Professional Documents
Culture Documents
Mr. W.L. Upali Project Manager (PM/Sanken) Sanken Construction (Pvt) Ltd
Excused
1
2. Lightning protection system
(a) PM/Sanken informed that the Faraday cage system will complete on 28th August 2023.
(b) Chairperson/MFBC instructed to provide proper supervision to avoid damaging the interlock
paving.
(c) SM/Sanken agreed to hand over the lightning protection system on 28th August 2023 to the
Client.
2) Emergency lights
a) In PRM 139, PM/Sanken agreed to submit numbers of missing emergency lights in a chart
with dates.
3) Generator
a) PM/Sanken informed that the generator is already jacked up and dismantling of wiring work
would be started soon.
b) PM/SEC instructed to call the inspections soon.
PM/Sanken informed that Sanken would not chair the meeting, the Client, and the Consultant to be
participated for the meeting with the fire services department.
(1) Instructions were given to Sanken to proceed the following work as per the fire department
visit on 08-02-2023.
(i) Place a 25 ltr dry powder fire extinguisher in the diesel tank at lower basement. –
PM/Sanken informed that the available capacity of dry powder fire extinguisher is 100L at
the market. Chairperson/MFBC instructed to check market availability of 25 ltr dry
powder fire extinguisher.
(2) As per PRM 135, Items to attended after receiving fire departments’ written comments by the
Client
(i) Shift the landing valves in to the fire lobbies
(ii) All the car parking slots needs to cover by sprinklers
(iii) “Exit” sign boards should have battery backup
2
a. Mezzanine floor near the lecture hall
b. 3rd floor near the void
c. Ground floor near the steel stair case , change the direction of fire
door
(ii) Separating the diesel tank from the pump in lower basement
3. Fire lift:
The firefighter switch glass is deemed unsafe for users and should be replaced with safe glass. -
PM/Sanken informed that the minimum glass thickness available at the market is 2mm.
Chairperson/MFBC instructed to fix a suitable tool hang to break the glass with a sharp end in one
side.
(5) MOU 2 – In PRM 138, Chairperson/MFBC instructed SEC to submit new MOU for the fire services
departments’ requirements.
1. Cyclorama screen protection – FE/FOM noted that a quotation received and the Client will
do procurement.
2. Handing over of timber doors in auditorium – In PRM 140, PM/Sanken stated that
modification work of 4 numbers of doors is in progress.
3
4. Hydrotherapy area in 11th floor
PM/Sanken requested the instruction to proceed work.
CE(D)/SEC informed that design office already forwarded instruction for the quarry raised by
the Sanken.
PM/SEC stated that PE(M&E)/SEC agreed to visit site on 25th August 2023 to check the
Hydrotherapy area
Chairperson/MFBC informed that the geezer from 5th floor could use for the 11th floor.
5. CCTV isolators
In PRM 139, DR/FOM agreed to procure the 14 numbers of plastic lockable enclosures for
CCTV isolators and requested from Sanken to install them.
4
141.2.13 Balance keys to hand over to the Client
FE/FOM stated that the keys of AHU room are still not handed over to the client.
141.2.17 Defects in FCUs – In PRM 140, FE/FOM tabled a list of defects in FCU s to attend.
Checked by,
………………………..
Eng. Damith Perera
Project Manager
State Engineering Corporation