Kurram Tangi Multipurpose Dam Project Stage-1

Kaitu Weir Irrigation and Power Project


Milestone Payment Schedule for Civil Works

Agreed USAID
Item Estimated
Work Item Description Reimbursement Amount Terms
# Completion Dates
(USD)

General Items including Dispensary, First Aid,


Upon
1 Laboratories, and Installation and Maintenance of 177,203 Apr/17
Completion
Engineer's Radio Communication System

Topographic Survey and Ground Investigations Upon


2 1,265,806 Apr/17
Survey till completion and submission of Reports Completion

Construction of Coffer Dam-1 & Dewatering Upon


3 555,556 May/17
Arrangement (Stage-1) for Undersluices Completion

Completion of Inlet & Outlet Portal of Feeder Tunnel,


Excavation and Lean Concrete of Power House IV Upon
4 877,215 Jun/17
Building, Excavation & Lean Concrete for Completion
Undersluices

Earthwork in all types of soil and rock for 24600 ft


Upon
5 Length of Access Road 456,381 Jul/17
Completion

RCC for Power House IV Building, Earthwork upto Upon


6 1,087,643 Sep/17
49800ft Length of Access Road Completion

Complete Excavation, Lean Concrete upto RCC


Level for Weir Structure Block 1; Cutting and Lining
Upon
7 upto 14170 ft length of Spaira Ragha Canal; 2,531,618 Oct/17
Completion
Compaction; Backfilling & Riprap for Undersluices.
Subgrade of Access Road upto 24600 ft Length

Subgrade of Access Road upto 49800 ft Length;


Upon
8 Excavation and Shotcrete for 2033 ft Length of 2,245,733 Nov/17
Completion
Feeder Tunnel

Structural Concreting upto 2nd Stage for


Upon
9 Undersluices; Base Course of Access Road upto 1,300,150 Dec/17
Completion
24600ft Length

Base Course of Access Road upto 49800ft Length,


Upon
10 2nd Stage Concrete for Power House IV Building; 2,304,673 Jan/18
Completion
Drainage Structures of Access Road

Complete Excavation, Lean Concrete upto RCC


Upon
11 Level for Kaitu Weir Structure Block 4; Concrete 1,586,094 Feb/18
Completion
Lining of Feeder Tunnel for 2033 ft length.

Construction of Coffer Dam 2, Prestressed Concrete


for Power House IV Building; Cutting & Lining of
Upon
12 Power House IV (Afterbay, Spill Channel) for 3375ft 3,899,930 May/18
Completion
Length; Excavation & Drainage arrangement for Silt
Excluder
Agreed USAID
Item Estimated
Work Item Description Reimbursement Amount Terms
# Completion Dates
(USD)
Handling of Water for Power House IV Building,
Cutting Lining of Spill Channel of Power House IV
Upon
13 (After bay, Spill Channel) upto 6750ft Length; 3,915,198 Jul/18
Completion
Cutting, Filling, Structure and PC Lining of Spaira
Ragha Canal upto 28340 ft length

Drains and Plumbing Works, Backfilling & Riprap for


Upon
14 Power House IV Building, Excavation & Shotcrete of 1,859,061 Sep/18
Completion
Feeder Tunnel upto 4067ft Length

Finishing Works for Power House IV Building,


Complete Spaira Ragha Canal Pump House, Cutting Upon
15 3,659,922 Oct/18
& Lining for 10125ft of Power House IV (After bay, Completion
Spill Channel)

Complete Excavation, Lean Concrete upto RCC


Upon
16 Level for Kaitu Weir Structure Block 3; Concrete 1,586,094 Nov/18
Completion
Lining of Feeder Tunnel upto 4067 ft length.

Complete Excavation, Lean Concrete upto RCC Upon


17 1,083,219 Jan/19
Level for Weir Structure Block 2 and 5. Completion

Cutting and PC Lining for Spaira Ragha Canal upto


Upon
18 42510 ft length; Complete Excavation & Lean 2,068,348 Apr/19
Completion
Concrete upto RCC Level for Weir Structure Block 6

Excavation, Reinforcement, Concreting and Upon


19 239,364 Apr/19
Backfilling of Feeder Channel (Complete) Completion

Backfilling, Rip Rap for Kaitu Weir; Procurement &


Installation of Gates upto Commissioning (i.e. Silt
Upon
20 Excluder, Kaitu Weir, Spaira Ragha Head Regulator 4,349,725 Apr/19
Completion
and Sheratalla Head Regulator), Excavation and
Concrete Lining upto 6100 ft length of feeder tunnel

Total Amount ($) 37,048,933


Kurram Tangi Multipurpose Dam Project Stage-1
Kaitu Weir Irrigation and Power Project
Milestone Payment Schedule for Civil Works
Completion
Estimated
Milestone Payment Dates as per
Description Original Dates Completion Reasons of Delays
No. $ Revised Base
Dates
line

General Items including Dispensary, First Aid,


Laboratories, and Installation and
1 177,203 Apr/17 Mar/17 Mar/17 Activity Completed
Maintenance of Engineer's Radio
Communication System

Topographic Survey and Ground


2 Investigations Survey till completion and 1,265,806 Apr/17 Apr/17 Apr/17 Activity Completed
submission of Reports

Construction of Coffer Dam-1 & Dewatering


3 555,556 May/17 Feb/17 Feb/17 Activity Completed
Arrangement (Stage-1) for Undersluices

Work could not start early as benchmark level was


Excavation & Lean Concrete for shifted from Bannu to Spinwam Site and due to flas
396,690 Jan/18 Apr/18
Undersluices flood on 28/06/2017 coffer dam was breached out
which caused delay.

Land Acquisition Issue at PH-IV site and change in


4 Excavation and Lean Concrete of Power Jun/17 design of foundation. i.e micro pile foundation
361,246 Dec/17 Nov/18
House IV Building, proposed instead of raft foundation as shale is
encountered while excavation.

Land Acquisition Issue at site. True ownership of land


Completion of Inlet & Outlet Portal of Feeder is unknown as the land is owned by tribe not a single
119,279 Nov/19 Oct/19
Tunnel person and the matter is under subjudice of Assistant
Political Agent Mirali.

Earthwork in all types of soil and rock for


delayed due to Resurvey,Redsign and change in
5 24600 ft Length of Access Road 456,381 Jul/17 May/18 Oct/18
alignment.

Land Acquisition Issue at PH-IV site and change in


RCC for Power House IV Building, Earthwork design of foundation. i.e micro pile foundation
6 1,087,643 Sep/17 Nov/18 Jan/19
upto 49800ft Length of Access Road proposed instead of raft foundation as shale is
encountered while excavation.
Completion
Estimated
Milestone Payment Dates as per
Description Original Dates Completion Reasons of Delays
No. $ Revised Base
Dates
line

Complete Excavation, Lean Concrete upto


RCC Level for Weir Structure Block 1;
Compaction; Backfilling & Riprap for 1,004,879 Mar/19 Oct/18 Work could not start early as benchmark level was
Undersluices. Subgrade of Access Road upto shifted from Bannu to Spinwam Site and due to flas
7 Oct/17
24600 ft Length flood on 28/06/2017 coffer dam was breached out
which caused delay.
Cutting and Lining upto 14170 ft length of
1,526,739 Jul/18 Oct/18
Spaira Ragha Canal;

Subgrade of Access Road upto 49800 ft delayed due to Resurvey,Redsign and change in
421,925 Nov/18 Feb/19
Length; alignment.

8 Nov/17 Land Acquisition issue and change in design as three


Excavation and Shotcrete for 2033 ft Length different stratas are merging at that point and the rock
1,823,808 Dec/18
of Feeder Tunnel encountered is soft for which rock support design is
revised.

Work could not start early as benchmark level was


Structural Concreting upto 2nd Stage for
shifted from Bannu to Spinwam Site and due to flas
9 Undersluices; Base Course of Access Road 517,363 Dec/17 Jun/18 Oct/18
flood on 28/06/2017 coffer dam was breached out
upto 24600ft Length
which caused delay.

Base Course of Access Road upto 49800ft delayed due to Resurvey,Redsign and change in
1,954,144 Jul/18 Mar/19
Length, Drainage Structures of Access Road alignment.

10 Jan/18 Land Acquisition Issue at PH-IV site and change in


2nd Stage Concrete for Power House IV design of foundation. i.e micro pile foundation
350,528 Apr/19
Building; proposed instead of raft foundation as shale is
encountered while excavation.
Completion
Estimated
Milestone Payment Dates as per
Description Original Dates Completion Reasons of Delays
No. $ Revised Base
Dates
line

Work could not start early as benchmark level was


Complete Excavation, Lean Concrete upto shifted from Bannu to Spinwam Site and due to flash
541,609 Jul/19 Nov/18
RCC Level for Kaitu Weir Structure Block 4; flood on 28/06/2017 coffer dam was breached out
which caused delay.
11 Feb/18
Land Acquisition issue and change in design as three
Concrete Lining of Feeder Tunnel for 2033 ft different stratas are merging at that point and the rock
1,044,485 Sep/19 Sep/19
length. encountered is soft for which rock support design is
revised.

Work could not start early as benchmark level was


Construction of Coffer Dam 2, Excavation & shifted from Bannu to Spinwam Site and due to flash
747,126 Nov/18 Nov/18
Drainage arrangement for Silt Excluder flood on 28/06/2017 coffer dam was breached out
which caused delay.
Cutting & Lining of Head Race Afterbay, Spill
Channel etc. of Power House IV for 3375ft of
12 May/18 Shifting of benchmark level from Bannu to Spinwam
length. Excavation, Reinforcement,
3,107,892 Feb/19 Feb/19 site. Design has been changed for the silt excluder as
Concreting, Backfilling, Drain holes for PVC
per site Conditions.
Pipes, and Drainage Arrangement for Silt
Excluder
Precast Prestressed Concrete for Power PH-IV site land acquisition issue.
44,911 Dec/18 May/19
House- IV Building Structure. PH-IV foundaion design has been changed.

Care and Handling of water for Power House PH-IV site land acquisition issue.
191,571 Apr/18 Nov/18
IV Building Affiliated Structure PH-IV foundaion design has been changed.

Cutting Lining of Spill Channel of Power


13 Jul/18 depend on feeder tunnel.whereas feeder tunnel is
House IV (After bay, Spill Channel) upto 2,196,889 Apr/18 Apr/19
realigned,redesigned for rock support design
6750ft Length;

Cutting, Filling, Structure and PC Lining of


1,526,739 Jun/19 Mar/19 Shifting of benchmark from Bannu to Spinwam site.
Spaira Ragha Canal upto 28340 ft length
Completion
Estimated
Milestone Payment Dates as per
Description Original Dates Completion Reasons of Delays
No. $ Revised Base
Dates
line

Drains and Plumbing Works, Backfilling &


Site Acquisition issue. Design change for PH-IV
Riprap for Power House IV Building,
14 1,859,061 Sep/18 Nov/18 Jun/19 foundation.Change in Feeder Tunnel Alignment.
Excavation & Shotcrete of Feeder Tunnel
Change in Rock support design for feeder tunnel.
upto 4067ft Length
Finishing Works for Power House IV Building, Ph-IV site acquisition issue.change in design for ph-
1,403,927 Dec/18 Oct/19
Complete Spaira Ragha Canal Pump House, IV foundation.
Cutting & Lining for 10125ft of Power House depend on feeder tunnel.whereas feeder tunnel is
2,196,889 Feb/19 Mar/19
15 IV (After bay, Spill Channel) Oct/18 realigned & rock support design redesigned.
Miscellaneous Structural, Architectural,
Ph-IV site acquisition issue.change in design for ph-
Finishing works (DPC, Tile Work, Plaster etc.) 59,107 Dec/18 Jun/19
IV foundation.
for Power House IV Building Structure
Bhenchmark shifted from Bannu to Spinwam site.
Complete Excavation, Lean Concrete upto
541,609 Jul/19 Dec/18 Coffer dam-I was breached out due to flash flood
RCC Level for Kaitu Weir Structure Block -3.
happened on 28/06/2017
16 Nov/18
Feeder tunnel was realigned & rock support design is
Feeder Tunnel Concrete Lining upto 4067 ft
1,044,485 Nov/19 Jul/19 redesigned due to shale encountered while
length.
excavation.
Bhenchmark shifted from Bannu to Spinwam site.
Complete Excavation, Lean Concrete upto
17 1,083,219 Jan/19 Aug/19 Feb/19 Coffer dam-I was breached out due to flash flood
RCC Level for Weir Structure Block 2 and 5.
happened on 28/06/2017
Cutting and PC Lining for Spaira Ragha
Bhenchmark shifted from Bannu to Spinwam site.
Canal upto 42510 ft length; Complete
18 2,068,348 Apr/19 Aug/19 Mar/19 Coffer dam-I was breached out due to flash flood
Excavation & Lean Concrete upto RCC Level
happened on 28/06/2017
for Weir Structure Block-6

Excavation, Reinforcement, Concreting and Feeder tunnel was realigned & due to which delay in
19 239,364 Apr/19 Nov/19 Sep/19
Backfilling of Feeder Channel (Complete) feeder channel happened.
Completion
Estimated
Milestone Payment Dates as per
Description Original Dates Completion Reasons of Delays
No. $ Revised Base
Dates
line

Backfilling, Rip Rap for Kaitu Weir;


Procurement & Installation of Gates upto Bhenchmark shifted from Bannu to Spinwam site.
Commissioning (i.e. Silt Excluder, Kaitu Weir, 1,488,108 Aug/19 Apr/19 Coffer dam-I was breached out due to flash flood
Spaira Ragha Head Regulator and Sheratalla happened on 28/06/2017
Head Regulator),
20 Apr/19 Feeder tunnel was realigned & rock support design is
Excavation and Shotcrete of respective
1,823,808 Aug/19 Sep/19 redesigned due to shale encountered while
sections of Feeder Tunnel upto 6100 ft length
excavation.
Feeder tunnel was realigned & rock support design is
Concrete Lining of Feeder Tunnel Concrete
1,037,809 Nov/19 Oct/19 redesigned due to shale encountered while
Lining upto 6100 ft
excavation.

Total Amount ($) 36,266,145

The main reason for the delay in project is Law & Order situation in the Project area i.e. North Waziristan Agency as
* working days are reduced as there are curfew imposed oftenly.
* working hours are less due to security threats and work is started in the morning when bomb disposal squad gives clearance given by the Armed forces.
* Night shift is not possible and only only work is done only in day time.
* Working on multiple and distinct sites is not possible.
Kurram Tangi Multipurpose Dam Project Stage-1
Kaitu Weir Irrigation and Power Project
Milestone Payment Schedule for Civil Works
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line

General Items including Dispensary,


First Aid, Laboratories, and
1 Installation and Maintenance of 177,203 Apr/17 Mar/17 Mar/17 Activity Completed
Engineer's Radio Communication
System

Topographic Survey and Ground


2 Investigations Survey till completion 1,265,806 Apr/17 Apr/17 Apr/17 Activity Completed
and submission of Reports

Construction of Coffer Dam-1 &


3 Dewatering Arrangement (Stage-1) 555,556 May/17 Feb/17 Feb/17 Activity Completed
for Undersluices

Work could not start early as


benchmark level was shifted
from Bannu to Spinwam Site
Excavation & Lean Concrete for
Jan/18 Apr/18 and due to flas flood on This activity has been cmpleted now
Undersluices
28/06/2017 coffer dam was
breached out which caused
delay.

Excavation has been completd up to 95


Land Acquisition Issue at PH-IV %. Further excavation would be started
site and change in design of after finalization of VariationOrder of
Approval of variation Order for micro
4 Excavation and Lean Concrete of 877,215 Jun/17 foundation. i.e micro pile Micro-piling because the Engineer has
Dec/17 Nov/18 pile foundation by the Project
Power House IV Building, foundation proposed with raft suggested "not to expose the
Consultant + Project Office.
foundation as shale is Foundation of PH-IV due to its swelling
encountered while excavation. nature" Now it depends upon the
Engineer & the Employer.

Land Acquisition Issue at site. Contractor Jv is planning to


True ownership of land is Excavation with Shotcreting would be complete the concrete and structure
Completion of Inlet & Outlet Portal of unknown as the land is owned completed till Dec-18 but structure work of Inlet & Outlet portal due to
Nov/19 Oct/19
Feeder Tunnel by tribe not a single person and would be completed after completion of the reason work space will not be
the matter is under subjudice of tunnel. available if concreting is done before
Assistant Political Agent Mirali. completion of Tunnel.
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line

Earthwork for Acces Road of PH-IV is Contractor JV is requested to speed


Earthwork in all types of soil and 90 % completd & further can be up the Pace of work.
delayed due to completed within Sep 2018.
rock for 24600 ft Length of Access
5 456,381 Jul/17 May/18 Sep/18 Resurvey,Redsign and change
Road
in alignment.

Land Acquisition Issue at PH-IV It again depends upon the finalization


site and change in design of of Micro-piling VO. RCC as per BOQ PD KTDP will take up the matter
RCC for Power House IV Building,
foundation. i.e micro pile amount will be completed till Jan-19. with local administration for land
6 Earthwork upto 49800ft Length of 1,087,643 Sep/17 Nov/18 Jan/19
foundation proposed in adddition About Access road, already briefed acquisition and survey of Access
Access Road
of raft foundation as shale is above. Now depends upon PD road and work will be started ASAP.
encountered while excavation. WAPDA.

Complete Excavation, Lean


Concrete upto RCC Level for Weir
Structure 1 No Block ; Compaction; Work would be completed till Oct-18.
Mar/19 Sep/18
Backfilling & Riprap for Work could not start early as Access road has already discussed.
Undersluices. Subgrade of Access benchmark level was shifted
Road upto 24600 ft Length from Bannu to Spinwam Site
7 2,531,618 Oct/17 and due to flas flood on
28/06/2017 coffer dam was
breached out which caused
Conractor JV is requested to speed
delay. If we mean to say completion of 14170
Cutting and Lining upto 14170 ft up the pace of work. Project
Jul/18 Sep/18 ft from 35700 ft then it would be
length of Spaira Ragha Canal; Consultants will approve Control
completed max NOV-18.
Joint rates ASAP.
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line

delayed due to
Subgrade of Access Road upto
Nov/18 Apr/19 Resurvey,Redsign and change At the discretion of PD WAPDA. Same as SR.No.6
49800 ft Length;
in alignment.

Land Acquisition issue and


8 2,245,733 Nov/17 change in design as three
Desingn of rock support has been
Excavation and Shotcrete for 2033 ft different stratas are merging at
Dec/18 Feb/19 PD WAPDA to provide land. issued to contractor. Iand acqusition
Length of Feeder Tunnel that point and the rock
issue need to be resolve by PD ktdp.
encountered is soft for which
rock support design is revised.

Work could not start early as


benchmark level was shifted
Structural Concreting upto 2nd
from Bannu to Spinwam Site Contractor JV is requested to
Stage for Undersluices; Base If PH-IV road will be considered then it
9 1,300,150 Dec/17 Jun/18 Sep/18 and due to flash flood on achieve the milestone within the
Course of Access Road upto would be completed within one month.
28/06/2017 coffer dam was timeframe.i.e Oct-2018.
24600ft Length
breached out which caused
delay.
Base Course of Access Road upto delayed due to
49800ft Length, Drainage Structures Jul/18 Jun/19 Resurvey,Redsign and change Discussed Same as SR.No.6
of Access Road in alignment.
Land Acquisition Issue at PH-IV
10 2,304,673 Jan/18 site and change in design of
2nd Stage Concrete for Power foundation. i.e micro pile Depends upon finalization of VO of
Apr/19
House IV Building; foundation proposed instead of Micro-pile.
raft foundation as shale is
encountered while excavation.
Work could not start early as
benchmark level was shifted
Complete Excavation, Lean from Bannu to Spinwam Site
It would be completed According to the
Concrete upto RCC Level for Kaitu Jul/19 Nov/18 and due to flash flood on
dates provided.
Weir Structure Block 4; 28/06/2017 coffer dam was
breached out which caused
11 1,586,094 Feb/18 delay.
Land Acquisition issue and PD KTDP to solve the Land
change in design as three Acquisition issue. Rock
This activity is in delay due to change
Concrete Lining of Feeder Tunnel different stratas are merging at support design has been issued by
Sep/19 Sep/19 in rock support design & land
for 2033 ft length. that point and the rock the Project Consultants. Now
acquisition issue.
encountered is soft for which Contracttor JV is requested to speed
rock support design is revised. up the work.
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line
Work could not start early as
benchmark level was shifted
Construction of Coffer Dam 2, from Bannu to Spinwam Site
It Would be completed According to the
Excavation & Drainage arrangement Nov/18 Nov/18 and due to flash flood on
dates provided.
for Silt Excluder 28/06/2017 coffer dam was
breached out which caused
delay.
Cutting & Lining of Head Race
Afterbay, Spill Channel etc. of Power
12 3,899,930 May/18 Shifting of benchmark level from
House IV for 3375ft of length.
Bannu to Spinwam site. Design It Would be completed According to the
Excavation, Reinforcement, Feb/19 Feb/19
has been changed for the silt dates provided.
Concreting, Backfilling, Drain holes
excluder as per site Conditions.
for PVC Pipes, and Drainage
Arrangement for Silt Excluder
PH-IV site land acquisition
Precast Prestressed Concrete for issue. PH-
Dec/18 May/19 Discussed above Same as SR.No.6
Power House- IV Building Structure. IV foundaion design has been
changed.
PH-IV site land acquisition
Care and Handling of water for
issue. PH- This is a continuos process & would
Power House IV Building Affiliated Apr/18 Dec/18
IV foundaion design has been continue till the completion of PH-IV.
Structure
changed.
depend on feeder
13 Cutting Lining of Spill Channel of 3,915,198 Jul/18 tunnel.whereas feeder tunnel is It Would be completed According to the
Power House IV (After bay, Spill Apr/18 Mar/19
realigned,redesigned for rock dates provided.
Channel) upto 6750ft Length;
support design
Cutting, Filling, Structure and PC
Shifting of benchmark from It Would be completed According to the
Lining of Spaira Ragha Canal upto Jun/19 Feb/19
Bannu to Spinwam site. dates provided.
28340 ft length
Site Acquisition issue. Design
Drains and Plumbing Works,
change for PH-IV
Backfilling & Riprap for Power
foundation.Change in Feeder
14 House IV Building, Excavation & 1,859,061 Sep/18 Nov/18 Jun/19 Discussed above
Tunnel Alignment. Change in
Shotcrete of Feeder Tunnel upto
Rock support design for feeder
4067ft Length
tunnel.
Finishing Works for Power House IV Ph-IV site acquisition issue.
Building, Complete Spaira Ragha Dec/18 Aug/19 change in design for ph-IV Discussed above
Canal Pump House, foundation.

depend on feeder It Would be completed According to the


Cutting & Lining for 10125ft of
tunnel.whereas feeder tunnel is dates provided. However project Project Consultants are requested to
Power House IV (After bay, Spill Feb/19 Mar/19
15 3,659,922 Oct/18 realigned & rock support design Consultants are requested to provide issue the drawings ASAP.
Channel)
redesigned. Tail race, Spill channel drawings.
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
15
No. 3,659,922
$ Oct/18
Dates Revised Base
Dates
line

Miscellaneous Structural,
Ph-IV site acquisition
Architectural, Finishing works (DPC,
Dec/18 Jun/19 issue.change in design for ph-IV Discussed above
Tile Work, Plaster etc.) for Power
foundation.
House IV Building Structure

Bhenchmark shifted from Bannu


Complete Excavation, Lean
to Spinwam site. Coffer dam-I It Would be completed According to the
Concrete upto RCC Level for Kaitu Jul/19 Dec/18
was breached out due to flash dates provided.
Weir Structure Block -3.
flood happened on 28/06/2017
16 1,586,094 Nov/18
Feeder tunnel was realigned &
Feeder Tunnel Concrete Lining upto rock support design is
Nov/19 Jul/19 same as Sr.No 11
4067 ft length. redesigned due to shale
encountered while excavation.

Bhenchmark shifted from Bannu


Complete Excavation, Lean
to Spinwam site. Coffer dam-I It Would be completed According to the
17 Concrete upto RCC Level for Weir 1,083,219 Jan/19 Aug/19 Feb/19
was breached out due to flash dates provided.
Structure Block 2 and 5.
flood happened on 28/06/2017

Cutting and PC Lining for Spaira


Bhenchmark shifted from Bannu
Ragha Canal upto 42510 ft length;
to Spinwam site. Coffer dam-I It Would be completed According to the
18 Complete Excavation & Lean 2,068,348 Apr/19 Aug/19 Mar/19
was breached out due to flash dates provided.
Concrete upto RCC Level for Weir
flood happened on 28/06/2017
Structure Block-6

Excavation, Reinforcement, Feeder tunnel was realigned &


19 Concreting and Backfilling of Feeder 239,364 Apr/19 Nov/19 Sep/19 due to which delay in feeder same as Sr.No 11
Channel (Complete) channel happened.

Backfilling, Rip Rap for Kaitu Weir;


Procurement & Installation of Gates Bhenchmark shifted from Bannu
upto Commissioning (i.e. Silt to Spinwam site. Coffer dam-I It Would be completed According to the
Aug/19 Apr/19
Excluder, Kaitu Weir, Spaira Ragha was breached out due to flash dates provided.
Head Regulator and Sheratalla flood happened on 28/06/2017
Head Regulator),

20 4,349,725 Apr/19
Completion
Estimated
Milestone Payment Original Dates as per
Description Completion Reasons of Delays Remarks from Contractor JV Action
No. $ Dates Revised Base
Dates
line

20 4,349,725 Apr/19 Feeder tunnel was realigned &


Excavation and Shotcrete of
rock support design is
respective sections of Feeder Aug/19 Sep/19 same as Sr.No 11
redesigned due to shale
Tunnel upto 6100 ft length
encountered while excavation.

Feeder tunnel was realigned &


Concrete Lining of Feeder Tunnel rock support design is
Nov/19 Oct/19 same as Sr.No 11
Concrete Lining upto 6100 ft redesigned due to shale
encountered while excavation.

Total Amount ($) 37,048,933


The main reason for the delay in project is Law & Order situation in the Project area i.e. North Waziristan Agency as
* working days are reduced as there are curfew imposed oftenly.
* working hours are less due to security threats and work is started in the morning when bomb disposal squad gives clearance given by the Armed forces.
* Night shift is not possible and only only work is done only in day time.
* Working on multiple and distinct sites is not possible.