The inspection report provides details on the structural works completed from October 23 to November 17 for a subdivision project in Angeles City, Pampanga, including welding of base plates and shipping containers, cutting additional openings in containers, installing roof and floor framing, pouring exterior slabs and stairs, and applying rust converter and epoxy primer to steel frames that was 95% completed but slowed by material shortage and typhoon.
The inspection report provides details on the structural works completed from October 23 to November 17 for a subdivision project in Angeles City, Pampanga, including welding of base plates and shipping containers, cutting additional openings in containers, installing roof and floor framing, pouring exterior slabs and stairs, and applying rust converter and epoxy primer to steel frames that was 95% completed but slowed by material shortage and typhoon.
The inspection report provides details on the structural works completed from October 23 to November 17 for a subdivision project in Angeles City, Pampanga, including welding of base plates and shipping containers, cutting additional openings in containers, installing roof and floor framing, pouring exterior slabs and stairs, and applying rust converter and epoxy primer to steel frames that was 95% completed but slowed by material shortage and typhoon.
, Don Bonifacio Subdivision Duration of Scope: Oct 23 - Present
Location : Angeles City, Pampanga Date of Inspection: Nov 17, 2020
INSPECTION REPORT STRUCTURAL WORKS
ITEM Date Date
ACTIVITY Remark (Comment) NO. Started Ended 1. Base Plate and Shipping Containers Cutting of holles on site and a. Base Plate Welding to pedestals 24-Oct 24-Oct welded on all pedestals
Base plate to Shipping Container
b. Shipping Container placements 27-Oct 27-Oct connection fully welded 2. Cutting of shipping container Additional opening at Kitchen Area a. Shipping Container Openings 28-Oct 13-Nov approved by client, Nov 7 3. Welding of frames and connections a. Roof Framing 31-Oct 4-Nov Truss and Purlin Flooring connecting both shipping b. Floor Framing 29-Oct 30-Oct containers 4. Exterior slabs
a. Mesh Size and Arrangement 10-Nov 14-Nov
on going curing b. Dimension and Placement of Exterior Deck 10-Nov 14-Nov c. Cement, Sand and Gravel Ratio 10-Nov 14-Nov 5. Waterproofing of Septic Tank N/A N/A OWNER SUPPLIED a. Leak Test Application of Rust Converter and epoxy primer for all steel On going installation of frames 6. frames and shipping container 28-Oct - 95% done, material shortage 7. Stair Installation a. Rebar Size and Arrangement 9-Nov 14-Nov b. Dimension of Slab/Stairs 9-Nov 14-Nov on going curing c. Cement, Sand and Gravel Ratio 9-Nov 14-Nov
8. Others: (Weather Condition, Material Specs major typhoon on nov 12, no
works done
Tools etc.) 11-Nov 17-Nov
Inspected by : Engr. Karry Sue Adawey Approved by : ___________________