Excavated material
E over 250mm average thick; arising from excavations m3 207 500.00 103,500.00
SURFACE TREATMENT
PESTICIDES: DIELDREX 20
J Applying to surfaces m2 525 40.00 21,000.00
To Collection 1,283,950.00
INSITU CONCRETE
PLAIN: GRADE 15
Beds
not exceeding 100mm thick; poured on earth surfaces ;as
A m3 7 23,000.00 161,000.00
blinding
REINFORCED: GRADE 20
REINFORCED: GRADE 25
FORMWORK: SAWN TO
Columns
M 20mm diameter high yield reinforcement bars t 1.30 300,000.00 390,000.00
To Collection 5,141,800.00
BRICK/BLOCK WALLING
Walls
A 230 thick filled solid with concrete grade 15 m2 320 4,500.00 1,440,000.00
Collection 1,440,000.00
COLLECTION
SUBSTUCTURE 7,865,750.00
Carried to Summary
INSITU CONCRETE
REINFORCED: GRADE 25
FORMWORK: SAWN TO
2514
step flight; 1.0mm wide; 150mm vertical risers; 175mm
T m 36 800.00 28,800.00
waist and 250mm horizontal threads
To Collection 12,746,600.00
REINFORCEMENT: TO BS 4449
Columns
Suspended slabs
Floor beams
Roof beams
Roof slab
To Collection 11,049,900.00
Lintels
To Collection 570,000.00
COLLECTION
C MASONRY
BRICK/BLOCK WALLING
Walls
MASONRY 6,650,000.00
Carried to Summary
D STRUCTURAL/CARCASSING METAL/TIMBER
E CLADDING/COVERING
Ridge capping
Valley capping
Pegola
CLADDING/COVERING 2,038,000.00
Carried to Summary
F LININGS/SHEATHING/DRY PARTITIONING
POP
POP Cornices
POP Screeding
G WINDOWS/DOORS/STAIRS
METAL WINDOWS
Fixed Glass:
To Collection 1,928,126.00
DOORS/SHUTTERS/HATCHES
TIMBER DOORS
STEELDOOR
To Collection 3,360,000.00
Burglar proofing
To Collection 1,463,658.00
METAL BALUSTRADES
To Collection 714,000.00
COLLECTION
L WINDOWS/DOORS/STAIRS 7,465,784.00
Carried to Summary
H SURFACE FINISHES
A Floated; 12mm thick to receive ceramic wall tiles m2 567 1,000.00 567,000.00
To Collection 1,776,100.00
Walls
To Collection 5,369,000.00
Walls
To Collection 5,659,775.00
C Ditto surfaces not exceeding 300mm wide; internal m 435 240.00 104,400.00
D Ditto surfaces not exceeding 300mm wide; external m 345 240.00 82,800.00
J Over 300mm wide; to burglar proofing & stairs balustrades m2 0 600.00 0.00
To Collection: 4,327,840.00
COLLECTION
J FURNITURE/EQUIPMENT
FURNITURE/EQUIPMENT 15,000,000.00
Carried to Summary
IRONMONGERY
L ELECTRICAL INSTALLATIONS
LV DISTRIBUTION
V20 LV DISTRIBUTION
Carried to Summary 308,000.00
GENERAL LIGHTING
1.5mm2 cables
Flourescent;
Ceiling mounted;
To Collection 5,191,000.00
Wall mounted;
To Collection 3,408,000.00
COLLECTION
Page 22 5,191,000.00
Page 23 3,408,000.00
GENERAL LV POWER
B Ditto for piping and wiring of all double socket outlet points
nr 36 7,000.00 252,000.00
C Allow for piping and wiring of all water heater socket outlet
points nr 24 8,000.00 192,000.00
D Allow for piping and wiring of all AC socket outlet points nr 30 8,000.00 240,000.00
E Allow for piping and wiring of all cooker control outlet points
nr 6 9,000.00 54,000.00
TV cables
F Allow for piping and wiring of all TV outlet points nr 24 5,000.00 120,000.00
Telephone cables
G Allow for piping and wiring of all telephone outlet points nr 24 5,000.00 120,000.00
ACCESSORIES FOR ELECTRICAL SERVICES
To Collection 1,365,000.00
To Collection 72,000.00
COLLECTION
Page 24 1,365,000.00
Page 25 72,000.00
SUMMARY
ELECTRICAL INSTALLATIONS
Carried to General Summary 10,344,000.00
M MECHANICAL INSTALLATIONS
To Collection 1,196,000.00
Allow a provisional sum of N664, 000 for the piping of; Air
Conditioning Foul Drainage above ground, Foul
Drainage below ground,(Cold and Hot Water supply to
E 664,000.00
be pipe with RIFENG PIPE ). Sum to be expended as
directed by engineer and as may be re-measured by the
Quantity Surveyors.
To Collection: 896,000.00
COLLECTION
PIPELINES
PIPELINE ANCILLARIES
SUMMARY
ITEM DESCRIPTION N : K
A GROUNDWORK 7,865,750.00
C MASONRY 6,650,000.00
E CLADDING/COVERING 2,038,000.00
G WINDOWS/DOORS/STAIRS 7,465,784.00
J FURNITURE/EQUIPMENT 15,000,000.00
VAT % 5 4,957,312.45
SUM TOTAL TO EXECUTE PROJECT
Carried to GENERAL SUMMARY 104,103,561.45