Professional Documents
Culture Documents
Quantity survey is a schedule of quantities of all the items of work in a building. At the
conceptual stage such estimation is done on the basis of conceptual drawings or in case of
any non-availability of such drawings, it is done on thumb-rule basis utilizing expertise and
experience of specialist. At the execution stage the quantities are calculated based on the
construction drawings.
1. Description and preparation of the bill of quantities and its items required for the
tender.
2. Preparation of the site material, material types, and material distribution
Accuracy, thoroughness, and ability to reconcile quantity and cost at every point of time are
the important qualities of a Good Quantity Surveyor.
Drawings
Complete and fully dimensioned drawings (i.e. plans, elevations, sections and other details)
of the building or work in question are required.
Specifications
Detailed specifications, giving the nature, quality and class of work, materials to be used,
quality of the material, their proportions, and method of preparation are required.
Rates
The rates of various of work, materials to be used in the construction, wages of different
categories of labor (skilled or unskilled) and cost of transportation charges should be
available for preparing an estimate of work cost.
Quantities can be calculated from the actual work done in the project site.
1. Quantity survey is essential to estimate before the construction starts the probable cost of
construction for the complete work. The construction cost includes cost of materials, cost of
transportation, cost of labor, cost of scaffolding, cost of tools and plants, establishment and
supervision charges, cost of water, taxes, and reasonable profit of the contractor, etc. The
estimate is required in inviting tenders for the works and to arrange contract for a complete
project.
2. Quantity survey is required to estimate the quantities of the various materials required
and the labor involved for satisfactory completion of a construction project.
3. It is also useful to check the works done by contractors during and after the execution.
Also, the payment to the contractor is done according to the actual measurements of the
completed part of each item of work.
4. A complete quantity survey or estimate is useful to provide useful advice to clients on:
(i) Valuation of properties (land and building) for sale, purchase and mortgage etc.
This is to find out an approximate cost in a short time. It is used to give an idea of the cost
of a proposed project. This estimate helps the client or sanctioning authority to make
decision of the administrative approval.
The approximate cost is prepared from the comparison with similar works. The
approximate cost can be found by using methods that depends on the area or cubic content
of a building and then multiplying this by an estimated rate for the unit of the area or cubic
content. Approximate quantities of materials and labor required per m2 of the area for a
proposed building also can be found.
Detailed Estimate
After getting the administrative approval, this estimate is prepared in detail prior to inviting
of tenders. The whole project is divided into sub-works, and the quantities of each sub-
work are calculated separately. The dimensions of the required work are taken from the
drawings of the project.
Quantity Estimates
This is a complete estimate of quantities for all items during project implementation.
Revised Estimate
Prepared if the estimate exceeded by 5% due to the rates being found insufficient or due to
some other reason.
Maintenance Estimate
Estimating required quantities and cost of work to maintain a structure (road, building,
etc.)
Quantity surveying and the estimated quantities of materials required on a project are
normally determined by professional surveyor or engineer.
The estimated quantities are provided to the interested bidders on a project to provide their
prices. In this method of bidding, the contractors are all bidding on the same quantities. The
estimators of contractors spend time developing the unit price of the different items in a
project. To win the bid, contractors will work on keeping the cost of purchasing and
installing the materials as low as possible.
As the project is built, the actual quantities are checked against the estimated quantities. For
example, if the estimated quantity of concrete for a wall is 23 m3, but the actual installed
concrete is 26 m3, then the contractor would be paid for the additional 3m3.
When there is a large difference between the estimated and actual quantities, an adjustment
to the unit price can be made. Small adjustments are usually made at the same unit as the
contractor bid. Large errors may require that the unit price be renegotiated.
If the contractor is aware of potential changes between the estimated quantities and those
that will be required in the project, the contractor may price his or her bid to take advantage
of this situation. For example, if the contractor is aware that the filling material in the
project will be changed from excavated soil to base-course, then he can provide low unit
price for filling with excavated soil (say P70/m3) and high unit price for the base-course
(say P210/m3). If the back-fill quantities were assumed to be 2000 m3 of soil and 100 m3
of base-course, so the assumed total price as in the bid will be P161,000.00. But if the
quantities were changed to 100 m3 of soil and 2000 m3 of base-course, then the new price
of the actual work because of this change will be P427,000.00, which will provide more
profit to the contractor.
Powerpoint
Powerpoint T
Templates
emplates
Page 1
Introduction to Quantity
Surveying
Powerpoint Templates
QUANTITY SURVEY???
Introduction
Once a construction project is completed or depending on the form of
contract upon completion of certain parts of the work, the contractor must
be paid for appropriately completed works.
This would then require that the actual works done be somehow
estimated or measured for payment purposes.
On the other hand to estimate how much a civil engineering project may
cost, the actual quantities of materials, labor, equipment etc. that is needed
for the construction work must be calculated at the beginning of the
work.
Such work of calculating the amount of materials and other
incidentals necessary for the realization of the work is called quantity
surveying.
Page 2
Powerpoint Templates
QUANTITY SURVEY???
Introduction Cont.
Quantity surveying is a term or processes used in the construction
industry to take measurements of civil works, prepare
specifications, and estimate the cost of works either for each trade of
work or for the whole project.
The term “surveying” means to inspect, study, review, investigate,
asses, and hence “to measure” therefore the term “quantity
surveying” means “quantity measuring” as applied to civil
engineering projects.
Quantity surveying is the application of standard methods of
measurement to quantify the amount of various items in a
construction project, for the undertaking of valuation, and certifying
payments.
Page 3
Powerpoint Templates
QUANTITY SURVEY???
Introduction Cont.
The following tasks are covered in quantity surveying.
1. Preparation of Specification
2. Taking measurements of civil works (Taking off quantities and
preparing BOQ)
3. Preparation of approximate (preliminary) cost estimate at the
very early stage of the project
4. Preparation of detail cost estimate at different stages (taking as
built measurements and preparing payment certificates or
approval of payment certificates prepared by taking
measurements)
5. Valuation of property
Page 4
Powerpoint Templates
QUANTITY SURVEY???
Pur pose of Quantity Sur veying
The purpose of quantity surveying hence the preparation of Bill of
quantities is:
i. Assist the client to have an accurate estimate of the volume of
work as well as the required budget.
ii. To assist in the accurate preparation of tenders, by providing
uniform measurement of quantities.
iii. To give an accurate checklist of work accomplished
iv. To assist in the certification of payments
v. To give insight into the required variation work amounts.
Page 5
Powerpoint Templates
ESTIMATE???
a. to judge tentatively or approximately the value, worth,
or significance of
b. to determine roughly the size, extent, or nature of
c. to produce a statement of the approximate cost of
Merriam - Webster
Page 6
Powerpoint Templates
Page 7
Powerpoint Templates
Purpose of Estimating
1. Estimating Materials
2. Estimating Labor
3. Estimating Equipment
4. Estimating Time
Page 8
Powerpoint Templates
Types of Construction Estimates
1. Estimates for Conceptual Planning
Page 9
Powerpoint Templates
Types of Construction Estimates
2. Estimates for Feasibility
±15 – 20 % accurate
Page 10
Powerpoint Templates
Types of Construction Estimates
3. Estimate During Engineering and Design
Page 11
Powerpoint Templates
Types of Construction Estimates
4. Estimates for Construction
•Subcontractor quotations
•Quantity takeoffs
•Construction procedures.
5% accuracy
Page 12
Powerpoint Templates
Types of Construction Estimates
5.Control Estimates.
Page 13
Powerpoint Templates
Estimating Techniques
Approximate Estimates
An approximate estimate is an approximate or rough estimate prepared
to obtain an approximate cost in a short time. For certain purposes the
use of such methods is justified.
Detailed Estimate
A detailed estimate of the cost of a project is prepared by determining the
quantities and costs of every thing that a contractor is required to provide
and do for the satisfactory completion of the work. It is the best and most
reliable form of estimate. A detailed estimate may be prepared in the
following two ways
Page 10
Powerpoint Templates
Qualification of an Quantity Surveyor
Page 15
Powerpoint Templates
Data Required for Preparing an Estimate
2. Specifications indicating
the exact nature and class
of materials to be used.
Page 16
Powerpoint Templates
Steps in Preparing Estimates
2. Squaring out
- Working out volumes, areas, etc. and casting up their total in recognized units.
3. Abstracting
- In the third step all the items along with the net results obtained in the second
step are transferred from measurement sheets to specially ruled sheets having
rate column ready for pricing.
Page 17
Powerpoint Templates
Work Breakdown Structure
Work Breakdown Structure (WBS)– provide a common
hierarchical framework for summarizing information and for the
quantitative reporting to customers (client/owner) and management.
Page 18
Powerpoint Templates
Page 19
Powerpoint Templates
Basics for Preparation of Estimates
Review Contract Documents
Prebid Conference – a meeting held prior to bid opening for the purpose of
explaining the project and answering questions that bidders have with respect to
the contract documents and the work.
Page 20
Powerpoint Templates
Basics for Preparation of Estimates
Planning The Work
Quantities
Page 21
Powerpoint Templates
Basics for Preparation of Estimates
Types of Cost
Direct Cost – all cost elements that can be associated with a specific item of
project work e.g. cost of labor, cost of materials, cost of equipment
Page 22
Powerpoint Templates
Basics for Preparation of Estimates
Historical production and cost data from similar past work are excellent
resources of when adequate details have been saved and adjustments to
project specifics can be defined.
Page 23
Powerpoint Templates
Basics for Preparation of Estimates
Unit Cost
Labor Unit Cost – cost based on a defined crew that performs the task
at an assigned production rate.
Page 20
Powerpoint Templates
Basics for Preparation of Estimates
cost for each task is developed by summing up the direct cost elements
for labor, equipment, materials, supplies and subcontractors.
Indirect cost and other markups associated with each task or work item
should be identified and considered properly.
Page 25
Powerpoint Templates
Basics for Preparation of Estimates
Supporting Documents
Page 26
Powerpoint Templates
Reference:
Page 27
Discussion Materials:
Part 1: Definition of Key Terms
Read and study lecture notes:
BID is the tender, or proposal, or quotation, or offer of a bidder to perform the work
described in the Contract which in form and substance complies with Instruction to
Bidders.
BID BOND refers to any acceptable form of bond accompanying the Bid submitted by the
bidder as a guarantee that the bidder will enter into the Contract with the Owner for the
construction of the Work, if the Contract is awarded to him.
CONTRACT is the term used to describe the Agreement and the Contract Documents.
DRAWINGS are graphical presentations of the Work. They include all supplementary
details and shop drawings.
GUARANTEE BOND is the approved form of security furnished by the Contractor and
his Surety as a guarantee of the quality of the materials provided, the equipment installed,
and the workmanship performed by the Contractor.
INSTRUCTION TO BIDDERS refers to the list of instructions regarding the manner bids
are to be prepared and the conditions for the award of the Contract.
PAYMENT BOND is the approved form of security furnished by the Contractor and his
Surety as a guarantee of good faith on the part of the Contractor to faithfully comply with
the Contract in respect of its obligations arising therefrom to its workers, subcontractors,
and suppliers .
PERFORMANCE BOND is the approved form of security furnished by the Contactor and
his Surety as a guarantee of good faith on the part of the Contractor to execute the Work in
accordance with the Contract.
In case of conflict between the provisions of the Agreement or of any Contract Document,
or between the provisions of one of the Contract Documents and the provisions of another
Contract Document, or in case of discrepancy, defective description, error or omission in
the Contract, the following rules shall be followed:
RULE 1: The Agreement and the Contract Documents shall be taken as mutually
explanatory of one another. The various provisions of the Contract shall be interpreted
together, attributing to the doubtful ones that sense which may result from all of them taken
jointly.
RULE 2: The provisions of the Civil Code of the Philippines on the interpretation of
contracts and of the Rules of Court on the Interpretation of Documents shall be applied.
RULE 3: Where the conflict between or among the provisions of the Agreement and/or the
Contract Documents cannot be resolved by Rules 1 and 2, it shall be understood that:
(a) the Detailed Drawings shall prevail over the General Drawings;
(b) words and figures shall prevail over the Drawings;
(c) words shall prevail over figures in Contract Documents;
(d) written dimensions shall prevail over measured dimensions.
RULE 4: Where the conflict cannot be resolved by applying Rule 3 or where Rule 3 does
not apply, the conflict shall be resolved by giving precedence to the Agreement or to
provisions of a Contract Document higher in order of priority among the various documents
which comprise the Contract. The order of priority among these documents shall be as
follows:
(a) Agreement as modified by Notice of Award of Contract, if such be the case, and the
Contractor’s conformity thereto:
(b) Instruction to Bidders and any amendment thereto:
(c) Addenda to Bid Documents;
(d) Specifications;
(e) Drawings;
(f) Special Conditions of Contract;
(g) General Conditions of Contract;
(h) Other Contract Documents; and
(i) Other documents forming part of the Contract attached thereto or incorporated
therein by reference.
Where the order of precedence is modified in the Agreement, such modified order of
precedence shall be followed; however, the mere listing of Contract Documents in the
Agreement or any Contract Document shall not be interpreted as establishing an order of
precedence among them.
RULE 6: The apparent silence of the Drawings, Specifications or any other Contract
Document as to any detail, or the lack of detailed description concerning any part of the
work, shall be understood to mean that good and accepted construction practice in
accordance with the usage or custom of the place shall be followed.
Step 2: Preparation of the Top Sheet. This is usually based on an examination of the
specifications table of contents. If there are no specifications, then the contractor should
use as a guide top sheets (summary sheets showing each trade) from previous estimates for
jobs of a similar nature, or checklists.
Step 3: Subcontractor Prices. Decide on which trades subbids will be obtained, and solicit
prices from subcontractors and suppliers in those trades. These requests for prices should be
made by postcard, telephone, or personal visit. Decide on which trades work will be done
by the contractor’s own forces, and prepare a detailed estimate of labor and material for
those trades.
Step 4: Pricing. Use either unit prices arrived at from the contractor’s own past records,
estimates made by the members of the contractor’s organization, or various reference books
that list typical unit prices Spreadsheets of unit prices for various types of work on different
structures may be maintained by a contractor. These can be updated electronically with new
wage and material costs, depending on the program used, so that prices can be applied
nearly automatically.
Step 5: Hidden Costs. Carefully examine the general conditions of the contract and visit
the site, to have a full knowledge of all the possible hidden costs, such as special insurance
requirements, portions of site not yet available, and complicated logistics.
Final Steps. Receive prices for materials and subcontracts. Review the estimate and
carefully note exclusions and exceptions in each subcontract bid and in material quotations.
Fill in with allowances or budgets those items or trades for which no prices are available.
Decide on the mark-up. This is an evaluation that should be made by the contractor,
weighing factors such as the amount of extras that may be expected, the reputation
of the owner, the need for work on the part of the general contractor, and the
contractor’s overhead.
Finally, and most importantly, the estimate must be submitted in the form requested
by the owner. The form must be filled in completely, without any qualifying
language or exceptions, and must be submitted at the time and place specified in the
invitation to bid. Sample table below shows part of an estimate and bid summary
produced for a multi-storey apartment building by a computer.
Preparation of estimates is facilitated by standardization of forms. These are used for
recording construction methods, equipment, and procedures that the estimator proposes as
best adapted to the various items of work; to record calculations of the estimated cost of
performing the work; and to summarize the estimated cost of the project. It is unnecessary
and impractical to provide detailed printed forms for all types of work. A few simple forms
are all that are needed. The mechanical makeup of an estimate must be simple because
conditions usually require that it be prepared in a short time—sometimes only two or three
days when the estimator would like to have a month. These conditions do not change; it
will always be necessary to make estimates quickly.
Lesson Two
Review of Bid Documents
BID DOCUMENTS AND CONTRACT DOCUMENTS
* The difference between bid and contract documents.
• The bid document applies to before the contract is
signed, whereas the contract document applies to
after the contract agreement is signed by the owner
and contractor .
*The bid documents consist of :
- The invitation to bid .
- Bid forms.
- Drawings.
- Specifications.
- Requirements of bonds and insurance.
- Addenda.
Bid Documents 2
* Why we need to bid documents?
The contractor used it in prepare an estimate and
submit a bid.
- It’s legal documents for construction and completion
of the project.
Bid Documents 3
• Contract Requirements:
1) Competitive contract.
2) Negotiated.
Bid Documents 4
_ The owner and engineer perform the evaluation of bids at
later date.
_ Most governments award contract to the lowest bidder,
provided all conditions of the contract have been met.
_ Private owners are not required to award the contract to
the lowest bidder but may select to the contractor
deemed most desirable for the project.
Bid Documents 5
• Arrangement of contract documents:
1) Legal matters:
- Bid forms.
- Bond requirements.
- Insurance requirements.
- General condition.
- Supplementary conditions of the contract.
Bid Documents 6
2) Technical matters :
- Plans (drawings).
- Specifications that describe the material,
workmanship, and methods of construction that are
required to build the project.
Bid Documents 7
• Building Construction Specifications:
It’s defined :
1) The quality of material.
2) Performance rating of equipment.
3) Level of workmanship.
4) Warranty requirements.
• Construction Specification Institute (CSI) Master
format organizes project information into major
divisions.
Bid Documents 8
A list of the CSI numbers and titles includes:
Bid Documents 10
Bidding requirements
• The information contained in this section of the contract
documents is extremely important to the estimating team . typical
information in the bidding requirements includes:
Bid Documents 11
Bid solicitation
• The bidding solicitation some times called the invitation to bid
contain the time that bids must be submitted . the estimator
must establish a plan to complete all work to meet the deadline
of the bid date , other wise the bid will be disqualified. The bid
solicitation also gives the name and address of the owner and
design organization with instructions on how to obtain the bid
documents.
Bid Documents 12
instruction to bidders
• The instruction to bidders section describes vital information that is
required to submit a bid. For example that may appear in the
instruction to is a statement that the contractor must make a
provision during execution of the contract document to allow the
owner to take advantage of the owner's contract documents to allow
the owner to take advantage of the owner's tax exempt status for
materials and equipment purchased for the project.
Bid Documents 13
Information Available to Bidders
Bid Documents 14
Bid forms
• The bid form defines the format that is required for submission of the
bid.
The format of the bid form impacts the assembly and summary of
costs in the final estimate . the owner may request the bid as lump
sum, unit prices based on predefined pay quantities in the bid
documents , or combination of both.
Bid Documents 15
• For construction project the work may priced by several method or
combination of the pricing method. The method selected depends on
distribution of risk between the owner and contractors.
Bid Documents 16
Bid form for lump-sum contracts
• for project where a complete set of plans and specification have
been prepared prior to construction and quantity of work is well
defined, the estimate is normally prepared for the purpose of
submitting a lump sum bid on the project. Building type project are
usually bid on a lump sum basis .
Bid Documents 17
• Its common practice for project to have one or more "alternates"
attached to the bid documents of lump sum contracts the alternate
may be to add or deduct a work item from the base of lump sum bid.
• A lump sum estimate must include the cost of all material, labor,
equipment, overhead, taxes, bonds and profit.
Bid Documents 18
Unit – Price contracts
Bid Documents 20
Addendum
• It is a change in the contract documents during
the bidding process, before a ward of the
contract.
• Addenda are issued to correct errors in the
contract documents or clarify an issue. May
concern addition to the work at the request of
the owner.
• The estimating team must be certain that the
costs of all addenda are included in the
estimate.
Bid Documents 21
Alternate
• It is an addition or subtraction to a base bid price for
substitutions requested by the owner during the
bidding process.
• Each alternate is listed and numbered separately in
the bid documents.
• For example:
An alternate No.1 may be add the parking lot.
An alternate No.2 may be deduct the sidewalks.
Bid Documents 22
Change order
Bid Documents 23
Warranties
25
Type of bonds
Three type of bonds are commonly
required in construction contracts (as
the book):
1. Bid bond.
2. Performance bond.
3. Payment bond.
26
Bid Bond
• It is ensure the owner that the contractor will sign
the contract for the bid amount, if the bidder refuses
or fails to sign the contract, the owner may retain the
bond or check as liquidated damages.
• Its amount equal to (5-20)% of the amount of the
bid.
27
Performance Bond
• It is ensure the owner that the contractor
will perform all work in accordance with the
contract documents.
• Performance bond last for the period of
construction of a project.
• Its amount 25,50,100% of the contract, but
the cost of the bond usually is based on:
1. Amount of the contract.
2. Duration of the project..
28
Payment Bond
or Material and Labor Payment Bond
29
Maintenance Bond is
not mentioned in this
book.
30
If the contractor:
default,
31
Insurance
• The contractor must secured insurance, because
there are many risks involved in construction.
• The precise losses that are reimbursable from
insurance are based on predetermined losses
named in the insurance policy.
32
Types of Available Insurance for Construction
Projects
1. Basic Builder's Risk Insurance.
2. Public Liability and Property Damage
Insurance.
3. Workmen’s Compensation Insurance.
4. Contractor’s Equipment Floater.
33
Basic Builder's Risk Insurance
• General Builder's Risk which covers damages to the
project due fires, wind, and hail.
• Insurance is based on the estimated completed
value of the project, so the premium rate usually is
set at 60% of the complete value.
• Basic Builder's Risk Insurance varies with the type
and location of the structure.
34
Public Liability and Property Damage Insurance
• It protects the contractor against injuries to the
general public or public property due to actions of
the employees while performing works.
• The cost of this insurance depends on the type of
work and the safety record of the contractor.
• It is range from (2-8)% of the base cost of the labor.
35
Workmen’s Compensation Insurance
• To protect workers as a result of injury or death on a project.
• It provides medical expenses and payment of lost wages during the
period of injury.
• The cost can range from (10-30)% of the base cost of the labor,
depending on the type of work that is performed by each worker.
36
Contractor’s Equipment Floater
• It provides protection against loss or damages to equipment because
of fire, tornado, flood, perils of transportation, and theft.
• The cost varies with location, it is about $1.50 per $100.00 of
equipment value per year.
37
Building construction drawings
title sheet (This sheet contains the name of the project, owner,
designer, and other pertinent information related to the project).
Bid Documents 38
Title sheet
Bid Documents 39
Building construction drawings
index sheet (which provides a summary of all the remaining sheet in
the drawings, Its shows the list of drawing. For building type project, the
remaining sheets generally follow this arrangement: civil, architectural,
structural, mechanical, electrical, plumbing, and fire protection. A letter
before the sheet number identifies each drawing. For example, the civil
drawing are number C1, C2, C3, etc.; the architectural drawings are
number as S1, S2, S3, etc).
Bid Documents 40
Index sheet
Bid Documents 41
Building construction drawings
Plans, elevations, and sections(he pictorial presentations used in
drawings are shown from several viewing angles).
plane views (Views looking vertically down on the object ).
elevation views (Views looking horizontally at an object ).
Bid Documents 42
Plane views
Bid Documents 43
Building construction drawings
perspective views (Views looking at an object
from a point that is not perpendicular to any face
of the object).
A section view (view of the object as seen by
passing a cutting plane through the object)
A detail (is an enlargement of a specific area of a
project. Connections of structural components are
generally sown as details).
Bid Documents 44
Detail drawing
Bid Documents 45
Building construction drawings
Bid Documents 46
Building construction drawings
Line Work:
Several types of line work that are used in preparing
drawings include:
• Thick lines-outline edges of objects (plans and elevations).
• Thin lines with short dashes-denote the centerline of an
object
• Phantom lines-show the path of moving parts
• Broken lines-denote the object is longer than shown
• Short dashed lines-denote edges on the object that cannot
be seen from the near side surface of the object
Bid Documents 47
Building construction drawings
• Scales
• Usually the type of scale used is identified at the bottom of
the page on the drawings. However, several different scale
may be used on a single sheet. Therefore, it is important to
be certain that the correct scale is used in determining the
quantities for estimating. Occasionally, a portion of the
drawing is shown without any scale. When this condition
exists, there should be a note that states the drawing is not
to scale. The estimator must also be cautious because
sometimes the drawings are reduced in size, such as a half-
size drawing, to permit easier handling during construction.
Bid Documents 48
Building construction drawings
• Scales
• Two types of scales are used in construction drawings, the architect’s scale
and the engineer’s scale. The architect’s scales that are commonly used for
plans and elevations include 1/32 in. = 1 ft and 1/16 in. = 1 ft. Complicated
areas often use the ¼ in. = 1 ft, or ½ in. = 1 ft on the architect’s scale. Special
applications that require high details are 1.5 in. = 1 ft, or 3 in. = 1 ft, or may
be drawn to a half or even a full scale.
• The engineer’s scale, graduated in tenths of an inch, is often used for civil,
structural, and mechanical drawings. The scales are 10, 20, 30, 40, 50, and
60. The higher numbers of 50 or 60 are used for large areas, such as site-
work or plot plans. Details of drawings often use the smaller numbers, such
as 10, 20, or 30. The 40 on the engineer’s scale is equivalent to the ¼ in. on
the architect’s scale.
Bid Documents 49
Building construction drawings
• Schedules
• To simplify the presentation of repetitious items (such as
footings, columns, doors, windows, room finishes, etc.) a
schedule is frequently used. A schedule is a tabular listing
of the repetitive items in the project. For example, a room
schedule is a tabular list of all rooms in the structure,
showing the type of floor covering, wall covering, and type
of ceiling. Likewise, a footing schedule is a listing of all
footings in the foundation, showing the diameter, depth,
type, size, and number of reinforcing bars. Thus, a schedule
is a concise and convenient method to show all common
types of items in one location.
Bid Documents 50
Building construction drawings
• Symbols and abbreviations
• Symbols are used on the drawings to identify the
types of materials and work required during
construction. Examples are valves, pumps, type of
welds, electrical outlets, etc. Abbreviations of
organization that produce technical information
and standards for materials and construction
procedures are frequently referenced in the
specifications of contract documents.
Bid Documents 51
Detail drawing
Bid Documents 52
DETAILED SPECIFICATION
• Nature of work
• Gives description of work in a detailed manner
signifying type /category of work.
• At different levels places structures buildings
etc
• Eg. Masonry in ..., plaster…., Flooring...,
Cladding... Etc for the material used.
DETAILED SPECIFICATIONS
• Materials involved
• Lists out various materials which are used in work
specifying
– Name,
– Class or grade,
– Type,
– Category.
• Tolerances
– Gives limit measured from true level /dimension up to which
material / workmanship could be accepted.
– This is in reference to the provisions under standard I.S. Codes of
practice or other references as per contract.
DETAILED SPECIFICATIONS
• Material specification
Gives physical and chemical composition of the material, it’s
properties according to relevant standards and also extent of
performance required of material viz. Acceptable limits.
• Work procedure
Gives a detailed description of various steps involved in
execution of work including necessary pre-cautions as
required.
• Method of measurement
• Specifies mode of measurements for various kinds of
work.
• This is based on the procedures given in contract
/standard I.S. Codes and others as the case may be.
• METHOD OF PAYMENTS
• Specifies procedures /rules governing terms of payments, stages
of payments, and modus - operandi for payments of various kinds
of works.