SUMMARY – 13-11-2023 – ADLI TG-2137 AND RAMHAN TG2139 – HARD PRECAST

Villa type

T2- Ramhan Island Fabrication drawings completed

T3-Ramhan Island Fabrication drawings completed

T3-A-Ramhan Fabrication drawings completed


Island

T2- Abu Dhabi Ground floor walls, first floor walls, first floor slabs, beams issued.
Luxury Island
Roof floor slab builder work not received.
(Massnoua)

V2-G- Abu Dhabi Design drawings Fabrication drawings


Luxury Island
(Massnoua) Drawings submitted to Fabrication drawing submitted on October
third party approval on 14th.
October 19th.
Fabrication drawings for MEP coordination
Third party comments resubmitted on October 25th. “As per the
received on November 3rd. architectural modifications”

Drawings resubmitted on Email received from Trojan (8 panels on


November 11th. ground floor are without MEP)-November
7th.

Rough surface drawings received on


November 13th,

6 panels will be issued to production by


November 13th. 2 columns still under
coordination with the Delta beams

T2-2 -Abu Dhabi HPBS requested the final Revit model on November 7th, and no
Luxury Island response received.
(Massnoua)

V2-G- New-Abu Drawings will be submitted on November 15th.


Dhabi Luxury
Island (Massnoua)

V1S -Abu Dhabi According to the latest architectural Revit model we received from the
Luxury Island client, the lengths of the cantilever areas are extensive.
(Massnoua)
This structural issue has been discussed, and we are currently in the
V4P -Abu Dhabi process of coordinating with the client and the consultant to update the
Luxury Island architectural models.
(Massnoua)
SUMMARY – 13-11-2023 – ADLI TG-2137 AND RAMHAN TG2139 – HARD PRECAST

V4B -Abu Dhabi Once these updates are completed and the issues are solved, we will
Luxury Island proceed with the structural drawings’ submissions.
(Massnoua)