Phase 1 Cost
Replace roof sheeting (only, framework should be fine) with a GI material and
add an insulation/heat shielding.
Move electrical switch from small front room to outside and build a cupboard
round it.
Cut in and add new doors for new bathroom, new CR and new bedroom
Remove and block up air bricks in small front room. (use one for the
bathroom extractor fan?)
Replace ceilings in new bathroom, CR, and bedroom, and kitchen (gypsum?)
LED spotlights in bathroom, CR, and kitchen, and standard pendant light
fitting in new bedroom.
Install new bath with shower fitting, large sink, and toilet in bathroom and
toilet and small sink in CR
New tile floor in bathroom, CR, and bedroom, and wall tiling around bath.
Install a new water source, electrical socket, and waste pipe into septic tank in