THE DISTRICT TOWER

Type of Meeting : ID Coordination Meeting 65


Date : 3 September 2020 Next Meeting
Time : 12:00 pm Date : 10 September 2020
Venue : Virtual meeting Time : 12:00 pm
Initiator / Typist : mfk (3+1 This Page) Type of meeting : Video conference

Initial ATTENDEES ORGANIZATION Copies to


SMAK Sheikha Maryam Al Khalifa Noor Enterprises Holding All Present
(NEH)

IH Mr. Iman Hassein Architecture 360


mfk Mohd Firdaus (A360)

XS Mr. Xavier Singh Cebarco Bahrain


(CB)

CVN Mr. CV Nathan Alliance Project


(AP)
 
 
 
 
 
 
 
 
Agenda:
1. Basement
2. Ground Floor
3. 1st Floor
4. Typical Floor
5. 13th Floor
6. 14th Floor
7. Others
8. Adjournment of Discussion
 
 
 
 
   
 

EA1295/TDT/IDCM-65/20200903/mfk 
                                
THE DISTRICT TOWER – ID Coordination Meeting No. 65
ITEM ACTION BY STATUS/DUE
1) Basement
1.1 A360 forwarded price for light fitting from Restoration Hardware NEH IN PROGRESS
without shipping cost for NEH review.
1.2 A360 forwarded cost quotation for Basement ablution door for NEH NEH IN PROGRESS
review.
2) Ground Floor
2.1 A360 forwarded the carpet design based on provided vector image NEH IN PROGRESS
by NEH for NEH review dated 3 September 2020.
2.2 NEH to confirm budget & design for ground floor chandelier for ED NEH ON-GOING
to proposed.
2.3 A360 to review shop drawing for onyx feature wall. CB/AP 16/08/2020
*PMN: A360 issued NRRS 356. CB/AP to update the resubmission dates
on 16 August 2020.
2.4 A360 to resent shop drawings for stone louvers in horizontal line for A360 03/09/2020
NEH review.
2.5 A360 issued SI 163 for approved Aluminium window option 1b by CB IN PROGRESS
NEH.
2.6 ED approved Entrance planter box drawing submitted by A360. CB IN PROGRESS
*PMN: NEH approved planter box drawing on a note height should be
similar to approved rendering. CB to arrange mockup for NEH review.
2.7 A360 submitted aluminum sample material for ground floor main CB IN PROGRESS
entrance door to NEH for review and approval.
*PMN: CB to provide cost of both materials plus automated door.
2.8 NEH requested ED to propose other options other than leather NEH IN PROGRESS
which is more durable for Charging station sitting.
*PMN: A360 proposed options other than leather for Charging station
sitting for NEH review.
2.9 A360 shared the approved Ground floor FHR detailing to Krin for A360/KRIN IN PROGRESS
developing Shop drawings.
2.10 A360 submitted ground floor sivec reception table for NEH NEH IN PROGRESS
approval.
*PMN: A360 shared images of grommet for reception table for NEH
review.
2.11 ED requested sample piece of charging station wireless charger BK IN PROGRESS
and USB port from Bukamal.
3) 1st Floor
3.1 CB reported male toilet calacatta tiles dry lay will be ready after CB IN PROGRESS
female toilet tiles installation complete.
4) Typical Floor (2nd to 12th Floor)
4.1 NEH to review on Pantry cabinet (J03) shop drawing. NEH IN PROGRESS
*PMN: A360 forwarded costing of Venaro white and Glass finish for NEH
review.

EA1295/TDT/IDCM-65/20200903/mfk Page 2 
                                
THE DISTRICT TOWER – ID Coordination Meeting No. 65
ITEM ACTION BY STATUS/DUE
5) 13th Floor
5.1 NEH to review Pantry cabinet (J06) shop drawing. NEH IN PROGRESS
*PMN: A360 forwarded costing of Venaro white and Glass finish for NEH
review.
6) 14th Floor
6.1 A360 forwarded freight charges of sanitary items for VIP area from NEH IN PROGRESS
Kallista UK for NEH review.
6.2 CB/AP submitted 14th floor common pantry feature wall shop CB/AP 16/08/2020
drawing.
*PMN: A360 issued NRRS 356. CB/AP to update the resubmission dates
on 16 August 2020.
6.3 CB/AP submitted shop drawing for lift lobby feature wall (Sivec + CB/AP 16/08/2020
Mirror) shop drawing.
*PMN: A360 issued NRRS 356. CB/AP to update the resubmission dates
on 16 August 2020.
6.4 ED reported Shop drawings for CEO and COO column shelving ED IN PROGRESS
area J04A, J04B and J04C to be revised after I beam cladding
detail approval.
*PMN: ED to submit I beam cladding detail for NEH review.
6.5 A360 forwarded the Carpet sample images with cost comparison NEH IN PROGRESS
for NEH review.
6.6 A360/CB reported due date for placing order for Aero lighting ON HOLD
quotation is 18 January 2020.
6.7 CB/AP to resubmit 14th floor glass elevation detail with the inclusion CB IN PROGRESS
of associated ceiling works.
*PMN: CB reported submission of MEP services layout to GEMAC. CB to
discuss the requirement of drop ceiling for MEP services with A360 and
ED.
6.8 A360 submitted VIP pantry cabinet shop drawing for NEH review. NEH IN PROGRESS
*PMN: NEH to review the proposals from ED on backsplash.
6.9 CB/AP submitted the sample board for all Common pantry finishes NEH IN PROGRESS
for NEH approval on Oxford river paint (PT 04a).
6.10 ED to forward reference images of Green room to CB/AP for ED IN PROGRESS
developing shop drawings.
6.11 A360 shared cost quotation received from Cebarco and Kallista UK NEH IN PROGRESS
supplier for Common pantry sink and mixer for NEH review.

7) Others
7.1 ED shall issue drawing on all approved layout by the client for shop INFO
drawing purposes in order to expedite the approvals.
7.2 All agreed for AP to proceed with mock-up base on material INFO
selection by NEH before proceeding with full procurement of the
materials.

EA1295/TDT/IDCM-65/20200903/mfk Page 3 
                                
THE DISTRICT TOWER – ID Coordination Meeting No. 65
ITEM ACTION BY STATUS/DUE
7) Others (Con’t)
7.3 A360 forwarded epoxy color scheme for guard house & substation NEH IN PROGRESS
roof finish for NEH selection.
7.4 CB reported cost for 13th and 14th to be approve and 50% advance INFO
payment to be made before starting with MEP works.
7.5 CB to submit coordinated MEP services drawing for all floors with CB IN PROGRESS
color differentiation of each MEP services.
7.6 ED forwarded render images of Marble signage option for NEH NEH IN PROGRESS
review.
*PMN: A360 reported design intent to be shared with Krin if NEH
approves the Sivec proposal.
7.7 A360 to forward Krin’s shop drawings of ground floor main entrance A360 03/09/2020
backlit signage for NEH review.
7.8 ED submitted final FFE drawing to NEH for review & approval. NEH IN PROGRESS
7.9 A360 reported BWS submission for SI 100 by end April. BWS/A360 IN PROGRESS
*PMN: BWS to update on SI 100 status within two weeks.
7.10 NEH requested for all parties to adhere and to remain committed INFO
on all stipulated submission dates.
7.11 CB/AP submitted samples of laminated finishes for Ground floor NEH/ED/ IN PROGRESS
charging station. A360
*PMN: Selection of laminate kept on hold until material for Charging
station sitting area is selected.
7.12 CB/AP to update pending submission dates on 16 August 2020. CB/AP 16/08/2020
7.13 A360 submitted revised cost quotation and schedule for both Glass NEH IN PROGRESS
and timber door for NEH review.
8) Adjournment of Meeting
8.1 Meeting adjourned at 12:30 pm. Next meeting is scheduled as
follows:
Date: 10 September 2020
Type of meeting: Video conference
Time: 12:00 pm
 
 
 
 
 
   

EA1295/TDT/IDCM-65/20200903/mfk Page 4 