Agreed USAID
Item Estimated
Work Item Description Reimbursement Amount Terms
# Completion Dates
(USD)
Subgrade of Access Road upto 49800 ft delayed due to Resurvey,Redsign and change in
421,925 Nov/18 Feb/19
Length; alignment.
Base Course of Access Road upto 49800ft delayed due to Resurvey,Redsign and change in
1,954,144 Jul/18 Mar/19
Length, Drainage Structures of Access Road alignment.
Care and Handling of water for Power House PH-IV site land acquisition issue.
191,571 Apr/18 Nov/18
IV Building Affiliated Structure PH-IV foundaion design has been changed.
Excavation, Reinforcement, Concreting and Feeder tunnel was realigned & due to which delay in
19 239,364 Apr/19 Nov/19 Sep/19
Backfilling of Feeder Channel (Complete) feeder channel happened.
Completion
Estimated
Milestone Payment Dates as per
Description Original Dates Completion Reasons of Delays
No. $ Revised Base
Dates
line
The main reason for the delay in project is Law & Order situation in the Project area i.e. North Waziristan Agency as
* working days are reduced as there are curfew imposed oftenly.
* working hours are less due to security threats and work is started in the morning when bomb disposal squad gives clearance given by the Armed forces.
* Night shift is not possible and only only work is done only in day time.
* Working on multiple and distinct sites is not possible.
Kurram Tangi Multipurpose Dam Project Stage-1
Kaitu Weir Irrigation and Power Project
Milestone Payment Schedule for Civil Works
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line
delayed due to
Subgrade of Access Road upto
Nov/18 Apr/19 Resurvey,Redsign and change At the discretion of PD WAPDA. Same as SR.No.6
49800 ft Length;
in alignment.
Miscellaneous Structural,
Ph-IV site acquisition
Architectural, Finishing works (DPC,
Dec/18 Jun/19 issue.change in design for ph-IV Discussed above
Tile Work, Plaster etc.) for Power
foundation.
House IV Building Structure
20 4,349,725 Apr/19
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line