CASA MARIA RESTORATION, REPAIRS AND UPGRADES: [Phase 2]

1. First Floor Guest Room Repairs:


Clothes cabinet damaged by infestation of termites. Strip down of entire old
clothes cabinet; cleaning; concrete ceiling of floor with sealing compound;
reconstruction of cabinets old design; plastering, sanding and repainting;
installation of new electrical wirings, lighting and switches. (COMPLETED)
2. The tearing down of the old stinky main drain of the house. The
construction of a deeper, wider and waterproofed watercourse made with
cleanouts every meters. The whole canal is slanted all the way from the
downspout from the beginning near the kitchen to the exit outside the fence.
Slope is 50 cm. from beginning to end. (COMPLETED)
3. The tearing down of the back gate. To include two nature damaged columns
slanting and causing weakening of the old beam supporting the wooden roof
likewise damaged by nature. Building of two new columns with steel
reinforcement from the foundations to the steel reinforced beams.
Installation of long span roofing. Electrical installation for lighting and
switch. (C0MPLETED)
4. Master’s bedroom water leaks. Roof treated with water sealants. Leaky walls
reviewed and leaking areas treating with water proofing compound. End of
window where a nature caused wood degeneration found and sealed.
(COMPLETED)
5. Kitchen ceiling damage. Damaged ceiling board removed, replaced and
plastered and painted.
6. Installation of roll up rattan curtains in dining room windows. Application of
sanding sealer for curtain. (COMPLETED)
7. Replacement of water sink from clay pot to ceramic made at bridge patio
coming from dining room to main bedroom. Installing new plumbing for the
sink. (COMPLETED)
8. Painting of ceiling in Living room in last few days.