You are on page 1of 2

Balancing Tank 80m Diameter With Projection 5.5m Uplift Height(m) 10.

2
S.No Description of Work Nos., Length (m) Breadth (m) Depth (m) Quantity (m3) Shuttering (m2)
I Earth Work Excavation
Step 1 1 10562.96 2.5 26407.4
Step 2 1 9498.5 2.5 23746.25
Step 3 1 8490.56 2.5 21226.4
Step 4 1 7539.14 2.5 18847.85
Step 5 1 6644.24 2.5 16610.6
Step 6 1 6010.15625 2.8 16828.4375
123666.9375
II PCC
100mm Thk., M10 1 6760.2944 0.1 676.02944 29.1392

III RCC confirming Grade M35

Base Slab 2.6m Thk., 1 6731.1866 2.6 17501.08516 755.9864

Wall 0.80mThk., for 3m 1 5226.9696 5024 9 1826.7264 4566.816

Middle Wall 0.45mThk., for 9m 233 13.5 0.8 2517.62688 6294.0672


(Counter Forts)

Middle Wall 0.6mThk., for 9m 1 80 0.8 9 576 1440

Middle Wall 0.45mThk., for 9m 32 13.5 0.8 345.6 864


(Counter Forts)
22767.03844
IV Projection With Plum Concrete
for 2.5m height 1 1606.2042 2.5 4015.5105 1453.82

V Reinforcement 110kg/m3 (approx) 2276.703844 MT

Excavation Quantity 123666.9375 m3


Unit Rate 300 /m3
Cost 37,100,081.25

Reinforced Concrete Quantity 22767.03844 m3


Unit Rate 5500 /m3
Cost 125,218,711.42

Steel Quantity 2276.703844


Unit Rate 3500 /ton
Cost 7,968,463.45

Plain Cement Concrete Quantity 676.02944 m3


Unit Rate 4000 /m3
Cost 2,704,117.76

Plum Concrete Quantity 4015.5105 m3


Unit Rate 3000 /m3
Cost 12,046,531.50

Shuttering 15374.6896 m2
Unit Rate 1800 /m3
Cost 27,674,441.28

Total Cost 212,712,346.66


Balancing Tank 80m Diameter With Projection 3.0 Projection and Anchor Piles
S.No Description of Work Nos., Length (m) Breadth (m) Depth (m) Quantity (m3) Shuttering (m2)
I Earth Work Excavation
Step 1 1 10562.96 2.5 26407.4
Step 2 1 9498.5 2.5 23746.25
Step 3 1 8490.56 2.5 21226.4
Step 4 1 7539.14 2.5 18847.85
Step 5 1 6644.24 2.5 16610.6
Step 6 1 6010.15625 2.8 16828.4375
123666.9375
II PCC
100mm Thk., M10 1 6051.4394 0.1 605.14394 27.5692

III RCC confirming Grade M35

Base Slab 1.0m Thk., 1 6023.9016 1 6023.9016 275.064

Wall 0.80mThk., for 3m 1 5226.9696 5024 9 1826.7264 4566.816

Middle Wall 0.45mThk., for 9m 221 11.25 0.8 1984.9824 4962.456


(Counter Forts)

Middle Wall 0.6mThk., for 9m 1 80 0.8 9 576 1440

Middle Wall 0.45mThk., for 9m 32 11.25 0.8 288 720


(Counter Forts)

IV Tension Piles 950 0.1589625 19 2869.273125

13568.883525

V Reinforcement 110kg/m3 (approx) 1356.8883525 MT

Excavation Quantity 123666.9375 m3


Unit Rate 300 /m3
Cost 37,100,081.25

Reinforced Concrete Quantity 13568.883525 m3


Unit Rate 5500 /m3
Cost 74,628,859.39

Plain Cement Concrete Quantity 605.14394 m3


Unit Rate 4000 /m3
Cost 2,420,575.76

Steel Quantity 1356.8883525


Unit Rate 3500 /ton
Cost 4,749,109.23

Shuttering 11964.336 m2
Unit Rate 1800 /m3
Cost 21,535,804.80

Pile Drving 18050 m


Unit Rate 450 /m
Cost 8,122,500.00
Total Cost 148,556,930.43

You might also like