Professional Documents
Culture Documents
WEEK 1
LEARNING OUTCOMES (CO1-PO1)
Understand the construction stages and where is bill of quantity being produced
??????
m3 ?
kg ?
@nurkamaliahmustaffa2013
HOW TO CALCULATE THE QUANTITIES?
m3 ?
@nurkamaliahmustaffa2013
Who responsible for civil engineering quantities?
Quantity Surveyor
– the application of expert knowledge in measure the
quantity and estimation of the cost and prices of labour,
materials and plant required.
Why?
TAKING OFF
•It is the process of measuring from drawings and
recording all dimensions in recognized form on
a special ruled paper called “Dimension Paper”
BILL OF QUANTITIES
•A list of items giving the quantities and brief description of
work to be carried out with is respective quantity and unit
cost for carrying out each work.
What is taking off sheet?
A process of measuring from drawings, recording all dimensions in recognized form called taking
of sheet or “dimension paper”
@nurkamaliahmustaffa2013
Leave blank
A list of items giving the quantities and brief description of work to be carried out with its
respective quantity and unit cost for carrying out each work.
Bill of Quantities
The purpose of Bill of Quantities (BQ):
1. To set down the various items of works in a logical sequence so that it readily
priced by contractor.
2. Enables all the contractors to tender on the same information.
3. Provide a convenient basis for valuation of stage payments during the
contract, before the accurate remeasurement figure are available.
4. Provide an approximate checklist for the contractor to order materials and
plan for other resources.
5. Provide data for cost analyses for use in cost planning of future projects.
6. Contractors are saved the costly exercise of each having to take off
quantities for themselves.
The Bills of Quantities
The Bills of quantity prepared by Quantity Surveyor based on
measurement from the construction drawings / building plans
and specification prepared by the designers/ engineers.
Function:
To standardize the method of preparing the measurement for building
works and civil engineering works. Contains of rules and principles
of measurement.
Malaysian Standard Methods of Measurement for Building
works. (SMM2) – Institution of Surveyors Malaysia (ISM)
(adapted from SMM by RICS(UK)
Malaysian Standard Method of Measurement for civil
engineering works (CESMM) – CIDB (adapted from CESMM
by ICE / FCEC(UK)
Standard Methods of Measurement for Building
Works (SMM)
Set out rules for the measurement and
description of building works.
SMM2 is a document that provides not
only a uniform basis for measuring
building work but also embodies the
essentials of good practice.
Without using it, a set of rules the quality
of BQ can vary widely.
Malaysian Standard Method of Measurement for
Civil Engineering Works (CESMM)
To be used in conjunction with the Conditions Of
Contract for Civil Engineering Works.
Before this document is produced, the party who responsible for the
working measurement refers to the method adopted in the United
Kingdom named ‘CESMM 2nd Edition or 3rd Edition’.
The actual measurement work must take into account the level of
complexity of work undertaken. Work measurement for any one
item of work is also closely related to the methodology and
construction activities
Malaysian Standard Method of Measurement
for Civil Engineering Works
MALAYSIAN STANDARD METHODS OF
MEASUREMENT FOR CIVIL
ENGINEERING WORKS is to be used in
conjunction with the Conditions Of
Contract for Civil Engineering Works.
Objective of CESMM
related charge.
A tenderer may insert in the BQ the method related charges
as he may decide to cover items of works relating to his
intended method of executing the works, the cost of which are
not to be considered as proportional to the quantities of the
other items and for which he has not allowed in the rates and
prices for the other items.
Basic contents of typical contract
documents
Conditions of contract
Contract drawings
Specification
Preambles
Bills of quantities
Schedule of rates
Contract Documentation for Civil
Engineering
1. Conditions of contract –a written agreement intended to
be enforceable by law to bind the appointed contractor with
the employer based on an agreed conditions.
2. Contract Drawings – technical / detailed construction
drawings for measurement / costing by QS / engineers –
prepared by architect / engineers.
3. Specification / Preambles - A concise description of
materials and workmanship, standard or quality of
workmanship. It must convey the architect and engineer’s
requirements.
4. Bill of Quantities – prepared by Quantity Surveyor based
on measurement from the construction drawings / building
plans This document were itemized all the quantities for each
categories of works applied in constructing the buildings. E.g.
building works, mechanical, electrical works, civil, structural
works, infrastructure works, etc. The contractor will
priced /estimate all the works associated in completing the
buildings during pre-construction stage.
Purpose / Objectives / Roles
Project stages Explanation
PRE- Tendering stage To enable the contractor to tender to a project & price the
CONTRACT described works.
(before official
contract signed To control in ordering materials and assessing the labour
between client requirement for the contract.
– contractor)
Preliminaries
Specifications of materials and workmanship
Preambles (only in Bill of Approx Qtty)
Measured works bill
Schedules of rates (only in Bill of Approx Qtty)
Preliminaries
It must:
Contain a definition of the scope of works and details of the
proposed form of contract / project.
Contain a detailed description of the administrative
mechanism / temporary facilities to implement the contract /
project.
Contain list of drawings and any special instructions to the
contractor – highlighting the method of pricing and
presenting tenders and other site information.
Specification
Working up / squaring Calculating and totaling the area, length, volume, numbers, item of
the dimensions to obtain the exact quantities for each measured item in
the dimension sheet.
Transfer to abstract Collecting the totals form dimension paper on to an abstract to produce
sheet a final total for each individual description.
Billing Reproducing the items from the abstract on to bill paper in draft form
ready for typing.
Preparation of billing
item description Qty unit rate amount
Cubic measurement = m3
Square or superficial measurement = m2
Linear measurement = m
Enumerated items – Nr/ Nos.
Items
Expressions of Measurement /
Rules in setting down the
dimension
•Deletions with
correcting fluid are
not encourage.
Note:
Anding-on , deductions
shall be in similar form of
dimension.
Rules in setting down the dimension:
Deductions
Where a deduction is to be made, the
description is preceded by Deduct which
is often abbreviated to Ddt.
An example as follows: