T1 & T2 Concrete Quantities

Item Tickness Length Width Number Total


Slab
Ground Slab 0.5 27.3 8.8 1 120.12
Slab of sump pit Check the Note Below: 5.36
Sump pit Type 1 1 1 1 -1 -1
Sump pit Type 2 0.2 0.6 0.6 -3 -0.216
Total 124.26
Concrete Pads
Pad Type 1 0.15 1.3 0.9 1 0.1755
Pad Type 2 0.15 0.6 0.6 2 0.108
Pad Type 3 0.15 1.2 0.5 4 0.36
Pad Type 4 0.3 0.5 0.5 2 0.15
Pad Type 5 0.15 2.4 1.2 2 0.864
Total 1.66
Walls C
Long Walls 4 27.3 0.4 2 87.36 u
b
Short Walls 4 8.8 0.4 3 42.24 i
Wall Intersection 4 0.4 0.4 6 3.84 c
Total 125.76
Roof M
e
Roof Slab 0.4 27.3 8.8 1 96.096 t
Openning Type 1 0.4 2 2 -1 -1.6 e
Openning Type 2 0.4 1.2 0.6 -2 -0.576 r
Openning Type 3 0.4 0.5 0.5 -1 -0.1
Beam Type 1 0.8 8.8 0.2 1 1.408
Beam Type 2 0.8 4.4 0.2 2 1.408
Beam Type 3 0.8 3.2 0.2 1 0.512
Beam Type 4 0.4 8 0.4 1 1.28
Total 98.43
Blinding Concrete
Blinding Concrete 0.15 27.5 9 1 37.125

Total of C35 350.11

Totalk C25 37.125

NOTE:
Reference to Section D in
SLAB OF SUMP PIT CALCULATION
Reinforcment Drawings
Rectangular Section 1 1.7 1.3 1 2.21
Triangular Section 1 1.7 1 1 0.85
Triangular Section 1 2.3 1 2 2.3
5.36