Professional Documents
Culture Documents
SD and CO Summary
SD and CO Summary
tio e
By
TGC ECG Hard Precast Royal Advance
Ac yp
n
T
lla
Vi
1- Roof MEP
1- The Precast Drawings have
1- To Provide Service Blocks Coordination drawings
been approved by the Third
Structural design as Cast In Situ have been submitted
Party. 2-
1- Roof Slab Shop drawings Reinforced Concrete. 22-NOV on 15th of November
Precast Boundary Wall Shop
T2 to be submitted on (Received 23rd - NOV)
drawings were commented
to Hard Precast for
29/11/2023 2- To Provide Site Layout for all their review and
by ECG and Sent to Hard
Service Blocks 22-NOV Coordination. (Still
Precast to revise them on 22-
(Received 23rd - NOV) Pending with Hard
NOV.
Precast)
1- Foundation design drawings 1-Awaiting the
and Calcualtions have been 1- Foundation Design Approval of T22
1- To revise the Foundation
submitted to third Party for Submitted on 28-11 to ECG Builders Work
and Plinth Wall Shop
approval on 28-11. 2- Precast Boundary Wall drawings from ECG in
T22 drawings based on the final
2- To Provide a revised IFC in Shop drawings will be order to forward them
precast drawings. 24th of
accordance with the latest submitted on 27th of to Hard Precast to be
Nov.
comments received on the November (Not Submitted) considered in their
Staircase on 22-NOV design.
1- Ground Floor panels
Coordination have been
done. 7 Panels has been
1- To coordinate with Royal revised by Royal advance and
1- Ground Floor panels
Advance and Hard Precast 5 panels are on hold awaiting
Coordination have
to complete the first floor the final ID Drawings.
been done. 7 Panels
slabs and beams 1- Precast Package has been 2- A clash of the Ceiling and
has been revised by
V2G Coordination drawings. To submitted to third party for 3.0 Delta beams has been
Royal advance and 5
be Completed on 17th Nov. approval on 28-11. resolved on the First Floor.
panels are on hold
for the beams and 22rd Submitted on 23-NOV to ECG
awaiting the final ID
Nov. for the panels. (Done for Approval
Drawings.
on 22nd of NOV) 3- Precast Boundary Wall
Shop drawings will be
submitted on 27th of
November. (Not Submitted)