Professional Documents
Culture Documents
Payment amounts are in US Dollars, as that is the currency of payment under the Assistance Agreement and Activity Agreement. Any currency risks or benefits are borne by the Grantee.
General items including dispensary, first aid, laboratories, and installation and maintenance of Upon issuance of milestone completion report
1 177,203 Completed
engineer's radio communication system by WAPDA
Upon issuance of milestone completion report
2 Topographic survey and ground investigations survey till completion and submission of reports 1,265,806 Completed
by WAPDA
Upon issuance of milestone completion report
3 Construction of coffer dam-1 and dewatering arrangement (Weir Stage-1) for undersluices 555,556 Completed
by WAPDA
installation of gates upto commissioning (i.e. silt excluder, Kaitu Weir, spaira ragha head regulator and Upon issuance of milestone completion report
d 170,849 30-May-2021
sheratalla head regulator) by WAPDA
b Installation and testing of mechanical equipments 101,037 Upon installation and testing of the equipment 31-Mar-2024
d Installation and testing of Electrical equipments 19,901 Upon installation and testing of the equipment 31-Mar-2024
12 Connecting/Feeder Channel
13 Headrace Channel, Forebay, Spill Channel. Tail race channel (Bill No C-1-P)
37,048,933
Kurram Tangi Multipurpose Dam
Stage-1
Kaitu Weir Irrigation and Power Project
Bill No: C-1-C
FEEDER TUNNEL
Specs.
No Milestone Unit Quantity
Ref.
C-1 Feeder Channel
3.11.3.1 Bulk excavation including disposal within area 3
C 1.1 cft. 197,000
(b) km.
Providing, laying and compacting 1500 psi plain
C 1.2 6.14.4 cft. 2,400
cement concrete
Supplying, placing and compacting of reinforced
C 1.3 6.14.6 (a) cft. 26,500
cement concrete 4000 psi.
Supplying, bending and fixing of deformed Re-
C 1.4 6.14.7 steel bars No. 3 through No. 11, G - 60. Tonne 48
C 1.5 4.7.3 Backfilling around the structure. cft. 39,300
C-2 Inlet Portal : Feeder Tunnel 14' Dia
Structural excavation in rock requiring blasting
C 2.1 3.11.4 (b) cft. 50,000
including disposal within 3 km area.
Providing, laying and compacting 1500 psi plain
C 2.2 6.14.4 cft. 200
cement concrete
Supplying, bending and fixing of deformed Re-
C 2.3 6.14.7 Tonne 13
steel bars No. 3 through No. 11, G - 60.
Supply and install welded steel wire mesh for
C 2.4.1 6.14.8 Tonne 0.07
shotcrete reinforcement
Provide and place shotcrete of class and
C 2.4.2 6.14.16.2 sq.ft. 680
thickness as shown in drawings.
Supply and install rock bolts complete with plate
C 2.5 6.10.1 washers.
C 2.5.1 6.14.16.3 - Non- Tensioned 10 ft in length Nos. 28
C 2.5.2 6.14.16.4 - Tensioned 15ft in Length Nos. 7
Supplying, placing and compacting of reinforced
C 2.6 6.14.6 (a) cft. 4,100
cement concrete 4000 psi.
C 2.7 5.17.3 Drain Holes 2" dia for PVC Slotted Pipes. Nos. 35
C 2.8 6.14.16.5 Galvanized Steel Railing Rft 60
C-3 Feeder Tunnel - 14 ft. Dia (HORSE SHOE)
Underground excavation in rock requiring
C 3.1 3.11.9 blasting including disposal of within 3 km area. cft. 1,366,000
1 3.11.3.1
(b) Bulk excavation in overburden/rock in rock (50%) Cft 23.06
1
6.14.4 &
2 6.14.6 Supplying, placing and compacting lean Cft 425
concrete/lining of 2000 psi,
(c )
wer Project
Unit Rate
Amount in PKR Rs.
PKR Rs.
8.91 1,755,270.00
300.00 720,000.00
550.00 14,575,000.00
135,000.00 6,480,000.00
8.38 329,334.00
- Inlet & Outlet portal
26.20 1,310,000.00
300.00 60,000.00
135,000.00 1,755,000.00
214,840.00 15,038.80
-
9,429.20 264,017.60
10,372.12 72,604.84
550.00 2,255,000.00
838.40 29,344.00
2,672.40 160,344.00
- Earthwork and shotcreting co
198.80 271,560,800.00 Earthwork and shotcreting cost for original length of 6100 ft
26.20 1,152,800.00
300.00 60,000.00
214,840.00 279,292.00
408.72 531,336.00
-
6,413,831.80
9,429.20 235,730.00
10,372.12 155,581.80
135,000.00 1,687,500.00
550.00 2,255,000.00
1,048.00 31,440.00
838.40 25,152.00
2,672.40 133,620.00
Total 934,955,736.40
Total in Million
HRC
Quantity Amount (Rs.)
12,502 5,313,414.600
119,279
8717483
1,770,726
184,863,791.94
378,497 756,993
Concreting cost
Silt Excluder
1 Slide Gate for Silt Excluder Intake.
Vertical Slide gate as specified in Bidding Documents /
1.1 No. 2 945,320.60 1,890,641.20
Drawings.
1.2 1st and 2nd stage embedded parts as specified. Set 2 876,926.40 1,753,852.80
Power operated rope and drum hoist, having provision of
1.3 manual operation, complete with support structures i.e. Set 2 1,503,040.00 3,006,080.00
access ladder, platform, railing etc.
Local hoist control module complete with electric power
1.4 unit and local control panels including all wiring and Set 2 6,395,480.00 12,790,960.00
cabling
Electrical distribution panel complete with cabling to gates
1.5 Set 2 949,746.00 1,899,492.00
Modules
Total Item 1 21,341,026.00
2 Trash rack for Silt Excluder Intake
2.1 Trash rack as specified in Bidding Documents / Drawings Set 2 6,345,920.00 12,691,840.00
2.2 1st and 2nd stage embedded parts as specified. Set 2 1,586,480.00 3,172,960.00
Lifting beam with all accessories required for satisfactory
2.3 Nos 1 770,000.00 770,000.00
operation
Total Item 2 16,634,800.00
3 Slide Gate for Silt Ejectors
Vertical Slide gate as specified in Bidding Documents /
3.1 Nos 12 114,174.20 1,370,090.40
Drawings
3.2 1st and 2nd stage embedded parts as specified. Set 12 33,087.60 397,051.20
Manually operated stem type hoisting arrangement
3.3 complete with support structures. i.e. access ladder, Set 12 204,120.00 2,449,440.00
platform, railing etc.
Total Item 3 4,216,581.60
4 Stoplogs for Silt Excluder Inlet and outlet
4.1 Stoplog as specified in Bidding Documents / Drawings Set 4 644,537.60 2,578,150.40
4.2 1st and 2nd stage embedded parts as specified. Set 8 597,903.60 4,783,228.80
Lifting beam with all accessories required for satisfactory
4.3 Nos 1 616,000.00 616,000.00
operation
Total Item 4 7,977,379.20
Kaitu Weir
Item No 4 d total cost (in Pkr) taking 15 % of C-1-O as per provision of Contract for
118910807*0.15 17,836,621
installation and commission of equipment
(Head Race, After Bay, Tail Race, Spill Channel and Water Shed Crossings)
respective
3.11.3.1
P-1.1 - in overburden cft. 6,279,336.00 8.91 55,948,883.76 component cost (in
(a)
396,239,976.90 PKR)
3.11.3.1
P-1.2 - in rock cft. 14,756,769.00 23.06 340,291,093.14 in USD
(b)
6.14.4 &
Supplying, placing and compacting
P-2.1 6.14.6 cft. 257,094.00 425.00 109,264,950.00
lean concrete/lining of 2000 psi,
C)
respective
Supplying, placing and compacting of
P-2.2 6.14.6 a) cft. 193,914.00 550.00 106,652,700.00 component cost (in
reinforced cement concrete 4000 psi
284,409,650.00 PKR)
Provide and install 1-1.5 inches wide
P-2.3 6.14.10 expansion joints in structures complete Rft. 7,850.00 2,620.00 20,567,000.00 in USD
with PVC water stop.
P-3 STEEL REINFORCEMENT / STRUCTURAL STEEL -
Supplying, bending and fixing of
P-3.1 6.14.7 Tonne 355.00 135,000.00 47,925,000.00
deformed G-60.
Total (in PKR) 284,409,650.00
Total (in USD) Milestone No 10 (b) 2,724,230.36
P-4 MISCELLANEOUS ITEMS -
4.7.1 (c) Provide and lay inverted filter under
P-4.1 cft. 4,266.00 60.78 259,287.48
(i) rip-rap.
P-4.2 4.7.4 Provide and lay stone rip-rap cft. 26,136.00 146.72 3,834,673.92
6.14.16. Provide and fix permanent galvanized
P-4.3 Rft. 150.00 2,672.40 400,860.00
5 steel pipe railing.
Compacted backfill behind and around
P-4.4 4.7.3 cft. 232,200.00 12.58 2,921,076.00
structure,
Total (in PKR) 7,415,897.40
Total (in USD) Milestone No 10 (b) 71,033.50
10 (a) 10 (b) 10 ( C ) 10 (d)
Stage-1
A Mechanical Works
Item No 10 a
(Taking 85 % of
Item No 10 b
the total, as 85
taking 15 % as
% of payment is
Designing, Manufacturing, Delivering to Site, Installing, per provision of
Vol.3A related with
Testing, Commissioning and Maintaining for One year each Contract for
Part -II procurment &
item of the following equipment installation and
delivery of
commission of
Equipment at
equipment
site as per
Contract)
19 3.1.3B Manifold as per design pressure and as shown on drawing Lumpsum 1 500,000.00 500,000.00
20 1.5.5 Hydrostatic testing Lumpsum 1 1,200,000.00 1,200,000.00
21 1.8.2 Coating and lining of all pipes as specified Lumpsum 1 95,000.00 95,000.00
Spare parts for pumps, motors and control panel for five
22 Lot 1 500,000.00 500,000.00
years operation (bidder to give details of spares)
23 3.10 Maintenance tools as specified Set 1 200,000.00 200,000.00
Any other items to be included in scope of supply which is
Provision
24 required to meet the intent of specification (bidder to give 5,000,000.00
sums
details)
in USD 572,543 101,037
10 light points including PVC conduits, wiring with 1.5 mm2 13,851,400.00 11,773,690.00 2,077,710.00
PVC cable with copper conductor, flourescent lights, two
4 1.16.7 Nos. 10 10,240.00 102,400.00
switches for indoor and outdoor lights, earth continuity
conductor completely functional in all respects.
Earthwork Cos
F 1.1.1 3.11.3.1 (a) - in overburden cft. 6,661,500 8.91 59,353,965.00###
F 3.6 4.7.4 Provide and lay stone riprap. cft. 16,020 146.72 2,350,454.40###
F 3.7 4.7.3 Compacted backfill behind & around structures . cft. 67,790 12.58 852,798.20###
F 3.8 11.16.3 Providing and install 6" Dia PVC pipe. Nos. 16,500 653.95 10,790,175.00###
F 4.7 14.15 Provide and lay 3" top surfacing of bridge road. sq.ft. 1,672 173.84 290,660.48###
F 4.8 4.7.4 Provide and lay stone metalling. cft. 2,000 99.56 199,120.00###
F 4.9 4.7.3 Backfilling behind and around structures. cft. 40,620 8.38 340,395.60###
F 5.6 4.7.4 Provide and lay stone pitching cft. 2,700 124.94 337,338.00###
F 5.7 4.7.3 Backfilling behind and around structures cft. 17,172 8.38 143,901.36###
Cross Drainage Structures : Culverts - 48 Nos. ;
F-6 ###
Syphons - 7 Nos. ; Super Passages - 6 Nos.
Structural excavation in overburden / rock including
F 6.1 ###
disposal within 3km area.
F 6.1.1 3.11.4(a) - in overburden cft. 861,400 9.93 8,553,702.00###
F 6.9 11.16.10 Providing and laying of gabions cft. 1,615 78.60 126,939.00###
F 6.10 4.4.4 Provide and lay stone riprap cft. 159,900 146.72 23,460,528.00###
F 6.11 4.7.3 Backfilling behind and around structures. cft. 3,593 8.38 30,105.15###
F 7.7 4.7.3 Backfilling behind and around structures. cft. 310,200 8.38 2,599,476.00###
ost of upper sheratalla canal for length of 6676 ft=2.03 km excluding the
11,999,877.66 114,941.36
Tunnel= (6676/85699
Divide the length in 2 parts 5,999,939
Cost of individual length in USD 57,471
20.96 23,084,191.20
26.20 72,208,248.00
122,684,057.42 61,342,028.71 587,567
4.19 1,977,700.95
5.24 2,888,329.92
12.59 22,525,587.35
67.86 60,706,402.38
168,731,745.72 84,365,872.86 808,102
81.02 108,025,343.34
12.66 18,597,160.20
134,027,160.20 67,013,580.10 641,893
100.00 115,430,000.00
63.95 36,908,742.50
150,000,000.00 226,908,742.50 113,454,371.25 1,086,728
40,000,000.00
Sub-Total 652,351,705.84 3,124,290
Kurram Tangi Multipurpose Dam
Stage-1
Kaitu Weir Irrigation and Power Project
Bill No: C-1-E
SPAIRA RAGHA CANAL, DRAINS, BRIDGES, CROSS-DRAINAGE STRUCTURES
Unit Rate
Specs.
No Milestone Unit Quantity PKR Amount in PKR Rs.
Ref.
Rs.
E Main Canal (RD 0.00 to 42+514), Minor No.1 (RD 0.00 to 5+405) and Lift Minor (RD 0.00 to 13+174)
E-1 Earth Work
Trench Excavation inluding disposal within 3km
E 1.1
area.