleaning) (1 weeks) First Billing Action Plan For finalization this week Laminated Flooring (Matimco) Glass and doors for Tatami (Bifold) Windows at kitchen Parksuites Finish Project: Kristoffe Abellera Construction Update Start of Construction: January 26, 2023 (Thursday) Current days: 20days Progress work: Dining Area 90% ceiling Install lighting 90% painting on ceiling Primer painting on walls Progress work: Dining Area 90% ceiling Install lighting 90% painting on ceiling Primer painting on walls Progress work: Hallway 100% ceiling Install lighting 90% painting on ceiling Primer painting on walls Progress work: Living area 100% ceiling Install lighting 90% painting on ceiling Primer painting on walls Progress work: Living area 100% ceiling Install lighting 90% painting on ceiling Primer painting on walls Fabrication of kitchen cabinets Construction Update Start of Construction: March 10, 2023 (Thursday) Current days: 20days