Professional Documents
Culture Documents
Ref: ThUp/032412/1208
5. Floor Tiles: removal and fixing of floor tiles and skirting in new and
old construction area.
Tile pattern: the tile as current if found otherwise a similar tile
pattern will be used.
7. Supply and fixing Panel Doors with lock/handle silver colours for the
whole villa and main door polishing with 2 panels.
Payment Terms:
1. Advance - 30%
2. 25% after 15 days (after completion of tile work including bathroom, complete
electric work, fixing doors and windows.
3. 25% after 30days kitchen complete and other remaining work
4. 20% after handover
A) This estimate is only for complete job done of entire villa including existing
extension and old area.
B) All necessary approvals/entry passes if any water and electricity supply if
required is the responsibility of client and cleaning the debris in included in
this quote.
C) The work shall commence only after approval of this quotation.
D) This quotation is valid only if confirmed within 10 days.
E) The job shall be completed within 45days from the date of approval of
quotation.
F) In case of any delay from contractor after 45 days the penalty will be 1000
AED per day.