Outstanding Material List (62SAV)

Items Remarks
1 Glass Wall at Conference (Level1-2) Check update/Status (CW)
Approved by Client; already submitted
2 Furniture (1st Batch) the Quotation from Supplier; QS to
Proceed
Furniture (2nd Batch) including Cabinet For Approval from client; Waiting for
3
and Plantbox the revised quotation from Supplier
Waiting for the revised quotation from
4 Built-in Cabinets Supplier, Finishes subject for clients
approval.
Already inform site team to set date
5 Existing Furniture (Changi and 80) tentive end of October/ when site is
readyfor furniture
Waiting for suppliers quotation,
6 Quartz
Approved by Client
7 Mirror with cove Waiting for suppliers quotation
8 Laminate for Accent walls, Carpentry, etc.
9 Vinyl Tiles Site team will set for delivery date
10 SWFA Nov. 1 to deliver
11 Lights Oct. 27 to Deliver
12 Light weight Concrete Superseded
13 Tile Cement Grout Color Approved
14 Tiles at Roof Deck Site team will set for delivery date
15 Skirting system For quotation
16 Tile Trim (Stainless steel) Approved, Site Team will proceed
17 Urinal Partition and Cubicle Site team will set for delivery date
18 Granolithic Floor Finish
19 Staircase Door
Samples will be delivered Oct. 31 for
20
Epoxy Flooring Clients Approval