Days
Sr # Delay event BL start BL Finish Actual Start Actual Finish Duration (Days) Impacting Reasons Remarks
Schedule
Complete site closure due to Letters shows the delay of 03 weeks however, weekly reports
1 2-Jun-20 23-Jun-20 21 21
covid-19 shows closure of 2 weeks (jun-2 to jun-15)
we will add these delaying events on Critical path, which will
payment was due on 03 jul but made on 13th of july, & it took impact the schedule.
2 Payment delay 3-Jul-20 23-Jul-20 20 20 additional 10 days for cheque clearence due to which payment
to sub-contractors could not be made.
(Predecessor: Need to complete the finishing works of the Pump Room.) (Successor:
3b Fire fighting pumps 1-Mar-20 23-Aug-20 175
Testing and Commissioning and Project Handing Over)
PL check dates, predecessors, successors
(Predecessor: Need to complete the finishing works of the Generator Room.)
3c Diesel Generator 19-Mar-20 19-Jul-20 122 (Successor: Testing and Commissioning of all equipments and Project Handing Over)
Variation Orders
(Predecessor : the Steel Structure Works including Roof of Main Building) and the
effect of Odor Control will be a delay in Testing & Commissioning and Handing Over
Odor Control & fresh Air what is the effect of odor contro system/ pl specify? Mention
4 11-Apr-20 20-Jun-20 11-Apr-20 7-Dec-20 170 118 of the Project. Also, this equipment came from overseas and the delivery to UAE was
system its Predecessor activities.
delayed. The Odor Control was delivered at the site last 11-Nov-2020. The expected
deliver of the item was 20-June-2021 if there was no delayed happen.
11-Aug-20
Note: Late delivries of material delays covering covid-19 complete closure & late payment delays
ADDITIONAL DELAYS
Days
Sr # Delay event BL start BL Finish Actual Start Actual Finish Duration (Days) Impacting Reasons
Schedule
Payment Delay - Month of
1 August 8-Sep-20 15-Oct-20 36 36