MATERIAL TAKE OFF FIRE WATER PUMP HOUSE

A. DATA STRUKTUR

Gambar - Model Struktur

F. MATERIAL TAKE OFF

No Profil Panjang (m) Berat (ton)


1 WF 400.200.8.13 20 1.28
2 WF 350.175.7.11 15 0.70
3 WF 250.125.6.9 25 0.70
4 WF 200.100.5,5.8 25 0.50
5 2L 60.60.5 67 0.59
6 RD 23 0.03
3.80

3
No Profil Berat (ton) BJ Vol. (m )
1 PD_50/50 2.40 2.4 1.00
2 TB_30/50 10.81 2.4 4.50
3 S-15 17.66 2.4 7.36
Jumlah Luas Tebal
4 F1_150/150 4.0 2.25 0.7 6.30
19.16

G. TIANG PANCANG (N/A)


No Diameter Pancang Panjang (m) Jumalah Titik
1 Spunpile Dia. 400 30 0.00

H. REKAP VOLUME TOTAL


No Deskripsi Unit Qty
1 Pekerjaan Tanah
3
Excavation m 23.40
3
Backfilling m 9.36
3
Sand Fill m 6.70
3
Lean Concrete m 6.70
2 Pekerjaan Beton
3
Concrete m 19.16
Reinforce kg 5,748.75
3 Pekerjaan Baja
Baja IWF kg 3,800.00