Professional Documents
Culture Documents
Code: CON4110
Name of the
Lecturer……………………………………
Date of Submission……………………………………
TABLE OF CONTENTS
TABLE OF FIGURES.............................................................................................4
CHAPTER ONE......................................................................................................5
1.0 INTRODUCTION.....................................................................................5
1.1 BACKGROUND...........................................................................................9
CHAPTER TWO...................................................................................................17
2.0 INTRODUCTION.......................................................................................17
CHAPTER THREE................................................................................................20
3.1 CONCLUSION............................................................................................20
3.2 RECOMMENDATION...............................................................................22
REFERENCES.......................................................................................................22
P a g e 2 | 34
APPENDIX I..........................................................................................................23
APPENDIX II........................................................................................................30
APPENDIX III.......................................................................................................32
P a g e 3 | 34
TABLE OF FIGURES
P a g e 4 | 34
CHAPTER ONE
1.0 INTRODUCTION
P a g e 5 | 34
Project tendering. The document is prepared and presented to potential
contractors to use for the purpose of tendering for a project.
Works done by a contractor. The contractor can prepare the B.Q. to
quantify whatever is done and used to compare with those presented by the
Quantity Surveyor.
Cash flow forecasting during construction. Construction is a capital-
intensive work and therefore requires planning to avoid delays in
continuous payment to suppliers for construction materials supplied.
Value engineering. This is revealed by the itemized breakdown of the
requirements for construction. It is easy to identify overly reinforced
concrete structures by getting the reinforcement required and comparing
with industry standard.
a. Taking off: this is also referred to as the material take off because it
involves the calculation of the materials required to finish a project. It also
involves calculating material to be disposed.
b. Working up: this is a systematic process of working raw dimension data on
the dimension sheet to find the volumes, area, length, numbers and items.
The data is categorized in the abstracting and transferred to the billing to
form the B.Q.
P a g e 6 | 34
The column 1 is the timesing column where the multiplying numbers are written
down. Column 2 is the dimension column where the dimensions from the working
drawing are written down. Column 3 is the squaring column where the product of
columns 1 and 2 are recorded in the form of volume or area (Lee, Trench, &
Willis, 2014).
ii. Abstract sheet: this document assists in the transferring of values worked
in the dimension sheet to the final B.Q. The values are arranged in groups
in this document.
P a g e 7 | 34
iii. Billing sheet: this document has the categorized section of the calculated
quantities and the prices for the estimation of the cost of the work.
P a g e 8 | 34
Figure 5: Sample of a Query sheet
1.1 BACKGROUND
The project take-off for this project is done by using the Group method. This
method structures the quantities according to the process of construction. The
processes are;
Substructure: they are foundation strip, pad, retaining wall, masonry wall,
slab, beams, columns.
Superstructure: they are columns, beams, suspended slabs, beams
Electrical and mechanical installations: conduits, lighting, heating,
Internal finishes: they are plastering, painting, decorating
P a g e 9 | 34
1.2 METHOD STATEMENT AND JUSTIFICATION
P a g e 10 | 34
1.2.1 Concrete block curbs
These are precast concrete elements that are used on the edges of roads, gardens,
pedestrian walkways. The curbs can be straight or curved and the come in
different shapes and sizes.
Demarcate the transition from one zone to another. The curbs are used to
separate the road and pedestrian sidewalks.
Channel water from the engulfing surface such as road to the drainages.
They prevent the wearing of roads and sidewalk edges. The edges of roads
or sidewalks are the weakest zones and therefore need protection from
wearing off.
Protection of pedestrians from vehicles on the road. The use of high curbs
prevents the free movement of vehicle on to the sidewalks without
damaging the vehicle.
Aesthetic appeal. Use of colored and curved curbs beautifies a place.
P a g e 11 | 34
Figure 8: Sample forms of concrete curbs
1.2.2 Steel railing work
Roof railing is a continuous element that is constructed on the edge of the building
for protective and aesthetic purposes. The preferred material for railing is steel
due to the strength and durability. The steel used for the railing must be painted
with oil-based paint to prevent corrosion.
Steel railings come in different forms and patterns to enhance the aesthetics of a
building. The railings should be embedded in the concrete beams to assist in
resisting lateral movement.
P a g e 12 | 34
Figure 9: A picture of a roof railing
1.2.3 Steel reinforcement
These are used to covert light energy from the sun to electric energy. The
photovoltaic cells in the solar panel are made of crystalline silicone.
The photovoltaic sets produce more electricity when the sun is brightest and does
not produce electricity at night.
P a g e 14 | 34
The solar energy system consists of the following;
a) Solar panels: the solar panels are mounted outside in a position to absorb
maximum sunlight.
b) Inverter: the electricity from the solar panel is in Direct current (DC) and
needs to be converted to Alternating current (AC) by the inverter.
c) Switch board: this assists in changing power into the home between that
from the main grid and from the solar panel. The change is dependent on
solar energy production.
d) Battery: solar energy is produced during the day and may not be fully
utilized and therefore used to charge batteries that will release electricity at
night.
This is a document that shows the breakdown of the construction process from
ground breaking to the completion of the project. This document is represented by
a Gantt chart. The Gantt chart gives a good picture of the activities and their
execution. Some activities overlap and therefore speeding up the process of
construction.
P a g e 15 | 34
Figure 14: A sample of the works program
1.2.6 Hong Kong Standard Method of Measurement (HKSMM)
P a g e 16 | 34
CHAPTER TWO
2.0 INTRODUCTION
The take-off of the quantities of this project are guided by the HKSMM4. The
clauses within the document are self-explanatory. The main clauses used in
solving the project are;
The concrete block curb from the drawing is on the perimeter edge of the roof
slab. The curbs are classified as roof finishes in the final B.Q.
The steel railing located at the top of the roof and therefore falls under the
category of roof finishes in the B.Q. From HKSMM4 XV(e)2.5, the railing is to
be measured in linear meters.
P a g e 17 | 34
The steel railing will run along the centerline of the railing will run along the
centerline of the concrete curbs and therefore share the same length (Appendix I).
The photovoltaic sets for the project are to be supplied to the client towards the
completion of the project. The system is not located in any drawings and therefore
a query was raised to the Electrical engineer to clarify the system to be installed.
The reply was that there should be a provisional sum provided for the work but
advised that specialized solar system contractors be invited to tender for the
system. The amount of money to be spent on the system will be dependent on the
willingness of the client to spend money on the whole system.
The cost benefit analysis of the setting up of the solar system should be used to
advice the client on the capital investment into the proje
P a g e 18 | 34
2.5 WORKS PROGRAM
The works program comes into the agreement through the client – contractor
correspondence. The program sets out the timeline of the construction activities
and the completion date. This document is important in making project follow up
especially on the time.
P a g e 19 | 34
CHAPTER THREE
3.1 CONCLUSION
In an era where the effect of human activities on the environment is at its highest,
the calculation of quantities comes to the fore. It had been reported that finding
sustainable design solutions raises project cost by 10 percent (Cartlidge, New
Aspects of Quantity Surveying Practice, 2011).
BIM involves the management of the construction design, planning, execution and
documentation through the use of software. The use of BIM supports the
collaboration of the construction professionals on a project. This has been
predicted to be the doom of quantity surveyors. This is because the software is
able to generate the quantities easily without pen and paper.
The use of BIM in its infancy but over time will take over the industry. It is to the
professionals to find their niche and importance within this change.
P a g e 20 | 34
The role of BIM is;
a) Client participation: the use of BIM will integrate the client into the
process because of the visual nature of the project. The client input is
easier through the BIM interface.
b) Project planning: the use of a single file for all professionals eases the
process of planning because all the information from various project
professionals is converged into one file.
c) Reduction of cost: the use of traditional methods leaves a lot of room for
changes that make budgets unpredictable. The use of BIM reduces the
unpredictability and therefore minimal changes to the final construction
budget.
d) Time management: the correspondence between the project professionals
may take long when using the traditional method. BIM enables changes to
be made on the model and the interested party notified on the changes.
This reduces the face to face meetings and enable the professionals to
work from anywhere provided they have access to the model.
Th quantity surveying profession has been subject to ridicule for not adding value
in the project other than generating quantities. The management of the supply
chain by the quantity surveyor leads to reduced costs. Sum of the ways they lead
is through identification of lowly priced bids with few members within the chain.
This increases price flexibility. The contractors can be convinced into reducing
their margins to the benefit of the client.
The role of the quantity surveyor is central in the exchange of money between the
client and the contractor. The professional misconduct of the quantity surveyor
may lead to loss of money to the client or delay of the project caused by
undercutting the contractor’s work done leading to litigation. These
P a g e 21 | 34
3.2 RECOMMENDATION
REFERENCES
Del Pico, W. J. (2012). Estimating Building Costs for the Residential & Light
Commercial Construction Professional. Nw Jersey: John Wiley & Sons.
P a g e 22 | 34
Lee, S., Trench, W., & Willis, A. (2014). Willis's Element of Quatity Surveying.
West Sussex: John Wiley & Sons.
APPENDIX I
P a g e 23 | 34
P a g e 24 | 34
P a g e 25 | 34
P a g e 26 | 34
P a g e 27 | 34
P a g e 28 | 34
P a g e 29 | 34
APPENDIX II
P a g e 30 | 34
P a g e 31 | 34
APPENDIX III
FORMWORK
COLUMN FORMWORK
WALL FORM WORK
SUSPENDED SLAB FORMWORK
ROOF BEAMS FORMWORK
REINFORCEMENT WORK
COLUMN REINFORCEMENT AND CASTING
WALL REINFORCEMENT AND CASTING
SUSPENDED SLAB REINFORCEMENT AND CASTING
ROOF BEAMS REINFORCEMENT AND CASTING
MASONRY WALLING
GROUND TO SOFFIT OF BEAMS
PLASTERING
PAINTING
FURNITURE AND FITTING
TILLING
ROOF FINISHES
TILING
MECHANICAL AND ELECTRICAL WORKS
LAYING CONDUITS AND WATER PIPES
P a g e 33 | 34
CABLING
LIGHTING
P a g e 34 | 34