Delays

Days
Sr # Delay event BL start BL Finish Actual Start Actual Finish Duration (Days) Impacting Reasons Remarks
Schedule

Complete site closure due to Letters shows the delay of 03 weeks however, weekly reports
1 2-Jun-20 23-Jun-20 21 21
covid-19 shows closure of 2 weeks (jun-2 to jun-15)
we will add these delaying events on Critical path, which will
payment was due on 03 jul but made on 13th of july, & it took impact the schedule.
2 Payment delay 3-Jul-20 23-Jul-20 20 20 additional 10 days for cheque clearence due to which payment
to sub-contractors could not be made.

3 late delivery of Goods due to Covid


I could not find it in ABL. However incorporated in Schedule
wheel wash station completed on 29-Aug-2020. (I think it is with predeceddor & successor. Pl check
3a Wheel Wash system 28-Mar-20 29-Aug-20 154 88 additional work contractor is doing, not mentioned in ABL)

(Predecessor: Need to complete the finishing works of the Pump Room.) (Successor:
3b Fire fighting pumps 1-Mar-20 23-Aug-20 175
Testing and Commissioning and Project Handing Over)
PL check dates, predecessors, successors
(Predecessor: Need to complete the finishing works of the Generator Room.)
3c Diesel Generator 19-Mar-20 19-Jul-20 122 (Successor: Testing and Commissioning of all equipments and Project Handing Over)

Variation Orders

(Predecessor : the Steel Structure Works including Roof of Main Building) and the
effect of Odor Control will be a delay in Testing & Commissioning and Handing Over
Odor Control & fresh Air what is the effect of odor contro system/ pl specify? Mention
4 11-Apr-20 20-Jun-20 11-Apr-20 7-Dec-20 170 118 of the Project. Also, this equipment came from overseas and the delivery to UAE was
system its Predecessor activities.
delayed. The Odor Control was delivered at the site last 11-Nov-2020. The expected
deliver of the item was 20-June-2021 if there was no delayed happen.
11-Aug-20

Note: Late delivries of material delays covering covid-19 complete closure & late payment delays

Project completion date (old) 11-Aug-20


Revised completion date 21-Jan-21
EOT (Days) 163

ADDITIONAL DELAYS
Days
Sr # Delay event BL start BL Finish Actual Start Actual Finish Duration (Days) Impacting Reasons
Schedule
Payment Delay - Month of
1 August 8-Sep-20 15-Oct-20 36 36

Payment Delay - Month of


2 September 24-Oct-20 15-Dec-20 51 51

The ADM approved modified drawing was received only 02-


Feb-2020. The effect of this is that we cannot proceed further
3 Modification of Site Plan 30 30
since the structural design is also affected. We can insert this
delay from 2nd or 3rd week of January.
At least 50 days in total. However, this needs to be splitted.
First part will start from February 2020 and the second part
will be January 2021. The second part should be 20 days. The
effect of this plan modification are the following (First Part is
that we already started the electrical works but there have
4 Electrical Plan Modification at least 50 at least 50 been a sudden changes on which we need to uninstall some
cables and conduits and also increase the capacity of the
Generators which needs to be procured again) (Second Part is
that once we finished all the electrical works, the plan was
modified again and needs to change/add some works. We can
consider it as a variation work.)