LABOR PRODUCTION TABLE


MANHOURS PER QUANTITY (M.H./UNIT)
ITEM NO. WORK DESCRIPTION M.H./ UNIT
LOW AVERAGE HIGH

A. FORM WORKS INSTALLATION


WALL ON THE GROUND SQ.M. 4.00 2.00 1.60
WALL ABOVER GROUND SQ.M. 4.70 2.35 1.88
BEAMS SQ.M. 6.16 3.08 2.46
COLUMN SQ.M. 4.70 2.35 1.88
SUSPENDED SLAB
0 TO 18' SQ.M. 3.34 1.67 1.34
18' TO 36' UP SQ.M. 6.66 3.33 2.66
ELEVATED AND SHORED SLAB FORMING
FORMING ONLY SQ.M. 17.20 9.00 6.88
FORMING AND SHORING SQ.M. 22.00 11.00 8.80
WOOD WALL AND PARTITION SQ.M. 1.00 0.60 0.40

B. FORMWORKS FABRICATION SQ.M. 2.15 1.08 0.86

C. STRIPPING OF FORMS
WALL ON GROUND SQ.M. 0.50 0.25 0.20
WALL ABOVE 10' SQ.M. 2.58 1.29 1.03
BEAMS SQ.M. 2.06 1.03 0.82
COLUMNS SQ.M. 1.70 0.85 0.68
SUSPENDED SLAB SQ.M.
0 TO 18' SQ.M. 1.67 0.83 0.67
18' TO 36' UP SQ.M. 2.16 1.08 0.86
ELEVATED AND SHORED SLAB FORMING SQ.M.
STRIP OF FORMS SQ.M. 7.00 3.50 2.80
FLOOR SLAB AT GRADE STRIP OF FORMS SQ.M. 5.60 2.80 2.24

D INSTALLION OF CARPENTRY WORKS


PLYWOOD PARTITION PC 2.00 1.00 0.80

T & G FLOORING AND SHORING B.F. 0.29 0.14 0.11

CEILING FRAME B.F. 0.30 0.36 0.29


https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 1/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …
CEILING FRAME B.F. 0.30 0.36 0.29
SIDING FRAME B.F. 0.53 0.27 0.21
FLOORING FRAME B.F. 1.94 0.97 0.77
WOODEN POSS ERECTION B.F. 0.85 0.43 0.34
TRUSS FABRICATION B.F. 0.70 0.35 0.28
TRUSS INSTALLATION B.F. 1.60 0.80 0.64
GIRTS INSTALLTION B.F. 0.43 0.21 0.17
PLATES INSTALLATION B.F. 0.27 0.13 0.11
PURLINS INSTALLATION B.F. 0.53 0.27 0.10
FASCIA BOARD INSTALLATION B.F. 0.91 0.46 0.36
1/4" or 3/4" thk PLYWOOD
CUTTING BY MANUAL PC 2.00 1.00 0.80
ASSEMBLY S.F. 0.83 0.42 0.33
CEILNG:
FRAME INSTALLATION SQ.M. 2.66 1.33 1.06
PLYWOOD INSTALLLATION SQ.M. 2.00 1.00 0.90
CABINET BOARDING B.F. 0.26 0.13 0.10
CABINET FRAMING B.F. 0.36 0.18 0.14
WOOD WALL PARTITION SQ.M. 1.00 0.50 0.40
PANEL WALL SQ.M. 14.00 7.00 5.60
FORMING WEIGHT ANCHOR BOLT SQ.M. 9.00 4.50 3.60
WET FORMING SQ.M. 7.00 3.50 2.80

E. DOORS AND WINDOWS


W-PANEL INSTALLATION PC. 0.80 0.40 0.32
STEEL WINDOWS INSTALLATION PC. 4.00 2.00 1.60
LOUVER WINDOWS INSTALLATION:
FIXED ASBESTOS SQ.M. 9.26 4.63 3.70
FIXED METAL LOUVERS SQ.M. 6.24 3.12 2.50
FIXED GI SHEETS SQ.M. 9.26 4.63 3.70
FIXED GLASS SQ.M. 6.34 3.12 2.50
FIXED WOODEN SQ.M. 6.76 3.38 2.70
ALUMINUM FRAME WINDOWS EACH 20.00 10.00 8.00
SLIDING GLASS DOOR EACH 24.00 12.00 9.60

HOLLOW METAL DOOR EACH 20.00 10.00 8.00


ROLLING DOORS EACH 50.00 25.00 20.00
FIXED WINDOW S.F. 0.63 0.31 0.25
DOOR LOCKSET SET 3.20 1.60 1.28
DOOR JAMB FABRICATION B.F. 0.44 0.22 0.18
DOOR JAMB INSTALLATION B.F. 0.66 0.33 0.26
CYCLONE WIRE INSTALLATION SQ.M. 6.24 3.12 2.50

F. TRADE MASONRY WORKS


GROUTING and TOL PLASTERING SQ.M. 3.34 1.67 1.34
PEBBLE FINISHED SQ.M. 2.86 1.43 1.34
MABLE INSTALLATION SQ.M. 4.00 2.00 1.60
https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 2/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …
MABLE INSTALLATION SQ.M. 4.00 2.00 1.60

1/4" x 2' x 8" RED BRICKS SQ.M. 10.00 5.00 4.00


GLAZED TILES SQ.M. 21.06 10.53 8.42
UNGLAZED TILES SQ.M. 8.70 4.35 3.48
GLAZED TILE WALL SQ.M. 6.00 3.00 2.40
CONC. BLOCK INT. WALL SQ.M. 9.00 4.50 3.60
CONC. BLOCK EXT. WALL SQ.M. 8.00 4.00 3.20
BRICKWORK SQ.M. 1.00 0.50 0.40
PLASTER WALL AND CEILING SQ.M. 6.00 3.00 3.40
HOLLOW TILE WALL SQ.M. 4.00 2.00 1.60
ACOUSTICAL TILE WALL SQ.M. 2.40 1.20 0.96
VINYL FLOOR TILE SQ.M. 3.60 1.80 1.44
UNGLAZED OR MOSAIC FLOOR TILE SQ.M. 17.00 9.50 6.80
LAYING OF CHB & ADOBE SQ.M. 2.28 1.14 0.91
CEMENT FINISH SQ.M. 1.43 0.72 0.57
CONC. HOLLOW BLOCK LAYING:
6" CHB SQ.M. 3.20 1.60 1.28
4" CHB SQ.M. 2.66 1.33 1.06
8" CHB SQ.M. 4.00 2.00 1.60
VIT. TILES FLOOR SQ.M. 10.66 5.33 4.26
VIT. TILES WALL SQ.M. 11.94 5.97 4.78

G. TINSMITHING WORK
CORR GI SHEETS:

Find study resources 숿

LIFTING SQ.M. 2.16 1.08 0.86


INSTALLATION SQ.M. 6.12 3.06 2.45
INSTALLATION OF ASBESTOS ROOFING SHT. 2.00 1.00 0.80
INSTALLATION OF ALUMINUM GI SHEET SHT. 1.60 9.80 0.64
COPPER CLADDING ROOF DECK L.M. 1.01 0.51 0.40
FAB, GI GUTTER SHT. 6.94 3.47 2.78
GI SHEET ROOFING SHT. 1.64 0.82 0.66
FAB OF GI GUTTER L.M. 1.05 0.53 0.42
FAB. GI DOWNSPOUT L.M. 1.94 0.97 1.78
GUTTER CUT & SHAPE L.M. 0.32 0.16 0.13
INST. OF GUTTER L.M. 1.78 9.00 0.71
DOWNSPOUT CUT AND SHAPE L.M. 0.59 0.30 0.24
https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 3/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …
DOWNSPOUT CUT AND SHAPE L.M. 0.59 0.30 0.24

DOWNSPOUT INSTALLATION L.M. 0.27 0.13 0.11


CORR. GI ROOFING

Find study resources 숿

https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 4/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …

Find study resources 숿

You've reached the end of your free preview.


Want to read all 31 pages?

TERM PROFESSOR TAGS


Edit
Fall '15 Randy Policarpio It

https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 5/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …

Twitter Email URL

Literature Study Guides

Learn more about It with Course Hero's FREE study guides and infographics!

Study Guide Infographic

Students who viewed this also studied

Find study resources 숿


1 page o the job safety.docx

Tarlac State University

ENGINEERIN 101

11 pages OFF THE JOB SAFETY.pptx

Tarlac State University

ENGINEERIN 101

1 page 125621689-Broms-method-xls.xls

Tarlac State University

ENGINEERIN 101

https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 6/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …

7 pages Review Progress.xlsx

Tarlac State University

ENGINEERIN 101
notes

10 pages 81714875-Algbra-Trigo-Wkly-Exm-Solution.docx

Tarlac State University

ENGINEERIN 101

8 pages SUDDEN QUIZ-3-


STRUC.pdf

Tarlac State University

ENGINEERIN 101

View more

Find study resources 숿

https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 7/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …

o the job safety.docx

세1

Find study resources 숿

https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 8/9
10/21/2020 151591149­Productivity­Rate­Labor­Eqpt (4).xls ­ LABOR PRODUCTION TABLE ITEM NO A WORK DESCRIPTION M.H UNIT MANHOURS PER …

OFF THE JOB SAFETY.pptx

세 11

125621689-Broms-method-xls.xls

세1

Find study resources 숿

Review Progress.xlsx
https://www.coursehero.com/file/28295513/151591149­Productivity­Rate­Labor­Eqpt­4xls/ 9/9

You might also like