You are on page 1of 11

RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout

Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
22-Sep-2021, RBL 22-7-2021 -Tahfeez Al Quran Eleme
RBL 22-7-2021 -Tahfeez Al Quran Elementary in Sumaira RB 1 - B1 243d 06-Dec-2020 A 22-Sep-2021 60.95% 68.86% 2,831,185.62

243d 06-Dec-2020 A 22-Sep-2021 60.95% 68.86% 2,831,185.62 22-Sep-2021, Construction


Construction
Key Milestones 243d 06-Dec-2020 A 22-Sep-2021 0% 0% 0.00 22-Sep-2021, Key Milestones
RUH17TE6450
Finsh Gate 0d 09-Sep-2021 0% 0% 0.00 Finsh Gate
RUH17TE8640
Finsih Collective Tank 5d 05-Aug-2021 10-Aug-2021 0% 0% 0.00 Finsih Collective Tank
RUH17TE8580
PROJECT FINISH 0d 22-Sep-2021 0% 0% 0.00 PROJECT FINISH
RUH17TE8290
Finish Guard House 0d 15-Sep-2021 0% 0% 0.00 Finish Guard House
RUH17TE6360
Finish Main Building 0d 22-Sep-2021 0% 0% 0.00 Finish Main Building
RUH17TE6420
Finish Electrical Room 0d 22-Sep-2021 0% 0% 0.00 Finish Electrical Room
RUH17TE4900
Finish General Site 0d 22-Sep-2021 0% 0% 0.00 Finish General Site
RUH17TE4250
Finish WaterTank and Pumbs 1 0d 22-Sep-2021 0% 0% 0.00 Finish WaterTank and Pumbs 1
RUH17TE1000
PROJECT START 0d 06-Dec-2020 A 100% 100% 0.00 PROJECT START
Engineering 74d 04-Jan-2021 A 30-Mar-2021 A 0% 0% 0.00 30-Mar-2021 A, Engineering
SHOP DRAWINGS SUBMITTAL & APPROVAL 74d 04-Jan-2021 A 30-Mar-2021 A 0% 0% 0.00 30-Mar-2021 A, SHOP DRAWINGS SUBMITTAL & APPROVAL
RUH17TE1060
Structural & Civil Shop Drawing Submission 7d 04-Jan-2021 A 11-Jan-2021 A 100% 100% 0.00 Structural & Civil Shop Drawing Submission
RUH17TE1480
Structural & Civil Shop Drawings Approval 37d 16-Feb-2021 A 30-Mar-2021 A 100% 100% 0.00 Structural & Civil Shop Drawings Approval
RUH17TE1070
Architectural Shop Drawings Submission 21d 08-Feb-2021 A 03-Mar-2021 A 100% 100% 0.00 Architectural Shop Drawings Submission
RUH17TE1110
Architectural Shop Drawings Approval 13d 16-Feb-2021 A 02-Mar-2021 A 100% 100% 0.00 Architectural Shop Drawings Approval
RUH17TE1080
Electrical Shop Drawings Submission 16d 13-Feb-2021 A 02-Mar-2021 A 100% 100% 0.00 Electrical Shop Drawings Submission
RUH17TE1440
Electrical Shop DrawingsApproval 21d 17-Feb-2021 A 13-Mar-2021 A 100% 100% 0.00 Electrical Shop Drawings Approval
RUH17TE1090
Plumbing Shop Drawings Submission 14d 13-Feb-2021 A 28-Feb-2021 A 100% 100% 0.00 Plumbing Shop Drawings Submission
RUH17TE1340
Plumbing Shop Drawings Approval 16d 15-Feb-2021 A 05-Mar-2021 A 100% 100% 0.00 Plumbing Shop Drawings Approval
RUH17TE1100
HVAC & Fire Fighting Shop Drawings Submission 15d 14-Feb-2021 A 02-Mar-2021 A 100% 100% 0.00 HVAC & Fire Fighting Shop Drawings Submission
RUH17TE1350
HVAC & Fire Fighting Shop Drawings Approval 33d 17-Feb-2021 A 27-Mar-2021 A 100% 100% 0.00 HVAC & Fire Fighting Shop Drawings Approval
Mobilization 15d 06-Dec-2020 A 22-Dec-2020 A 100% 100% 11,300.00 22-Dec-2020 A, Mobilization
RUH17TE1010
Mobilization & Set offices &Site Cleaning 15d 06-Dec-2020 A 22-Dec-2020 A 100% 100% 11,300.00 Mobilization & Set offices &Site Cleaning
All Building 240d 09-Dec-2020 A 22-Sep-2021 60.79% 68.74% 2,819,885.62 22-Sep-2021,All Building
Gate 224d 15-Dec-2020 A 09-Sep-2021 56.36% 51.95% 94,968.59 09-Sep-2021, Gate
SUB-STRUCTURE 91d 15-Dec-2020 A 30-Mar-2021 A 100% 100% 9,605.00 30-Mar-2021 A, SUB-STRUCTURE
RUH17TE2180
Slab on Grade 5d 25-Mar-2021 A 30-Mar-2021 A 100% 100% 9,605.00 Slab on Grade
RUH17TE2140
Check&Repair for Existing Concrete 13d 15-Dec-2020 A 29-Dec-2020 A 100% 100% 0.00 Check&Repair for Existing Concrete
SUPER STRUCTURE 204d 07-Jan-2021 A 09-Sep-2021 51.45% 46.55% 85,363.59 09-Sep-2021, SUPER STRUCTURE
FINISHING WORK 177d 09-Jan-2021 A 10-Aug-2021 60.48% 55.52% 50,692.48 10-Aug-2021, FINISHING WORK
RUH17TE7940
Supply and installation of External Metal Shades 10d 24-Jul-2021 03-Aug-2021 0% 0% 18,361.37 Supply and installation of External Metal Shades
RUH17TE7950
Maintenance and paint Handrail with All Accessiors 6d 04-Aug-2021 10-Aug-2021 0% 0% 459.68 Maintenance and paint Handrail with All Accessiors
RUH17TE7960
Specialities 8d 02-Aug-2021 10-Aug-2021 0% 0% 485.22 Specialities
RUH17TE7460
Internal Painting 98d 04-Apr-2021 A 03-Aug-2021 89.8% 80% 1,149.21 Internal Painting
RUH17TE6890
External Painting 171d 09-Jan-2021 A 03-Aug-2021 94.15% 75% 10,425.89 External Painting
RUH17TE7440
Doors 73d 02-Apr-2021 A 29-Jun-2021 A 100% 100% 2,553.80 Doors
RUH17TE7450
Windows 83d 10-Apr-2021 A 24-Jul-2021 100% 95% 8,135.13 Windows
RUH17TE7120
Change the Invalid Floor Tiles (Broken + Air blanks) 13d 16-Mar-2021 A 30-Mar-2021 A 100% 100% 3,243.33 Change the Invalid Floor Tiles (Broken + Air blanks)
RUH17TE6350
Check &Repair Internal Plastering 7d 09-Jan-2021 A 16-Jan-2021 A 100% 100% 0.00 Check &Repair Internal Plastering
RUH17TE7130
Changing Invalid Wall Tiles (Broken + With air spaces)Ceramic Tilefor Wall 6d 03-Apr-2021 A 08-Apr-2021 A 100% 100% 1,053.44 Changing Invalid Wall Tiles (Broken + With air spaces)Ceramic Tilefor Wall

Project Baseline Bar Critical Remaining ... Page 1 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
RUH17TE6900
Ceiling Finish 14d 09-Mar-2021 A 24-Mar-2021 A 100% 100% 1,468.44 Ceiling Finish
RUH17TE7230
Roof - Execute a Polyurethane Insulation Layer For Surfaces 77d 30-Mar-2021 A 30-Jun-2021 A 100% 100% 1,161.98 Roof - Execute a Polyurethane Insulation Layer For Surfaces
RUH17TE7280
External Plaster 14d 10-Mar-2021 A 25-Mar-2021 A 100% 100% 0.00 External Plaster
RUH17TE6080
Maintenace Door Frame 14d 01-Mar-2021 A 16-Mar-2021 A 100% 100% 2,194.99 Maintenace Door Frame
MECHANICAL WORK 154d 07-Mar-2021 A 09-Sep-2021 62.87% 53.11% 17,088.20 09-Sep-2021, MECHANICAL WORK
RUH17TE7970
Fire Extinguisher 2d 29-Jul-2021 31-Jul-2021 0% 0% 319.23 Fire Extinguisher
RUH17TE7990
Plumbing Fixtures 1d 09-Sep-2021 09-Sep-2021 0% 0% 4,596.84 Plumbing Fixtures
RUH17TE8190
Exhaust Fan 5d 04-Sep-2021 08-Sep-2021 0% 0% 702.30 Exhaust Fan
RUH17TE7980
Electric water Heater 19d 03-Jul-2021 A 28-Jul-2021 73.68% 90% 957.12 Electric water Heater
RUH17TE6950
HVAC 97d 03-Apr-2021 A 01-Aug-2021 91.75% 60% 5,746.05 HVAC
RUH17TE6930
Check on Existing Water Supply System 7d 07-Mar-2021 A 14-Mar-2021 A 100% 100% 1,915.35 Check on Existing Water Supply System
RUH17TE6940
Check and Install Drinage Pipe and Fiting 7d 15-Mar-2021 A 22-Mar-2021 A 100% 100% 2,851.32 Check and Install Drinage Pipe and Fiting
ELECTRICAL WORK 198d 07-Jan-2021 A 02-Sep-2021 14.31% 14.31% 17,582.91 02-Sep-2021, ELECTRICAL WORK
RUH17TE6960
Panel Board 5d 11-Aug-2021 16-Aug-2021 0% 0% 3,830.70 Panel Board
RUH17TE8000
Lighting Fixture 8d 25-Aug-2021 02-Sep-2021 0% 0% 4,213.77 Lighting Fixture
RUH17TE6980
Public Adress System 7d 17-Aug-2021 24-Aug-2021 0% 0% 1,085.37 Public Adress System
RUH17TE8010
Telephone System 8d 25-Aug-2021 02-Sep-2021 0% 0% 2,936.87 Telephone System
RUH17TE8020
FireAlarm System 8d 25-Aug-2021 02-Sep-2021 0% 0% 3,000.72 FireAlarm System
RUH17TE6020
Lighting System First Fix 4d 07-Jan-2021 A 11-Jan-2021 A 100% 100% 1,213.06 Lighting System First Fix
RUH17TE6970
Lighting System Second Fix 28d 04-Apr-2021 A 05-May-2021 A 100% 100% 1,302.44 Lighting System Second Fix
General Site Works 227d 24-Dec-2020 A 22-Sep-2021 59.43% 72.06% 591,263.46 22-Sep-2021, General Site Works
Procurment 197d 31-Dec-2020 A 25-Aug-2021 57.47% 41.45% 98,423.00 25-Aug-2021, Procurment
GSW1290 Transformer -Delivery 5d 21-Aug-2021 25-Aug-2021 0% 0% 28,815.00 Transformer -Delivery
GSW1240 Main DB -Delivery 53d 15-Jun-2021 A 19-Aug-2021 54.72% 0% 28,815.00 Main DB -Delivery
GSW1230 Main DB -PO 35d 31-Dec-2020 A 09-Feb-2021 A 100% 100% 19,210.00 Main DB -PO
GSW1250 Low Voltage Cable -Po 9d 02-Feb-2021 A 12-Feb-2021 A 100% 100% 949.20 Low Voltage Cable -Po
GSW1260 Low Voltage Cable -Delivery 7d 08-Feb-2021 A 15-Feb-2021 A 100% 100% 1,423.80 Low Voltage Cable -Delivery
GSW1280 Transformer-PO 17d 09-Feb-2021 A 28-Feb-2021 A 100% 100% 19,210.00 Transformer-PO
Site Works &Concrete 182d 24-Dec-2020 A 01-Aug-2021 93.23% 98.98% 17,797.50 01-Aug-2021, Site Works &Concrete
GSW1390 Bitumen Paint for Grade Beams With Soil 12d 14-Jul-2021 A 01-Aug-2021 33.33% 90% 1,808.00 Bitumen Paint for Grade Beams With Soil
GSW1140 Executing 4 Boring Points At the General Site 54d 24-Dec-2020 A 25-Feb-2021 A 100% 100% 8,136.00 Executing 4 Boring Points At the General Site
GSW1150 Steel Fixing &Caste For Slab on Grade 6d 09-Jun-2021 A 15-Jun-2021 A 100% 100% 3,616.00 Steel Fixing &Caste For Slab on Grade
GSW1380 Block Wall For Fence 27d 03-Feb-2021 A 06-Mar-2021 A 100% 100% 4,237.50 Block Wall For Fence
Finshing (Wall &Paving ) 211d 12-Jan-2021 A 22-Sep-2021 36.83% 78.99% 219,053.89 22-Sep-2021, Finshing (Wall &Paving )
GSW1180 Internal Cemen Tiles (Inside The Fence) 42d 20-Jul-2021 A 09-Sep-2021 0% 83% 40,018.95 Internal Cemen Tiles (Inside The Fence)
GSW1200 Supply Precast Concrete Waste Baskets 11d 11-Sep-2021 22-Sep-2021 0% 0% 1,695.00 Supply Precast Concrete Waste Baskets
GSW1210 Installation of External Metal Shades 27d 22-Jul-2021 A 23-Aug-2021 0% 79% 25,425.00 Installation of External Metal Shades
GSW1310 Wheel Stopper 11d 11-Sep-2021 22-Sep-2021 0% 0% 1,728.90 Wheel Stopper
GSW1360 Precast Concrete Chairs 26d 24-Aug-2021 22-Sep-2021 0% 0% 9,492.00 Precast Concrete Chairs
GSW1410 Internal Painting 42d 22-Jul-2021 A 09-Sep-2021 0% 75% 31,188.00 Internal Painting
GSW1350 Installation of Artificial Grass for Sun Shedand Play Ground 56d 03-Jul-2021 A 09-Sep-2021 25% 40% 2,966.25 Installation of Artificial Grass forSun Shedand Play Ground
GSW1420 External Painting 56d 03-Jul-2021 A 09-Sep-2021 25% 80% 4,427.34 External Painting
GSW1190 Supply and place Sand 100 mm thikAccording to the Drawings 71d 15-Jun-2021 A 09-Sep-2021 40.85% 69% 6,085.05 Supply and place Sand 100 mm thik According to the Drawing
GSW1000 Curbstones 135d 29-Mar-2021 A 09-Sep-2021 68.89% 90% 36,572.45 Curbstones

Project Baseline Bar Critical Remaining ... Page 2 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
GSW1010 Supply and Install Cement Tiles outside (Outsidethe Fence) 400 x 400 135d 29-Mar-2021 A 09-Sep-2021 68.89% 85% 7,458.00 Supply and Install Cement Tilesoutside (Outsidethe Fence) 4
GSW1340 Interlook 135d 29-Mar-2021 A 09-Sep-2021 68.89% 80% 19,243.90 Interlook
GSW1300 Site Cleaning &Site Leveling Cut and Fill 22d 20-Feb-2021 A 16-Mar-2021 A 100% 100% 6,763.05 Site Cleaning &Site Leveling Cut and Fill
GSW1400 Plaster Works 89d 12-Jan-2021 A 25-Apr-2021 A 100% 100% 25,990.00 Plaster Works
Metal (Doors &Expansion joint ) 26d 24-Jun-2021 A 28-Jul-2021 80.77% 75% 2,463.40 28-Jul-2021, Metal (Doors &Expansion joint )
GSW1430 Expansion Joint Installation 26d 24-Jun-2021 A 28-Jul-2021 80.77% 75% 2,463.40 Expansion Joint Installation
Mechanical Works 211d 12-Jan-2021 A 22-Sep-2021 94.18% 95.83% 135,429.37 22-Sep-2021, Mechanical Works
GSW1130 Public Drainge System Connection 76d 22-Jun-2021 A 22-Sep-2021 30.26% 50% 11,300.00 Public Drainge System Connection
GSW1080 R.C Manholes(Rain Drain &Drainge &Fire ) 112d 21-Jan-2021 A 03-Jun-2021 A 100% 100% 30,849.00 R.C Manholes(Rain Drain &Drainge &Fire )
GSW1090 Check on Existing Drainage Rain Pipe System 17d 18-Feb-2021 A 09-Mar-2021 A 100% 100% 3,051.00 Check on Existing Drainage Rain Pipe System
GSW1100 Public Water System Connection 12d 08-Jun-2021 A 21-Jun-2021 A 100% 100% 5,650.00 Public Water System Connection
GSW1110 Install Fire water Pipe Line With Valve 22d 20-Feb-2021 A 16-Mar-2021 A 100% 100% 32,019.68 Install Fire water Pipe Line With Valve
GSW1120 Domestic Water Supply System Line With Valve 13d 16-Feb-2021 A 02-Mar-2021 A 100% 100% 15,080.98 Domestic Water Supply System Line With Valve
GSW1220 Sanitary & Waste Pipe System Check Install New 44d 12-Jan-2021 A 03-Mar-2021 A 100% 100% 37,478.71 Sanitary & Waste Pipe System Check Install New
Electrical Works 203d 10-Jan-2021 A 11-Sep-2021 57.62% 53.33% 118,096.30 11-Sep-2021, Electrical Works
GSW1060 Site , Gate and Shading Lighting 35d 02-Aug-2021 11-Sep-2021 0% 0% 4,429.60 Site , Gate and Shading Lighting
GSW1070 Public Address System 35d 02-Aug-2021 11-Sep-2021 0% 0% 1,695.00 PublicAddress System
GSW1270 Main Connection With SCECO 58d 30-Jun-2021 A 09-Sep-2021 27.59% 98% 48,025.00 Main Connection With SCECO
GSW1020 Main Distribution Board 42d 09-Jun-2021 A 01-Aug-2021 80.95% 0% 48,025.00 Main Distribution Board
GSW1030 Site Pipes(Spares + Future Extension) 4d 10-Jan-2021 A 13-Jan-2021 A 100% 100% 2,813.70 Site Pipes(Spares + Future Extension)
GSW1040 R.C Manholes 21d 10-Jan-2021 A 02-Feb-2021 A 100% 100% 10,735.00 R.C Manholes
GSW1050 Low Voltage Cable 2d 16-Feb-2021 A 17-Feb-2021 A 100% 100% 2,373.00 Low Voltage Cable
MAIN BUILDING 1 (26/22) 240d 09-Dec-2020 A 22-Sep-2021 65.26% 70.75% 1,590,760.89 22-Sep-2021, MAIN BUILDING 1 (26/22)
PROCUREMENT 205d 04-Jan-2021 A 07-Sep-2021 79.36% 79.53% 395,335.02 07-Sep-2021, PROCUREMENT
CIVIL & ARC. 198d 04-Jan-2021 A 30-Aug-2021 91.91% 92.42% 130,597.49 30-Aug-2021, CIVIL & ARC.
METAL DOORS 73d 04-Jan-2021 A 29-Mar-2021 A 100% 100% 48,093.37 29-Mar-2021 A, METAL DOORS
MPRO.1040
Metal Doors - Material Submittal 3d 04-Jan-2021 A 06-Jan-2021 A 100% 100% 0.00 Metal Doors - Material Submittal
MPRO.1050
Metal Doors - Material Approval 5d 07-Jan-2021 A 12-Jan-2021 A 100% 100% 0.00 Metal Doors - Material Approval
MPRO.1060
Metal Doors - PO 10d 11-Jan-2021 A 22-Jan-2021 A 100% 100% 19,237.69 Metal Doors - PO
MPRO.1070
Metal Doors - Delivery 20d 07-Mar-2021 A 29-Mar-2021 A 100% 100% 28,855.68 Metal Doors - Delivery
ALUMINUM WORKS (WINDOW & CURTAIN WALL & SKY LIGHT ) 75d 06-Jan-2021 A 03-Apr-2021 A 100% 100% 60,695.13 03-Apr-2021 A,ALUMINUM WORKS (WINDOW & CURTAIN WALL & SKYLIGHT )
MPRO.1080
WINDOW &CURTAIN WALL& SKY LIGHT - Material Submittal 7d 06-Jan-2021 A 13-Jan-2021 A 100% 100% 0.00 WINDOW &CURTAIN WALL& SKY LIGHT - Material Submittal
MPRO.1090
WINDOW &CURTAIN WALL &SKYLIGHT - Material Approval 12d 09-Jan-2021 A 22-Jan-2021 A 100% 100% 0.00 WINDOW &CURTAIN WALL &SKYLIGHT - Material Approval
MPRO.1100
WINDOW - PO Placement 5d 20-Jan-2021 A 25-Jan-2021 A 100% 100% 24,278.05 WINDOW - PO Placement
MPRO.1110
WINDOW - Delivery 22d 09-Mar-2021 A 03-Apr-2021 A 100% 100% 36,417.08 WINDOW - Delivery
CELLING & COUNTER 121d 04-Apr-2021 A 30-Aug-2021 51.54% 54.62% 21,809.00 30-Aug-2021, CELLING & COUNTER
A1030 COUNTER TOP -DELIVERY 15d 14-Aug-2021 30-Aug-2021 0% 0% 9,729.30 COUNTER TOP -DELIVERY
A1020 GYPSUM BOARD AND ALMINIUM STRIP -DELIVERY 52d 03-Jun-2021 A 07-Aug-2021 75% 95% 3,356.10 GYPSUM BOARD AND ALMINIUM STRIP -DELIVERY
A1000 GYPSUM BOARD AND ALMINIUM STRIP -PO 7d 04-Apr-2021 A 11-Apr-2021 A 100% 100% 2,237.40 GYPSUM BOARD AND ALMINIUM STRIP -PO
A1010 COUNTER TOP -PO 9d 06-Apr-2021 A 15-Apr-2021 A 100% 100% 6,486.20 COUNTER TOP -PO
MECHANICAL 190d 10-Jan-2021 A 26-Aug-2021 91.23% 91.23% 147,104.53 26-Aug-2021, MECHANICAL
HVAC DUCT & AC UNITS 86d 10-Jan-2021 A 19-Apr-2021 A 100% 100% 125,593.85 19-Apr-2021 A,HVAC DUCT & AC UNITS
MPRO.1240
HVAC Duct & AC Units - Material Submittal 20d 10-Jan-2021 A 01-Feb-2021 A 100% 100% 0.00 HVAC Duct & AC Units - Material Submittal
MPRO.1250
HVAC Duct & AC Units - Material Approval 3d 25-Jan-2021 A 27-Jan-2021 A 100% 100% 0.00 HVAC Duct & AC Units - Material Approval

Project Baseline Bar Critical Remaining ... Page 3 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
MPRO.1260
HVAC Duct & AC Units - PO Placement 23d 03-Feb-2021 A 01-Mar-2021 A 100% 100% 50,237.54 HVAC Duct & AC Units - PO Placement
MPRO.1270
HVAC Duct & AC Units - Delivery 18d 30-Mar-2021 A 19-Apr-2021 A 100% 100% 75,356.31 HVAC Duct & AC Units - Delivery
General Exhaust Fan 170d 02-Feb-2021 A 26-Aug-2021 40% 40% 9,328.15 26-Aug-2021, General Exhaust Fan
MPRO.1310
Fans - Delivery 30d 24-Jul-2021 26-Aug-2021 0% 0% 5,596.89 Fans - Delivery
MPRO.1280
Fans - Material Submittal 8d 02-Feb-2021 A 10-Feb-2021 A 100% 100% 0.00 Fans - Material Submittal
MPRO.1290
Fans - Material Approval 33d 16-Feb-2021 A 25-Mar-2021 A 100% 100% 0.00 Fans - Material Approval
MPRO.1300
Fans - PO Placement 9d 04-Apr-2021 A 13-Apr-2021 A 100% 100% 3,731.26 Fans - PO Placement
PLUMBING FIXTURES 169d 03-Feb-2021 A 26-Aug-2021 40% 40% 12,182.53 26-Aug-2021, PLUMBING FIXTURES
MPRO.1390
Plumbing Fixtures - Delivery 30d 24-Jul-2021 26-Aug-2021 0% 0% 7,309.52 Plumbing Fixtures - Delivery
MPRO.1360
Plumbing Fixtures - Material Submittal 6d 03-Feb-2021 A 09-Feb-2021 A 100% 100% 0.00 Plumbing Fixtures - Material Submittal
MPRO.1370
Plumbing Fixtures - Material Approval 32d 16-Feb-2021 A 24-Mar-2021 A 100% 100% 0.00 Plumbing Fixtures - Material Approval
MPRO.1380
Plumbing Fixtures -PO Placement 8d 05-Apr-2021 A 13-Apr-2021 A 100% 100% 4,873.01 Plumbing Fixtures -PO Placement
ELECTRICAL 180d 02-Feb-2021 A 07-Sep-2021 50.61% 50.61% 117,633.00 07-Sep-2021, ELECTRICAL
LIGHTING FIXTURES 179d 03-Feb-2021 A 07-Sep-2021 40% 40% 42,149.00 07-Sep-2021, LIGHTING FIXTURES
MPRO.1430
Lighting Fixtures - Delivery 40d 24-Jul-2021 07-Sep-2021 0% 0% 25,289.40 Lighting Fixtures - Delivery
MPRO.1400
Lighting Fixtures - Material Submittal 6d 03-Feb-2021 A 09-Feb-2021 A 100% 100% 0.00 Lighting Fixtures - Material Submittal
MPRO.1410
Lighting Fixtures - Material Approval 33d 15-Feb-2021 A 24-Mar-2021 A 100% 100% 0.00 Lighting Fixtures - Material Approval
MPRO.1420
Lighting Fixtures - PO Placement 19d 05-Apr-2021 A 26-Apr-2021 A 100% 100% 16,859.60 Lighting Fixtures - PO Placement
FIRE ALARM & PUBLIC ADRESS SYSTEM 169d 03-Feb-2021 A 26-Aug-2021 40% 40% 18,108.25 26-Aug-2021, FIRE ALARM & PUBLIC ADRESS SYSTEM
MPRO.1470
FireAlarm & Public Adress System - Delivery 30d 24-Jul-2021 26-Aug-2021 0% 0% 10,864.95 FireAlarm & Public Adress System - Delivery
MPRO.1440
FireAlarm & Public Adress System - Material Submittal 5d 03-Feb-2021 A 08-Feb-2021 A 100% 100% 0.00 FireAlarm & Public Adress System - Material Submittal
MPRO.1450
FireAlarm & Public Adress System - Material Approval 46d 15-Feb-2021 A 08-Apr-2021 A 100% 100% 0.00 FireAlarm & Public Adress System - Material Approval
MPRO.1460
FireAlarm & Public Adress System - PO Placement 12d 04-Apr-2021 A 17-Apr-2021 A 100% 100% 7,243.30 FireAlarm & Public Adress System - PO Placement
Public Adress System 102d 22-Apr-2021 A 26-Aug-2021 40% 40% 9,051.30 26-Aug-2021, Public Adress System
MPRO.2270
Public Adress - Delivery 30d 24-Jul-2021 26-Aug-2021 0% 0% 5,430.78 PublicAdress - Delivery
MPRO.2260
Public Adress - PO Placement 4d 22-Apr-2021 A 26-Apr-2021 A 100% 100% 3,620.52 PublicAdress - PO Placement
Panel Boards and Power Cable 14d 02-Feb-2021 A 17-Feb-2021 A 100% 100% 20,792.00 17-Feb-2021 A, Panel Boards and Power Cable
MPRO.2540
Power Cable - PO 3d 14-Feb-2021 A 16-Feb-2021 A 100% 100% 5,152.80 Power Cable - PO
MPRO.2550
Power Cable-Delivery 2d 16-Feb-2021 A 17-Feb-2021 A 100% 100% 7,729.20 Power Cable-Delivery
MPRO.1480
Panel Boards - Material Submittal 7d 02-Feb-2021 A 09-Feb-2021 A 100% 100% 0.00 Panel Boards - Material Submittal
MPRO.1490
Panel Boards - Material Approval 3d 13-Feb-2021 A 15-Feb-2021 A 100% 100% 0.00 Panel Boards - Material Approval
MPRO.1500
Panel Boards - PO Placement 3d 14-Feb-2021 A 16-Feb-2021 A 100% 100% 3,164.00 Panel Boards - PO Placement
MPRO.1510
Panel Boards - Delivery 2d 15-Feb-2021 A 16-Feb-2021 A 100% 100% 4,746.00 Panel Boards - Delivery
INFORMATION & DATA SYSTEM 180d 02-Feb-2021 A 07-Sep-2021 40% 40% 27,532.45 07-Sep-2021, INFORMATION & DATA SYSTEM
MPRO.1550
Information & Data System - Delivery 40d 24-Jul-2021 07-Sep-2021 0% 0% 16,519.47 Information & Data System - Delivery
MPRO.1520
Information & Data System - Material Submittal 7d 02-Feb-2021 A 09-Feb-2021 A 100% 100% 0.00 Information & Data System - Material Submittal
MPRO.1530
Information & Data System - Material Approval 59d 15-Feb-2021 A 24-Apr-2021 A 100% 100% 0.00 Information & Data System - Material Approval
MPRO.1540
Information & Data System - PO Placement 10d 25-Apr-2021 A 05-May-2021 A 100% 100% 11,012.98 Information & Data System - PO Placement
SUBSTRUCTURE WORKS & CHECK FOR BUILDINGS - SCH 187d 09-Dec-2020 A 18-Jul-2021 A 100% 100% 96,954.00 18-Jul-2021 A, SUBSTRUCTURE WORKS & CHECK FOR BUILDING
RUH17TE1200
Eexecute Supporting Works for Reinforced Foundations 175d 20-Dec-2020 A 14-Jul-2021 A 100% 100% 84,750.00 Eexecute Supporting Works for Reinforced Foundations
RUH17TE1210
Execute Reinforced Concrete 30 MPa for staircases , Entrance Steps,Ramps 12d 05-Jul-2021 A 18-Jul-2021 A 100% 100% 2,712.00 Execute Reinforced Concrete 30 MPa for staircases , Entrance Steps,Ramp
RUH17TE1030
RemoveAll Residues Inside and Outside the Main Building 10d 10-Dec-2020 A 21-Dec-2020 A 100% 100% 5,650.00 RemoveAll Residues Inside and Outside the Main Building
RUH17TE1180
3 Sample OF Core Test For Columns 12d 09-Dec-2020 A 22-Dec-2020 A 100% 100% 2,712.00 3 Sample OF Core Test For Columns
RUH17TE1190
Check For Three Old Elements With Check Design 12d 10-Dec-2020 A 23-Dec-2020 A 100% 100% 1,130.00 Check For Three Old Elements With Check Design

Project Baseline Bar Critical Remaining ... Page 4 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
SUPERSTRUCTURE - SCH 220d 02-Jan-2021 A 22-Sep-2021 57.12% 65.01% 1,098,471.87 22-Sep-2021, SUPERSTRUCTURE - SCH
CONCRETE WORKS 167d 02-Jan-2021 A 21-Jul-2021 A 100% 100% 97,123.50 21-Jul-2021 A, CONCRETE WORKS
Ground Floor 167d 02-Jan-2021 A 21-Jul-2021 A 100% 100% 50,511.00 21-Jul-2021 A, Ground Floor
A1600 Check &Repair and Strenghting Of Existing Concrete Elements (Columns &Slabs) 167d 02-Jan-2021 A 18-Jul-2021 A 100% 100% 25,255.50 Check &Repair and Strenghting Of Existing Concrete Elements (Columns &
First Floor 157d 13-Jan-2021 A 21-Jul-2021 A 100% 100% 25,255.50 21-Jul-2021 A, First Floor
A1610 Check &Repair and Strenghting Of Existing Concrete Elements(Columns &Slabs) 157d 13-Jan-2021 A 21-Jul-2021 A 100% 100% 25,255.50 Check &Repair and Strenghting Of Existing Concrete Elements(Columns
Roof Floor 10d 23-Mar-2021 A 03-Apr-2021 A 100% 100% 46,612.50 03-Apr-2021 A,Roof Floor
A1620 Installation of Roof Sandwich Panels 10d 23-Mar-2021 A 03-Apr-2021 A 100% 100% 46,612.50 Installation of Roof Sandwich Panels
ROUGH FINISH - SCH 160d 10-Jan-2021 A 18-Jul-2021 A 100% 100% 48,388.32 18-Jul-2021 A, ROUGH FINISH - SCH
GROUND FLOOR 121d 10-Jan-2021 A 02-Jun-2021 A 100% 100% 9,249.91 02-Jun-2021 A, GROUND FLOOR
RUH17TE4500
Check and Complete for Internal and External Existing Block 70d 10-Jan-2021 A 31-Mar-2021 A 100% 100% 1,271.25 Check and Complete for Internal and External Existing Block
RUH17TE4780
Treating and Repairs Crack on Internal Plaster 65d 19-Jan-2021 A 04-Apr-2021 A 100% 100% 706.25 Treating and Repairs Crack on Internal Plaster
RUH17TE5090
Check and Change Water Proofing For Wet Area 10d 23-May-2021 A 02-Jun-2021 A 100% 100% 5,480.50 Check and Change Water Proofing For Wet Area
RUH17TE6530
Treating and Repairs Crack PLaster Works for Roof 13d 03-Mar-2021 A 17-Mar-2021 A 100% 100% 1,791.91 Treating and Repairs Crack PLaster Works for Roof
1ST FLOOR 158d 11-Jan-2021 A 17-Jul-2021 A 100% 100% 9,249.91 17-Jul-2021 A, 1ST FLOOR
MPRO.1890
Check and Complete for Internal and External Existing Block 98d 11-Jan-2021 A 04-May-2021 A 100% 100% 1,271.25 Check and Complete for Internal and External Existing Block
MPRO.1910
Treating and Repairs Crack on Internal Plaster 80d 18-Jan-2021 A 20-Apr-2021 A 100% 100% 706.25 Treating and Repairs Crack on Internal Plaster
MPRO.1920
Water Proofing For Wet Area 46d 25-May-2021 A 17-Jul-2021 A 100% 100% 5,480.50 Water Proofing For Wet Area
MPRO.1970
Treating and Repairs Crack PLaster Works for Roof 10d 09-Mar-2021 A 20-Mar-2021 A 100% 100% 1,791.91 Treating and Repairs Crack PLaster Works for Roof
Roof Floor 111d 08-Mar-2021 A 18-Jul-2021 A 100% 100% 29,323.50 18-Jul-2021 A, Roof Floor
A1110 Add A ProtectiveLayer With an Air-Resistant Material (PVC )for all the roof 111d 08-Mar-2021 A 18-Jul-2021 A 100% 100% 29,323.50 Add A ProtectiveLayer With an Air-Resistant Material (PVC )for all the roof
FACADE 39d 05-May-2021 A 22-Jun-2021 A 100% 100% 565.00 22-Jun-2021 A, FACADE
RUH17TE7210
Check and Repair External Plastering 39d 05-May-2021 A 22-Jun-2021 A 100% 100% 565.00 Check and Repair External Plastering
SOFT FINISH - SCH 207d 10-Jan-2021 A 15-Sep-2021 43.56% 54.56% 313,755.80 15-Sep-2021, SOFT FINISH - SCH
GROUND FLOOR 128d 22-Mar-2021 A 25-Aug-2021 52.11% 73.91% 106,553.35 25-Aug-2021, GROUND FLOOR
RUH17TE6520
Installation Celling Tiles & Gypsum Board and Alminium Strip 16d 08-Aug-2021 25-Aug-2021 0% 0% 1,398.38 Installation Celling Tiles & Gypsum Board and Alminium Strip
RUH17TE6390
Vinyel Roll With Screed if Needed 13d 15-Jul-2021 A 03-Aug-2021 23.08% 60% 53,064.80 Vinyel Roll With Screed if Needed
RUH17TE6550
Fix Saudi Bainco Granite Honed Tile Flooring 69d 02-Jun-2021 A 25-Aug-2021 57.97% 90% 13,221.00 Fix Saudi Bainco Granite Honed Tile Flooring
RUH17TE6510
Installation Susbending System For Celling 37d 21-Jun-2021 A 07-Aug-2021 64.86% 90% 1,398.38 Installation Susbending System For Celling
RUH17TE6380
Check and Change Broken Porcylian or Ceramic Floor With Skirting 103d 29-Mar-2021 A 03-Aug-2021 90.29% 90% 16,735.30 Check and Change Broken Porcylian or Ceramic Floor With Skirting
RUH17TE5730
Primer Painting For Walls 108d 23-Mar-2021 A 03-Aug-2021 90.74% 80% 8,136.00 Primer Painting For Walls
RUH17TE6440
Check and Change Broken Ceramic Tiles For Toilets Walls 109d 22-Mar-2021 A 03-Aug-2021 90.83% 90% 4,181.00 Check and Change Broken Ceramic Tiles For Toilets Walls
RUH17TE6540
Primer Painting For Roof 26d 24-May-2021 A 22-Jun-2021 A 100% 100% 8,418.50 Primer Painting For Roof
1st FLOOR 117d 22-Mar-2021 A 12-Aug-2021 82.3% 74.74% 31,849.05 12-Aug-2021, 1st FLOOR
MPRO.2040
Installation Celling Tiles & Gypsum Board and Alminium Strip 6d 07-Aug-2021 12-Aug-2021 0% 0% 1,398.38 Installation Celling Tiles & Gypsum Board and Alminium Strip
MPRO.2030
Installation Susbending System For Celling 26d 03-Jul-2021 A 05-Aug-2021 53.85% 75% 1,398.38 Installation Susbending System For Celling
MPRO.2000
Check and Change Broken Porcylian or Ceramic Floor With Skirting 104d 03-Apr-2021 A 09-Aug-2021 85.58% 78% 16,735.30 Check and Change Broken Porcylian or Ceramic Floor With Skirting
MPRO.1990
Primer Painting For Walls 102d 30-Mar-2021 A 03-Aug-2021 90.2% 73% 8,136.00 Primer Painting For Walls
MPRO.2010
Check and Change Broken Ceramic Tiles For Toilets Walls 109d 22-Mar-2021 A 03-Aug-2021 90.83% 90% 4,181.00 Check and Change Broken Ceramic Tiles For Toilets Walls
FOR ALL FLOORS 198d 10-Jan-2021 A 05-Sep-2021 31.04% 33.24% 139,306.40 05-Sep-2021, FOR ALL FLOORS
RUH17TE8130
Supply and installation of a Specific Identification Plate for the School 5d 31-Aug-2021 05-Sep-2021 0% 0% 5,085.00 Supply and installation of a Specific Identification Plate for the S
RUH17TE8530
Final Painting Coat For Wall 11d 01-Aug-2021 12-Aug-2021 0% 0% 17,594.10 Final Painting Coat For Wall
RUH17TE8490
Accessories for Toilets 10d 24-Jul-2021 03-Aug-2021 0% 0% 7,186.80 Accessories for Toilets
RUH17TE8540
Counters Installation 10d 04-Aug-2021 15-Aug-2021 0% 0% 16,215.50 Counters Installation

Project Baseline Bar Critical Remaining ... Page 5 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
RUH17TE8100
Advertising Boards of Natural cork Panels 6d 16-Aug-2021 22-Aug-2021 0% 0% 2,542.50 Advertising Boards of Natural cork Panels
RUH17TE8500
Installation Directory Signboard 6d 23-Aug-2021 29-Aug-2021 0% 0% 791.00 Installation Directory Signboard
RUH17TE2120
Lower and Upper Mounted 6d 30-Aug-2021 05-Sep-2021 0% 0% 10,509.00 Lower and Upper Mounted
RUH17TE8510
Supply and Install White Porcelain Board 20d 14-Aug-2021 05-Sep-2021 0% 0% 27,459.00 Supply and Install White Porcelain Board
RUH17TE8630
Final Painting For Roof 21d 03-Jul-2021 A 31-Jul-2021 66.67% 85% 8,418.50 Final Painting For Roof
RUH17TE8600
Stairs Granite 185d 10-Jan-2021 A 31-Jul-2021 86.49% 90% 43,505.00 Stairs Granite
FACADE 94d 25-May-2021 A 15-Sep-2021 32.45% 61.91% 36,047.00 15-Sep-2021, FACADE
RUH17TE8440
Saudi Bianco Granite ( skerting ) 47d 19-Jul-2021 A 15-Sep-2021 0% 10% 12,656.00 Saudi Bianco Granite ( skerting )
RUH17TE8210
External Painting Works (Work Shops &Profile &Painting With Marble ) 94d 25-May-2021 A 15-Sep-2021 50% 90% 23,391.00 External Painting Works (Work Shops &Profile &Painting W
METAL WORK-SCH 145d 29-Mar-2021 A 21-Sep-2021 71.03% 91.32% 139,952.21 21-Sep-2021, METAL WORK-SCH
RUH17TE8520
Installation Ladder 10d 11-Sep-2021 21-Sep-2021 0% 0% 3,390.00 Installation Ladder
RUH17TE8590
Installation Flag 10d 11-Sep-2021 21-Sep-2021 0% 0% 1,695.00 Installation Flag
RUH17TE8040
Handrail for All Floors 41d 29-Jun-2021 A 19-Aug-2021 41.46% 95% 25,538.00 Handrail forAll Floors
RUH17TE8610
Installation Shaft Cover made of Sandwiche panel 38d 22-Jun-2021 A 21-Sep-2021 60.53% 60% 1,525.50 Installation Shaft Cover made of Sandwiche panel
RUH17TE8330
Installation of Windows 122d 05-Apr-2021 A 01-Sep-2021 71.31% 95% 33,240.09 Installation of Windows
RUH17TE8400
Installation Metal Doors (Leafs) 111d 05-Apr-2021 A 19-Aug-2021 78.38% 95% 25,492.80 Installation Metal Doors (Leafs)
RUH17TE8370
Maintenance and Painting Steel Window Grill 107d 05-Apr-2021 A 15-Aug-2021 81.31% 95% 8,108.32 Maintenance and Painting Steel Window Grill
RUH17TE8620
Supply and Fix Steel Windows Grills 99d 12-Apr-2021 A 21-Sep-2021 81.82% 90% 18,362.50 Supply and Fix Steel Windows Grills
RUH17TE8030
Installation of Metal Door Frames 5d 29-Mar-2021 A 03-Apr-2021 A 100% 100% 22,600.00 Installation of Metal Door Frames
MECHANICAL WORKS - SCH 218d 04-Jan-2021 A 22-Sep-2021 72.22% 80.89% 251,399.01 22-Sep-2021, MECHANICAL WORKS - SCH
GROUND FLOOR 168d 17-Feb-2021 A 08-Sep-2021 85.54% 88.53% 36,937.35 08-Sep-2021, GROUND FLOOR
PLUMBING 43d 17-Feb-2021 A 07-Apr-2021 A 100% 100% 18,119.55 07-Apr-2021 A,PLUMBING
RUH17TE5430
First Fix Santairy and Water Supply Pipe 35d 17-Feb-2021 A 29-Mar-2021 A 100% 100% 13,158.85 First Fix Santairy and Water Supply Pipe
RUH17TE6370
Second Fix &Valve Installation 5d 03-Apr-2021 A 07-Apr-2021 A 100% 100% 4,960.70 Second Fix &Valve Installation
FIRE FIGHTING 4d 06-May-2021 A 10-May-2021 A 100% 100% 1,584.83 10-May-2021 A, FIRE FIGHTING
RUH17TE5420
Install Steel Pipe 4d 06-May-2021 A 10-May-2021 A 100% 100% 1,584.83 Install Steel Pipe
HVAC Works 130d 03-Apr-2021 A 08-Sep-2021 69% 75.41% 17,232.97 08-Sep-2021, HVAC Works
A1170 Celling Diffuser andAccessiors 12d 26-Aug-2021 08-Sep-2021 0% 0% 2,542.50 Celling Diffuser andAccessiors
A1150 Check & Install Internal Duct Works With insulation and Smoke Test 111d 03-Apr-2021 A 17-Aug-2021 80.18% 88% 14,125.00 Check & Install Internal Duct Works With insulation and Smoke Tes
A1160 Check of Flexible Duct 6d 09-Jun-2021 A 15-Jun-2021 A 100% 100% 565.47 Check of Flexible Duct
1st FLOOR 170d 01-Mar-2021 A 22-Sep-2021 81.94% 85.26% 36,416.60 22-Sep-2021, 1st FLOOR
PLUMBING 37d 01-Mar-2021 A 12-Apr-2021 A 100% 100% 18,119.55 12-Apr-2021 A,PLUMBING
MPRO.2120
First Fix Santairy and Water Supply Pipe 36d 01-Mar-2021 A 11-Apr-2021 A 100% 100% 13,158.85 First Fix Santairy and Water Supply Pipe
MPRO.2130
Second Fix &Valve Installation 6d 06-Apr-2021 A 12-Apr-2021 A 100% 100% 4,960.70 Second Fix &Valve Installation
FIRE FIGHTING 4d 08-May-2021 A 11-May-2021 A 100% 100% 1,064.08 11-May-2021 A, FIRE FIGHTING
MPRO.2140
Check ForAll Steel Pipe 4d 08-May-2021 A 11-May-2021 A 100% 100% 1,064.08 Check ForAll Steel Pipe
HVAC Works 108d 12-May-2021 A 22-Sep-2021 61.83% 68.85% 17,232.97 22-Sep-2021, HVAC Works
MPRO.2220
Celling Diffuser andAccessiors 12d 09-Sep-2021 22-Sep-2021 0% 0% 2,542.50 Celling Diffuser andAccessiors
MPRO.2200
Check & Install Internal Duct Works With insulation and Smoke Test 77d 12-May-2021 A 17-Aug-2021 71.43% 80% 14,125.00 Check & Install Internal Duct Works With insulation and Smoke Tes
MPRO.2210
Check of Flexible Duct 7d 16-Jun-2021 A 23-Jun-2021 A 100% 100% 565.47 Check of Flexible Duct
Roof Floor 14d 28-Feb-2021 A 15-Mar-2021 A 100% 100% 9,044.52 15-Mar-2021 A, Roof Floor
A1130 Supply and Installation of Gargouri Drainage Water 14d 28-Feb-2021 A 15-Mar-2021 A 100% 100% 9,044.52 Supply and Installation of Gargouri Drainage Water
FOR ALL FLOORS 216d 04-Jan-2021 A 20-Sep-2021 65.74% 77.26% 169,000.54 20-Sep-2021, FOR ALL FLOORS
PLUMBING 61d 29-Jun-2021 A 12-Sep-2021 44.18% 44.18% 23,344.67 12-Sep-2021, PLUMBING

Project Baseline Bar Critical Remaining ... Page 6 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
RUH17TE8070
Install and Testing PVC Water Storage Tank 15d 26-Aug-2021 12-Sep-2021 0% 0% 847.50 Install and Testing PVC Water Storage Tank
RUH17TE8060
Plumbing Fixture Installation 11d 14-Aug-2021 25-Aug-2021 0% 0% 12,182.53 Plumbing Fixture Installation
RUH17TE8050
Electrical Water Heater Installation 4d 29-Jun-2021 A 03-Jul-2021 A 100% 100% 10,314.64 Electrical Water Heater Installation
HVAC (AIR CONDITIONING) 216d 04-Jan-2021 A 20-Sep-2021 73.01% 87.11% 138,040.80 20-Sep-2021, HVAC (AIR CONDITIONING)
RUH17TE8250
Air Curtian 10d 26-Aug-2021 06-Sep-2021 0% 0% 3,118.80 Air Curtian
RUH17TE8350
Installing Exhaust Fans 106d 12-May-2021 A 20-Sep-2021 51.89% 10% 9,328.15 Installing Exhaust Fans
RUH17TE8380
AC Units - Instaling Inside & outside Machines 216d 04-Jan-2021 A 20-Sep-2021 76.39% 95% 125,593.85 AC Units - Instaling Inside & outside Machines
FIRE FIGHTING 4d 16-Sep-2021 20-Sep-2021 0% 0% 7,615.07 20-Sep-2021, FIRE FIGHTING
RUH17TE8360
Fire Extingusher With Cabient 4d 16-Sep-2021 20-Sep-2021 0% 0% 7,615.07 Fire Extingusher With Cabient
ELECTRICAL WORKS - SCH 207d 17-Jan-2021 A 22-Sep-2021 25.95% 26.72% 247,853.02 22-Sep-2021, ELECTRICAL WORKS - SCH
GROUND FLOOR 197d 17-Jan-2021 A 11-Sep-2021 46.76% 47.54% 51,066.94 11-Sep-2021, GROUND FLOOR
EARTHING SYSTEM 145d 09-Feb-2021 A 04-Aug-2021 92.41% 68% 1,469.00 04-Aug-2021, EARTHING SYSTEM
RUH17TE3150
Installation of Earthing Cable 145d 09-Feb-2021 A 04-Aug-2021 92.41% 68% 1,469.00 Installation of Earthing Cable
LIGHTING, UPS 197d 17-Jan-2021 A 11-Sep-2021 54.45% 54.45% 31,007.20 11-Sep-2021, LIGHTING, UPS
RUH17TE5770
UPS 5d 06-Sep-2021 11-Sep-2021 0% 0% 14,125.00 UPS
RUH17TE5100
First Fix Conduit and Box inside Wall and Slab 10d 17-Jan-2021 A 27-Jan-2021 A 100% 100% 8,441.10 First Fix Conduit and Box inside Wall and Slab
RUH17TE5760
Second Fix For Lighting and Poweroutlet 60d 31-Jan-2021 A 10-Apr-2021 A 100% 100% 8,441.10 Second Fix For Lighting and Poweroutlet
Fire Alarm and Detectors 127d 30-Mar-2021 A 01-Sep-2021 78.92% 95% 4,527.07 01-Sep-2021, FireAlarm and Detectors
MPRO.2310
Second Fix of FireAlarm and Detector 83d 24-May-2021 A 01-Sep-2021 57.83% 90% 2,263.54 Second Fix of FireAlarm and Detector
MPRO.2300
First Fix of Conduit and Boxes 4d 30-Mar-2021 A 03-Apr-2021 A 100% 100% 2,263.54 First Fix of Conduit and Boxes
Information and Date System 178d 22-Jan-2021 A 01-Sep-2021 91.42% 92.5% 2,262.82 01-Sep-2021, Information and Date System
RUH17TE5120
Second Fix of Information and Data System 169d 02-Feb-2021 A 01-Sep-2021 82.84% 85% 1,131.41 Second Fix of Information and Data System
RUH17TE5110
First Fix of Conduit and Boxes 2d 22-Jan-2021 A 24-Jan-2021 A 100% 100% 1,131.41 First Fix of Conduit and Boxes
Public Adress System 35d 24-Jul-2021 01-Sep-2021 0% 0% 6,882.51 01-Sep-2021, Public Adress System
MPRO.2280
First Fix of Conduit and Boxes 24d 24-Jul-2021 19-Aug-2021 0% 0% 3,441.26 First Fix of Conduit and Boxes
MPRO.2290
Second Fix of Public Adress System 32d 27-Jul-2021 01-Sep-2021 0% 0% 3,441.26 Second Fix of Public Adress System
Telephone System 35d 24-Jul-2021 01-Sep-2021 0% 0% 4,918.33 01-Sep-2021, Telephone System
A1200 First Fix of Telephone System 22d 24-Jul-2021 17-Aug-2021 0% 0% 2,459.16 First Fix of Telephone System
A1210 Second Fix of TelephoneSystem 12d 19-Aug-2021 01-Sep-2021 0% 0% 2,459.16 Second Fix of TelephoneSystem
1st FLOOR 196d 22-Jan-2021 A 15-Sep-2021 41.22% 42.48% 49,597.94 15-Sep-2021, 1st FLOOR
LIGHTING, UPS 178d 22-Jan-2021 A 25-Aug-2021 54.45% 54.45% 31,007.20 25-Aug-2021, LIGHTING, UPS
MPRO.2340
UPS 20d 03-Aug-2021 25-Aug-2021 0% 0% 14,125.00 UPS
MPRO.2320
First Fix Conduit and Box inside Wall and Slab 10d 22-Jan-2021 A 02-Feb-2021 A 100% 100% 8,441.10 First Fix Conduit and Box inside Wall and Slab
MPRO.2330
Second Fix For Lighting and Poweroutlet 59d 03-Feb-2021 A 12-Apr-2021 A 100% 100% 8,441.10 Second Fix For Lighting and Poweroutlet
Fire Alarm and Detectors 98d 03-May-2021 A 01-Sep-2021 78.66% 92.5% 4,527.07 01-Sep-2021, FireAlarm and Detectors
MPRO.2420
Second Fix of FireAlarm and Detector 82d 25-May-2021 A 01-Sep-2021 57.32% 85% 2,263.54 Second Fix of FireAlarm and Detector
MPRO.2410
First Fix of Conduit and Boxes 10d 03-May-2021 A 17-May-2021 A 100% 100% 2,263.54 First Fix of Conduit and Boxes
Information and Date System 29d 24-Jul-2021 25-Aug-2021 0% 0% 2,262.82 25-Aug-2021, Information and Date System
MPRO.2350
First Fix of Conduit and Boxes 12d 12-Aug-2021 25-Aug-2021 0% 0% 1,131.41 First Fix of Conduit and Boxes
MPRO.2360
Second Fix of Information and Data System 12d 24-Jul-2021 05-Aug-2021 0% 0% 1,131.41 Second Fix of Information and Data System
Public Adress System 29d 24-Jul-2021 25-Aug-2021 0% 0% 6,882.51 25-Aug-2021, PublicAdress System
MPRO.2390
First Fix of Conduit and Boxes 12d 12-Aug-2021 25-Aug-2021 0% 0% 3,441.26 First Fix of Conduit and Boxes
MPRO.2400
Second Fix of Public Adress System 12d 24-Jul-2021 05-Aug-2021 0% 0% 3,441.26 Second Fix of Public Adress System
Telephone System 30d 12-Aug-2021 15-Sep-2021 0% 0% 4,918.33 15-Sep-2021, Telephone System

Project Baseline Bar Critical Remaining ... Page 7 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
MPRO.2370
First Fix of Telephone System 12d 12-Aug-2021 25-Aug-2021 0% 0% 2,459.16 First Fix of Telephone System
MPRO.2380
Second Fix of TelephoneSystem 12d 02-Sep-2021 15-Sep-2021 0% 0% 2,459.16 Second Fix of TelephoneSystem
ROOF FLOOR 95d 18-May-2021 A 09-Sep-2021 60.07% 70.9% 23,334.50 09-Sep-2021, ROOF FLOOR
LIGHTNING And Power Cable 68d 18-May-2021 A 09-Aug-2021 77.94% 60% 6,384.50 09-Aug-2021, LIGHTNING And Power Cable
RUH17TE8270
Lightning and Powe Cable on Roof 68d 18-May-2021 A 09-Aug-2021 77.94% 60% 6,384.50 Lightning and Powe Cable on Roof
Earthing 90d 24-May-2021 A 09-Sep-2021 53.33% 75% 16,950.00 09-Sep-2021, Earthing
A1190 Installation Earthing System 90d 24-May-2021 A 09-Sep-2021 53.33% 75% 16,950.00 Installation Earthing System
FOR ALL FLOORS 182d 15-Feb-2021 A 22-Sep-2021 4.82% 3.51% 123,853.65 22-Sep-2021, FOR ALL FLOORS
LIGHTING 10d 12-Sep-2021 22-Sep-2021 0% 0% 78,761.00 22-Sep-2021, LIGHTING
RUH17TE8430
Installation of Power Cables 10d 12-Sep-2021 22-Sep-2021 0% 0% 12,882.00 Installation of Power Cables
RUH17TE8410
Installation Of Lighting Fixtures 10d 12-Sep-2021 22-Sep-2021 0% 0% 42,149.00 Installation Of Lighting Fixtures
RUH17TE8420
Installation Of Disconnect Switches 10d 12-Sep-2021 22-Sep-2021 0% 0% 23,730.00 Installation Of Disconnect Switches
Information and Data System 5d 12-Sep-2021 16-Sep-2021 0% 0% 13,766.23 16-Sep-2021, Information and Data System
A1220 Installation Accessiors 5d 12-Sep-2021 16-Sep-2021 0% 0% 13,766.23 Installation Accessiors
Public Adress System 5d 16-Sep-2021 21-Sep-2021 0% 0% 4,525.65 21-Sep-2021, Public Adress System
A1230 Installation Accessiors 5d 16-Sep-2021 21-Sep-2021 0% 0% 4,525.65 Installation Accessiors
PANEL BOARDS 171d 15-Feb-2021 A 09-Sep-2021 75.44% 55% 7,910.00 09-Sep-2021, PANEL BOARDS
RUH17TE5130
Supply install, test and commissioning of Branch Distribution Panels 171d 15-Feb-2021 A 09-Sep-2021 75.44% 55% 7,910.00 Supply install, test and commissioning of Branch Distribution
Telphone System 6d 31-Jul-2021 05-Aug-2021 0% 0% 9,836.65 05-Aug-2021, Telphone System
A1180 Installation of Accessiors 6d 31-Jul-2021 05-Aug-2021 0% 0% 9,836.65 Installation of Accessiors
Fire Alarm and Smoke Dtector 5d 01-Aug-2021 05-Aug-2021 0% 0% 9,054.13 05-Aug-2021, FireAlarm and Smoke Dtector
A1630 Installation of Smoke Detector and FireAlarm Devisces 5d 01-Aug-2021 05-Aug-2021 0% 0% 9,054.13 Installation of Smoke Detector and FireAlarm Devisces
Guard House 212d 04-Jan-2021 A 15-Sep-2021 67.74% 71.22% 166,583.47 15-Sep-2021, Guard House
Existing Structure Works Repair and Check 67d 05-Jan-2021 A 23-Mar-2021 A 100% 100% 9,944.00 23-Mar-2021 A, ExistingStructure Works Repair and Check
RUH17TE2160
R.C slab on Grade 8d 15-Mar-2021 A 23-Mar-2021 A 100% 100% 9,040.00 R.C slab on Grade
RUH17TE2170
R.C Ramps and Ground Stairs 13d 16-Feb-2021 A 02-Mar-2021 A 100% 100% 904.00 R.C Ramps and Ground Stairs
RUH17TE2130
Check and Repaie for Existing Structure Works 5d 05-Jan-2021 A 10-Jan-2021 A 100% 100% 0.00 Check and Repaie for Existing Structure Works
SUPER STRUCTURE 212d 04-Jan-2021 A 15-Sep-2021 65.69% 69.4% 156,639.47 15-Sep-2021, SUPER STRUCTURE
FINISHING WORK 212d 04-Jan-2021 A 15-Sep-2021 86.67% 90.23% 82,094.50 15-Sep-2021, FINISHING WORK
RUH17TE7870
Specialities With counters 10d 05-Sep-2021 15-Sep-2021 0% 0% 5,096.30 Specialities With counters
RUH17TE8120
External Painting 49d 03-Jul-2021 A 01-Sep-2021 28.57% 80% 3,955.00 External Painting
RUH17TE7420
Windows 122d 05-Apr-2021 A 01-Sep-2021 71.31% 88% 4,248.80 Windows
RUH17TE7430
Internal Painting 126d 31-Mar-2021 A 01-Sep-2021 72.22% 75% 6,497.50 Internal Painting
RUH17TE8110
External Plaster 38d 20-Jan-2021 A 04-Mar-2021 A 100% 100% 11,582.50 External Plaster
RUH17TE6400
Testing for insulation Works in theAreas Exposed to Water 5d 15-Mar-2021 A 20-Mar-2021 A 100% 100% 3,751.60 Testing for insulation Works in theAreas Exposed to Water
RUH17TE7410
Doors 79d 03-Apr-2021 A 06-Jul-2021 A 100% 100% 9,040.00 Doors
RUH17TE7100
Change the Invalid Floor tiles (Broken + Air blanks)with Skirting 4d 31-Mar-2021 A 04-Apr-2021 A 100% 100% 9,175.60 Change the Invalid Floor tiles (Broken + Air blanks)with Skirting
RUH17TE6340
Internal Cement Plastering 57d 11-Jan-2021 A 17-Mar-2021 A 100% 100% 9,181.25 Internal Cement Plastering
RUH17TE7110
Changing invalid Wall Tiles (Broken + With Air Spaces) 5d 03-Apr-2021 A 07-Apr-2021 A 100% 100% 1,582.00 Changing invalid Wall Tiles (Broken + With Air Spaces)
RUH17TE6800
Ceiling & Roof Finish 11d 17-Mar-2021 A 29-Mar-2021 A 100% 100% 3,661.20 Ceiling & Roof Finish
RUH17TE5450
Check and Repair on Block Works 9d 04-Jan-2021 A 13-Jan-2021 A 100% 100% 350.30 Check and Repair on Block Works
RUH17TE7220
Roof -protectivel layer With an Air-Resistant Material PVC 14d 25-May-2021 A 09-Jun-2021 A 100% 100% 3,729.00 Roof -protectivel layer With an Air-Resistant Material PVC
RUH17TE6070
Install Door Frame 24d 01-Mar-2021 A 28-Mar-2021 A 100% 100% 10,243.45 Install Door Frame
MECHANICAL WORK 153d 02-Mar-2021 A 04-Sep-2021 50.89% 57.4% 44,385.27 04-Sep-2021, MECHANICAL WORK

Project Baseline Bar Critical Remaining ... Page 8 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
RUH17TE7880
Fire Extinguisher 2d 02-Sep-2021 04-Sep-2021 0% 0% 285.89 Fire Extinguisher
RUH17TE7900
Plumbing Fixtures 15d 24-Jul-2021 09-Aug-2021 0% 0% 11,897.77 Plumbing Fixtures
RUH17TE8180
Exhaust Fan 10d 29-Jul-2021 09-Aug-2021 0% 0% 734.50 Exhaust Fan
RUH17TE7890
Electric water Heater 51d 30-Jun-2021 A 01-Sep-2021 31.37% 90% 3,118.80 Electric water Heater
RUH17TE6850
HVAC 118d 10-Apr-2021 A 01-Sep-2021 70.34% 75% 22,713.00 HVAC
RUH17TE6830
Water Supply System 7d 02-Mar-2021 A 09-Mar-2021 A 100% 100% 870.10 Water Supply System
RUH17TE6840
Drinage Pipe With Rain Drain 8d 23-Mar-2021 A 31-Mar-2021 A 100% 100% 4,765.21 Drinage Pipe With Rain Drain
ELECTRICAL WORK 184d 07-Jan-2021 A 17-Aug-2021 30.35% 30.35% 30,159.70 17-Aug-2021, ELECTRICAL WORK
RUH17TE6860
Panel Board 5d 04-Aug-2021 09-Aug-2021 0% 0% 1,864.50 Panel Board
RUH17TE7910
Lighting System Third Fix 10d 01-Aug-2021 11-Aug-2021 0% 0% 6,836.50 Lighting System Third Fix
RUH17TE6880
Power Socket & Disconnect Switches 7d 24-Jul-2021 31-Jul-2021 0% 0% 8,237.70 Power Socket & Disconnect Switches
RUH17TE7920
Telephone System 5d 12-Aug-2021 17-Aug-2021 0% 0% 1,130.00 Telephone System
RUH17TE7930
FireAlarm System 5d 12-Aug-2021 17-Aug-2021 0% 0% 2,938.00 FireAlarm System
RUH17TE6000
Lighting System First Fix 4d 07-Jan-2021 A 11-Jan-2021 A 100% 100% 4,576.50 Lighting System First Fix
RUH17TE6870
Lighting System Second Fix 5d 30-Jun-2021 A 05-Jul-2021 A 100% 100% 4,576.50 Lighting System Second Fix
Water Tank and Pumbs 164d 08-Mar-2021 A 22-Sep-2021 38.66% 57.75% 316,720.92 22-Sep-2021, Water Tank and Pumbs
Procurement 153d 08-Mar-2021 A 09-Sep-2021 75.16% 94.32% 110,657.51 09-Sep-2021, Procurement
A1590 Pumbs-Delivery 96d 17-May-2021 A 09-Sep-2021 56.25% 90% 62,823.48 Pumbs-Delivery
A1580 Pumbs -PO 22d 08-Mar-2021 A 01-Apr-2021 A 100% 100% 47,834.03 Pumbs -PO
Construction 67d 03-Jul-2021 A 22-Sep-2021 19.05% 38.11% 206,063.41 22-Sep-2021, Construction
RUH17TE2150
Check For Existing Concrete 5d 24-Jul-2021 28-Jul-2021 0% 0% 0.00 Check For Existing Concrete
RUH17TE2330
Epoxy Coating for Internal Walls With Plaster 5d 29-Jul-2021 03-Aug-2021 0% 0% 15,622.71 Epoxy Coating for Internal Walls With Plaster
RUH17TE2440
Check Leakage With Water Test 5d 04-Aug-2021 09-Aug-2021 0% 0% 6,384.50 Check Leakage With Water Test
RUH17TE2550
Water Proofing Membrane For External Walls and Slab 10d 10-Aug-2021 21-Aug-2021 0% 0% 11,492.10 Water Proofing Membrane For External Walls and Slab
RUH17TE2660
Fill WorkAround Tank 10d 22-Aug-2021 01-Sep-2021 0% 0% 0.00 Fill Work Around Tank
RUH17TE2800
Install ladder 10d 02-Sep-2021 13-Sep-2021 0% 0% 1,436.51 Install ladder
RUH17TE2900
Install Steel Cover Manhole 3d 14-Sep-2021 16-Sep-2021 0% 0% 638.45 Install Steel Cover Manhole
RUH17TE3020
Maintaince and PaintSteel Works for pumbs Room 3d 18-Sep-2021 20-Sep-2021 0% 0% 3,064.56 Maintaince and PaintSteel Works for pumbs Room
RUH17TE3280
Mechanchial installation 2d 21-Sep-2021 22-Sep-2021 0% 0% 5,258.27 Mechanchial installation
RUH17TE3540
Electrical installation 6d 11-Sep-2021 16-Sep-2021 0% 0% 5,107.60 Electrical installation
RUH17TE3530
Water Supply & Fire Pumps Installation 56d 03-Jul-2021 A 09-Sep-2021 25% 50% 157,058.70 Water Supply & Fire Pumps Installation
Elecrtical Room 215d 07-Jan-2021 A 22-Sep-2021 61.15% 61.15% 58,684.29 22-Sep-2021, Elecrtical Room
SUPER STRUCTURE 215d 07-Jan-2021 A 22-Sep-2021 61.15% 61.15% 58,684.29 22-Sep-2021, SUPER STRUCTURE
Check for Existing Concrete Structure 17d 22-Mar-2021 A 10-Apr-2021 A 100% 100% 3,729.00 10-Apr-2021 A,Check for Existing Concrete Structure
RUH17TE2090
Slab on Grade Beams 6d 29-Mar-2021 A 04-Apr-2021 A 100% 100% 2,825.00 Slab on Grade Beams
RUH17TE2100
R.C Stairs and Ramps 5d 05-Apr-2021 A 10-Apr-2021 A 100% 100% 904.00 R.C Stairs and Ramps
RUH17TE2080
Check and Repair of Concrete Structure Element 6d 22-Mar-2021 A 28-Mar-2021 A 100% 100% 0.00 Check and Repair of Concrete Structure Element
FINISHING WORK 212d 10-Jan-2021 A 21-Sep-2021 54.91% 54.91% 40,654.01 21-Sep-2021, FINISHING WORK
RUH17TE6270
External painting 5d 05-Sep-2021 09-Sep-2021 0% 0% 5,220.60 External painting
RUH17TE6280
Saudi Bainco Granite Honed Tread With Bull-Nose 5d 11-Sep-2021 15-Sep-2021 0% 0% 2,809.18 Saudi Bainco Granite Honed Tread With Bull-Nose
RUH17TE6290
Floor Epoxy & Finshing 5d 16-Sep-2021 21-Sep-2021 0% 0% 3,011.45 Floor Epoxy & Finshing
RUH17TE6260
Roof - install protective layer with an air-resistant material PVC 10d 24-Aug-2021 04-Sep-2021 0% 0% 1,728.90 Roof - install protective layer with an air-resistant material PVC
RUH17TE5680
Internal Paint Wall and slab 15d 25-Aug-2021 11-Sep-2021 0% 0% 5,559.60 Internal Paint Wall and slab
RUH17TE4770
Check for Existing Blok Works 5d 10-Feb-2021 A 15-Feb-2021 A 100% 100% 0.00 Check for Existing Blok Works

Project Baseline Bar Critical Remaining ... Page 9 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
RUH17TE5660
Doors 6d 13-Apr-2021 A 19-Apr-2021 A 100% 100% 5,650.00 Doors
RUH17TE5670
Check and Painting Existing Windows 10d 07-Apr-2021 A 18-Apr-2021 A 100% 100% 127.69 Check and Painting Existing Windows
RUH17TE5180
Internal Plastering Wall and Slab 53d 10-Jan-2021 A 11-Mar-2021 A 100% 100% 8,757.50 Internal Plastering Wall and Slab
RUH17TE5690
External Plaster 4d 01-Mar-2021 A 05-Mar-2021 A 100% 100% 3,167.39 External Plaster
RUH17TE5070
Door Frame 8d 23-Mar-2021 A 31-Mar-2021 A 100% 100% 4,621.70 Door Frame
MECHANICAL WORK 112d 13-Mar-2021 A 28-Jul-2021 0% 0% 766.14 28-Jul-2021, MECHANICAL WORK
RUH17TE5940
Fire Extingusher 5d 24-Jul-2021 28-Jul-2021 0% 0% 766.14 Fire Extingusher
RUH17TE5740
Check on Existing Exhaust Fan 7d 03-Apr-2021 A 10-Apr-2021 A 100% 100% 0.00 Check on Existing Exhaust Fan
RUH17TE5720
Check on Existing Drainage Pipe 7d 13-Mar-2021 A 20-Mar-2021 A 100% 100% 0.00 Check on Existing Drainage Pipe
ELECTRICAL WORK 215d 07-Jan-2021 A 22-Sep-2021 72.64% 72.64% 13,535.14 22-Sep-2021, ELECTRICAL WORK
RUH17TE5910
Lighting System Third Fix 5d 12-Sep-2021 16-Sep-2021 0% 0% 2,426.11 Lighting System Third Fix
RUH17TE5920
FireAlarm &Smoke Detector 5d 18-Sep-2021 22-Sep-2021 0% 0% 1,276.90 FireAlarm &Smoke Detector
RUH17TE5700
Panel Board 6d 14-Apr-2021 A 20-Apr-2021 A 100% 100% 2,553.80 Panel Board
RUH17TE5040
Lighting System First Fix 5d 07-Jan-2021 A 12-Jan-2021 A 100% 100% 1,404.59 Lighting System First Fix
RUH17TE5710
Lighting System Second Fix 6d 13-Apr-2021 A 19-Apr-2021 A 100% 100% 766.14 Lighting System Second Fix
RUH17TE4230
Earthing Protection System 8d 05-Apr-2021 A 13-Apr-2021 A 100% 100% 5,107.60 Earthing Protection System
Collective Tank 11d 24-Jul-2021 04-Aug-2021 0% 0% 904.00 04-Aug-2021, Collective Tank
Construction 11d 24-Jul-2021 04-Aug-2021 0% 0% 904.00 04-Aug-2021, Construction
STK1100 Steel Cover Manhole 11d 24-Jul-2021 04-Aug-2021 0% 0% 904.00 Steel Cover Manhole
EOT -NO.1 198d 27-Jan-2021 A 22-Sep-2021 0% 0% 0.00 22-Sep-2021, EOT -NO.1
EOT1-1090 Finish EOT 0d 22-Sep-2021 0% 0% 0.00 Finish EOT
EOT1-1080 Start EOT 0d 20-Jun-2021 A 100% 100% 0.00 Start EOT
Structural study of the building 118d 27-Jan-2021 A 16-Jun-2021 A 0% 0% 0.00 16-Jun-2021 A, Structural study of the building
EOT1-1130 Work lab test 27d 27-Jan-2021 A 27-Feb-2021 A 100% 100% 0.00 Work lab test
EOT1-1140 Submit & Reject Structural studay 1st 7d 21-Apr-2021 A 29-Apr-2021 A 100% 100% 0.00 Submit & Reject Structural studay 1st
EOT1-1150 Submit & Reject Structural studay 2nd 6d 17-May-2021 A 24-May-2021 A 100% 100% 0.00 Submit & Reject Structural studay 2nd
EOT1-1160 Submit & Approval Structural studay by structural committee 7d 08-Jun-2021 A 16-Jun-2021 A 100% 100% 0.00 Submit & Approval Structural studay by structural committee
EOT1-1170 Submit & Approval of a company for construction study 9d 03-Mar-2021 A 14-Mar-2021 A 100% 100% 0.00 Submit & Approval of a company for construction study
EOT1-1180 Submit & Reject Structural studay 3rd 4d 26-May-2021 A 31-May-2021 A 100% 100% 0.00 Submit & Reject Structural studay 3rd
EOT1-1190 Submit & Reject Structural studay 4th 2d 06-Jun-2021 A 08-Jun-2021 A 100% 100% 0.00 Submit & Reject Structural studay 4th
Engineer Work 14d 20-Jun-2021 A 05-Jul-2021 A 0% 0% 0.00 05-Jul-2021 A, Engineer Work
EOT1-1010 Submitting and approval of emergency door manufacturing plans 14d 20-Jun-2021 A 05-Jul-2021 A 100% 100% 0.00 Submitting and approval of emergency door manufacturing plans
EOT1-1020 Submitting and approving Handrialfixed plans 14d 20-Jun-2021 A 05-Jul-2021 A 100% 100% 0.00 Submitting and approving Handrialfixed plans
EOT1-1120 Submitting and approval method of work and material 7d 20-Jun-2021 A 28-Jun-2021 A 100% 100% 0.00 Submitting and approval method of work and material
G.B Treatment Work 23d 28-Jun-2021 A 28-Jul-2021 0% 0% 0.00 28-Jul-2021, G.B Treatment Work
EOT1-1110 Painting iron bars & Re-pour cover concrerte 8d 15-Jul-2021 A 28-Jul-2021 35.48% 0% 0.00 Painting iron bars & Re-pour cover concrerte
EOT1-1100 Remove concrete cover & replace the damaged iron bars 15d 28-Jun-2021 A 15-Jul-2021 A 100% 100% 0.00 Remove concrete cover & replace the damaged iron bars
Civil defense requirements 78d 20-Jun-2021 A 22-Sep-2021 0% 0% 0.00 22-Sep-2021, Civil defense requirements
Demolition Work 4d 20-Jun-2021 A 23-Jun-2021 A 0% 0% 0.00 23-Jun-2021 A, Demolition Work
EOT1-1000 Demolition wall 4d 20-Jun-2021 A 23-Jun-2021 A 100% 100% 0.00 Demolition wall
Finish work 74d 24-Jun-2021 A 22-Sep-2021 0% 0% 0.00 22-Sep-2021, Finish work
EOT1-1040 Plaster work 7d 06-Sep-2021 13-Sep-2021 0% 0% 0.00 Plaster work
EOT1-1050 Paintting work 8d 14-Sep-2021 22-Sep-2021 0% 0% 0.00 Paintting work
EOT1-1030 Masonary work 9d 24-Jun-2021 A 04-Jul-2021 A 100% 100% 0.00 Masonary work

Project Baseline Bar Critical Remaining ... Page 10 of 11 TASK filter: All Activities
© Oracle Corporation
Actual Work Milestone
Remaining Work Summary
RBL 22-7-2021 -Tahfeez Al Quran Obaeda Schedule Layout
Elementary in Sumaira RB 1 - B1
                  
Activity ID Activity Name Original Duration Start Finish Schedule % Performance % Budgeted Total Cost
Complete Complete 2021 2022
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Metal work 49d 06-Jul-2021 A 05-Sep-2021 0% 0% 0.00 05-Sep-2021, Metal work
EOT1-1060 Supply and fixed emergency door 49d 06-Jul-2021 A 05-Sep-2021 22.05% 100% 0.00 Supply and fixed emergency door
Handrail 21d 06-Jul-2021 A 03-Aug-2021 0% 0% 0.00 03-Aug-2021, Handrail
EOT1-1070 Supply and installation eiron emergency staircase 21d 06-Jul-2021 A 03-Aug-2021 51.81% 0% 0.00 Supply and installation eiron emergency staircase
TESTING & COMMISSIONING 10d 12-Sep-2021 22-Sep-2021 0% 0% 0.00 22-Sep-2021, TESTING & COMMISSIONING
RUH17TE8550
Testing & Commissioning B 10d 12-Sep-2021 22-Sep-2021 0% 0% 0.00 Testing & Commissioning B
RUH17TE8570
Handing Over The Project B 2d 21-Sep-2021 22-Sep-2021 0% 0% 0.00 Handing Over The Project B