ESTIMATED MEASUREMENT

NAME OF CONTRACTOR: - M/s RANA CONSTRUCTION CO. NAGPUR


cost of 1rm compound wall
Item No. Description Unit Nos Lgth Bdth Hgt Qty
1 Excavaton cum
excavation of footing 4 1.20 1.20 1.20 6.91

total cum 6.91

2 Centering of PCC sqm


in footing 4 1.10 0.10 0.44

total sqm 0.44

3 PCC 1:5:10 cum


PCC in footing 4 1.10 1.10 0.10 0.48

total cum 0.48

4 Steel below plinth kg


Dia of Weight in kgs.
Sr.No. DESCRIPTION Bar(mm) NOS NO. of Cutting
Bars Length m 8 10
mm mm
footing 10 4 12 1.50 72.00
below plinth column 12 4 4 1.50
rings 8 4 11 0.74 32.74
Plinth Beam 12 3 4 3.37
rings 8 3 18 0.74 41.22

total rm 73.95 72.00

Abstract of weight of steel


Weight of Steel unit wt.
1) 8Ø 73.95 0.395 29.21 Kg
2) 10Ø 72.00 0.617 44.42 Kg
3)12Ø 64.44 0.888 57.22 Kg

total kg 130.86

5 Centering of footing sqm


in footing 4 1.00 0.40 1.60

total sqm 1.60

6 Centering of columns sqm


below plinth columns 16 0.23 0.50 1.84

total sqm 1.84

7 Centering of Beam sqm


beams 6 2.77 0.23 3.82
3 2.77 0.23 1.91

total sqm 5.73

8 RCC 1:1.5:3 cum


RCC of footing 4 1.00 1.00 0.40 1.60
RCC of columns 4 0.23 0.23 0.50 0.11
RCC of beams 3 2.77 0.23 0.23 0.44

total cum 2.15

9 Steel above plinth kg


Dia of Weight in kgs.
Sr.No. DESCRIPTION Bar(mm) NOS NO. of Cutting
Bars Length m 8 10
mm mm
above plinth column 12 4 4 3.00
rings 8 4 21 0.74 62.50

total rm 62.50 0.00

Abstract of weight of steel


Weight of Steel unit wt.
1) 8Ø 62.50 0.395 24.69 Kg
2) 10Ø 0.00 0.617 0.00 Kg
3)12Ø 48.00 0.888 42.62 Kg

total kg 67.31

10 Centering of columns sqm


above plinth columns 16 0.23 3.00 11.04

total sqm 11.04

11 RCC 1:1.5:3 cum


RCC of columns 4 0.23 0.23 3.00 0.63

total cum 0.63

12 brick work 0.23mm cum


above plinth 3 2.77 0.23 3.00 5.73
total cum 5.73

13 plaster 12mm sqm


plaster 12mm 2 9.23 3.23 59.63
top 1 9.23 0.23 2.12

total sqm 61.75

ESTIMATED ABSTRACT
NAME OF CONTRACTOR: - M/s RANA CONSTRUCTION CO. NAGPUR
cost of 1rm compound wall
Item No. Description Unit QTY. Rate Amount
1 Excavation cum 6.91 286.85 1982.71
2 PCC 1:5:10 cum 0.48 6050.65 2928.51
3 steel below plinth kg 130.86 89.65 11731.45
4 centering below plinth sqm 9.61 600.00 5768.34
5 RCC 1:1.5:3 (BP) cum 2.15 8364.20 17944.55
6 steel above plinth kg 67.31 89.65 6034.33
7 centering above plinth sqm 11.04 700.00 7728.00
8 RCC 1:1.5:3 (AP) cum 0.63 10185.00 6465.44
9 Brick work 0.23mm cum 5.73 7000.00 40137.30
10 Plaster 12mm sqm 61.75 350.00 21612.05

total for 9.23 RM 122332.68


for 1 RM 13253.81