You are on page 1of 2

Annex-1

Sr. As Per NEA Observation Contractor’s Clarification NEA Observation


No. Submission
1. Foundation Plan In Table Heading 2.1.2- Confirmed, Reference document will be Noted
Excavation work the reference approved foundation plan /Drawings.
document column is mentioned
as Foundation Plan. We
understand the reference
document is the Approved
Foundation Plan and Drawings
Kindly verify
2 Testing of In Table 2.6 Concreting-Sub- Testing of concrete cubes will be done as per Noted. However, no. of Cubes for testing
Concrete cubes heading 214-Testing of Concrete contract agreement. Will be done in house shall be casted strictly in line with the
for compression Cube, the Quantum of Check- wherever possible if in house testing not requirement of IS 456 & 516 for each of
strength. 7Days Contractor is mentioned as one possible. May be done at third party lab and we the concrete batch.
or 28 Days. set per substation by third party will be inform to NEA.
lab test. We understand that
rest of the cube sampling and
testing shall be done in house
with record. Kindly elaborate
3 Masonry work In Table 2.7-Masonry work- Sub- Confirmed Quantum of check will be 100%. Noted
heading 2.7.2-Plumb &
Alignment the Quantum of
check-Contractor is mentioned
as random. We understand that
the alignment should be
accurate for any structure to be
constructor hence, the Quantum
of Check-Contractor should be
12.0%.
4 The quarry site plan may kindly Unable to understand which types of plan Please provide a details of quarry site
be provided for both the required. Please suggest contract reference alongwith the material to be extracted viz
substation sites clause for the same a viz requirement of material at site.
Kindly Refer Pg- 6-B-1-27
5 The supplier for all the material Confirmed, Supplier/Make for the material i.e. Noted
should be from the Approved stone aggregate sand, Cement, Bricks &
Supplier list Reinforcement Steel will be as per approval
from NEA.
6 FQP for Aggregates, pre & post Confirmed Noted
pouring check, Plumbing &
Sanitary installation, Floor
finished & allied works, Doors,
windows Shutters etc. and
painting may please be included
suitably
7 Wherever reference document Confirmed Noted
to be mentioned. It should
approved document, approved
drawing. Relevant standard
should be mentioned.

You might also like