Baseline Schedulre Rev. 03
Activity ID Activity Name Original Start Finish
Duration 2022 2023 2024 2025 2026
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RUA AL MADINAH MAIN INFRASTRUCTURE PACKAGE REV03 618 23-May-23 31-May-25 31-May-25, RUA AL MADINAH MAIN INFRASTRUCTUR
JAH-Z1-IWU-AWC.105
Pipe Installation alongwith Valves, Fittings & Accessories 30 19-Feb-25 25-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories
JAH-Z1-IWU-AWC.110
Testing 4 27-May-25 31-May-25 Testing
ZONE 2 - FROM STA. 0+500 ~ 0+994 87 28-Nov-24 09-Mar-25 09-Mar-25, ZONE 2 - FROM STA. 0+500 ~ 0+994
CONSTRUCTION 87 28-Nov-24 09-Mar-25 09-Mar-25, CONSTRUCTION
WET & DRY UTILITIES 87 28-Nov-24 09-Mar-25 09-Mar-25, WET & DRY UTILITIES
INSIDE WET CULVERT 87 28-Nov-24 09-Mar-25 09-Mar-25, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 87 28-Nov-24 09-Mar-25 09-Mar-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z2-IWU-AWC.130
Pipe Supports Installation 25 28-Nov-24 26-Dec-24 Pipe Supports Installation
JAH-Z2-IWU-AWC.135
Pipe Installation alongwith Valves, Fittings & Accessories 30 28-Dec-24 30-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories
JAH-Z2-IWU-AWC.140
Testing 4 05-Mar-25 09-Mar-25 Testing
ZONE 3 - FROM STA. 0+994 ~ 1+268 67 28-Aug-24 14-Nov-24 14-Nov-24, ZONE 3 - FROM STA. 0+994 ~ 1+268
CONSTRUCTION 67 28-Aug-24 14-Nov-24 14-Nov-24, CONSTRUCTION
WET & DRY UTILITIES 67 28-Aug-24 14-Nov-24 14-Nov-24, WET & DRY UTILITIES
INSIDE WET CULVERT 67 28-Aug-24 14-Nov-24 14-Nov-24, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 67 28-Aug-24 14-Nov-24 14-Nov-24, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z3-IWU-AWC.115
Pipe Supports Installation 30 28-Aug-24 02-Oct-24 Pipe Supports Installation
JAH-Z3-IWU-AWC.120
Pipe Installation alongwith Valves, Fittings & Accessories 30 03-Oct-24 06-Nov-24 Pipe Installation alongwith Valves, Fittings & Accessories
JAH-Z3-IWU-AWC.125
Testing 7 07-Nov-24 14-Nov-24 Testing
ZONE 4 - FROM STA. 1+268 ~ 1+753 143 28-Sep-24 12-Mar-25 12-Mar-25, ZONE 4 - FROM STA. 1+268 ~ 1+753
CONSTRUCTION 143 28-Sep-24 12-Mar-25 12-Mar-25, CONSTRUCTION
WET & DRY UTILITIES 143 28-Sep-24 12-Mar-25 12-Mar-25, WET & DRY UTILITIES
INSIDE WET CULVERT 143 28-Sep-24 12-Mar-25 12-Mar-25, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 143 28-Sep-24 12-Mar-25 12-Mar-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z4-WU-AWC.145
Pipe Supports Installation 25 28-Sep-24 26-Oct-24 Pipe Supports Installation
JAH-Z4-WU-AWC.150
Pipe Installation alongwith Valves, Fittings & Accessories 30 27-Oct-24 30-Nov-24 Pipe Installation alongwith Valves, Fittings & Accessories
JAH-Z4-WU-AWC.155
Testing 4 09-Mar-25 12-Mar-25 Testing
ZONE 5 - FROM STA. 1+753 ~ 2+157 87 18-Nov-24 26-Feb-25 26-Feb-25, ZONE 5 - FROM STA. 1+753 ~ 2+157
CONSTRUCTION 87 18-Nov-24 26-Feb-25 26-Feb-25, CONSTRUCTION
WET & DRY UTILITIES 87 18-Nov-24 26-Feb-25 26-Feb-25, WET & DRY UTILITIES
INSIDE WET CULVERT 87 18-Nov-24 26-Feb-25 26-Feb-25, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 87 18-Nov-24 26-Feb-25 26-Feb-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z5-WU-AWC.160
Pipe Supports Installation 25 18-Nov-24 16-Dec-24 Pipe Supports Installation
JAH-Z5-WU-AWC.165
Pipe Installation alongwith Valves, Fittings & Accessories 30 17-Dec-24 20-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories
JAH-Z5-WU-AWC.170
Testing 4 23-Feb-25 26-Feb-25 Testing
ZONE 6 - FROM STA. 2+157 ~ 2+826.33 66 30-Nov-24 13-Feb-25 13-Feb-25, ZONE 6 - FROM STA. 2+157 ~ 2+826.33
CONSTRUCTION 66 30-Nov-24 13-Feb-25 13-Feb-25, CONSTRUCTION
WET & DRY UTILITIES 66 30-Nov-24 13-Feb-25 13-Feb-25, WET & DRY UTILITIES
INSIDE WET CULVERT 66 30-Nov-24 13-Feb-25 13-Feb-25, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 66 30-Nov-24 13-Feb-25 13-Feb-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z6-WU-AWC.175
Pipe Supports Installation 30 30-Nov-24 02-Jan-25 Pipe Supports Installation
Actual Work
Remaining Work
1 of 3
Critical Remaining Work
Milestone
RUA AL MADINAH MAIN INFRASTRUCTURE PACKAGE
REV03
Baseline Schedulre Rev. 03
Activity ID Activity Name Original Start Finish
Duration 2022 2023 2024 2025 2026
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-WU-AWC.180
Pipe Installation alongwith Valves, Fittings & Accessories 30 04-Jan-25 06-Feb-25 Pipe Installation alongwith Valves, Fittings & Accessories
JAH-Z6-WU-AWC.185
Testing 6 08-Feb-25 13-Feb-25 Testing
AP-Z7-WU-AWC.195
Pipe Installation alongwith Valves, Fittings & Accessories 30 23-Dec-24 26-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories
AP-Z7-WU-AWC.200
Testing 4 01-Feb-25 04-Feb-25 Testing
KAAR TUNNEL (KING ABDULAZIZ ROAD TUNNEL EAST) 54 15-Feb-25 22-Apr-25 22-Apr-25, KAAR TUNNEL (KING ABDULAZIZ ROAD TUNN
ZONE 8 - FROM STA. 0+015.13 ~ 0+553 54 15-Feb-25 22-Apr-25 22-Apr-25, ZONE 8 - FROM STA. 0+015.13 ~ 0+553
CONSTRUCTION 54 15-Feb-25 22-Apr-25 22-Apr-25, CONSTRUCTION
WET & DRY UTILITIES 54 15-Feb-25 22-Apr-25 22-Apr-25, WET & DRY UTILITIES
INSIDE WET CULVERT 54 15-Feb-25 22-Apr-25 22-Apr-25, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 54 15-Feb-25 22-Apr-25 22-Apr-25, AUTOMATIC WASTE COLLECTION NETWORK
KAAR-Z8-WU-AWC.205
Pipe Supports Installation 20 15-Feb-25 09-Mar-25 Pipe Supports Installation
KAAR-Z8-WU-AWC.210
Pipe Installation alongwith Valves, Fittings & Accessories 30 10-Mar-25 17-Apr-25 Pipe Installation alongwith Valves, Fittings & Accessories
KAAR-Z8-WU-AWC.215
Testing 4 19-Apr-25 22-Apr-25 Testing
KAAR TUNNEL (KING ABDULAZIZ ROAD TUNNEL WEST) 70 25-Oct-23 14-Jan-24 14-Jan-24, KAAR TUNNEL (KING ABDULAZIZ ROAD TUNNEL WEST)
ZONE 9 - STA. 0+000~ 0+461-1 70 25-Oct-23 14-Jan-24 14-Jan-24, ZONE 9 - STA. 0+000~ 0+461-1
CONSTRUCTION 70 25-Oct-23 14-Jan-24 14-Jan-24, CONSTRUCTION
WET & DRY UTILITIES 70 25-Oct-23 14-Jan-24 14-Jan-24, WET & DRY UTILITIES
INSIDE WET CULVERT 70 25-Oct-23 14-Jan-24 14-Jan-24, INSIDE WET CULVERT
AUTOMATIC WASTE COLLECTION NETWORK 70 25-Oct-23 14-Jan-24 14-Jan-24, AUTOMATIC WASTE COLLECTION NETWORK
TU1-Z9-WU-AWC.220
Pipe Supports Installation 30 25-Oct-23 28-Nov-23 Pipe Supports Installation
TU1-Z9-WU-AWC.225
Pipe Installation alongwith Valves, Fittings & Accessories 30 29-Nov-23 02-Jan-24 Pipe Installation alongwith Valves, Fittings & Accessories
TU1-Z9-WU-AWC.230
Testing 10 03-Jan-24 14-Jan-24 Testing
TU2-Z10-WU-AWC.240
Pipe Installation alongwith Valves, Fittings & Accessories 30 11-Sep-24 16-Oct-24 Pipe Installation alongwith Valves, Fittings & Accessories
TU2-Z10-WU-AWC.245
Testing 4 17-Oct-24 21-Oct-24 Testing
TU3-Z11-WU-AWC.255
Pipe Installation alongwith Valves, Fittings & Accessories 30 15-Aug-24 18-Sep-24 Pipe Installation alongwith Valves, Fittings & Accessories
TU3-Z11-WU-AWC.260
Testing 4 23-Oct-24 27-Oct-24 Testing
EXTERNAL SURROUNDING UTILITIES 311 23-May-23 27-May-24 27-May-24, EXTERNAL SURROUNDING UTILITIES
DISTRICT - D9 174 27-Sep-23 20-Apr-24 20-Apr-24, DISTRICT - D9
Actual Work
Remaining Work
2 of 3
Critical Remaining Work
Milestone
RUA AL MADINAH MAIN INFRASTRUCTURE PACKAGE
REV03
Baseline Schedulre Rev. 03
Activity ID Activity Name Original Start Finish
Duration 2022 2023 2024 2025 2026
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
EXTERNAL WET UTILITIES 174 27-Sep-23 20-Apr-24 20-Apr-24, EXTERNAL WET UTILITIES
CONSTRUCTION 174 27-Sep-23 20-Apr-24 20-Apr-24, CONSTRUCTION
AUTOMATED WASTE COLLECTION NETWORK 174 27-Sep-23 20-Apr-24 20-Apr-24, AUTOMATED WASTE COLLECTION NETWORK
EU-D9-WU-CO-AWC.110
Trench Excavation 15 27-Sep-23 14-Oct-23 Trench Excavation
EU-D9-WU-CO-AWC.115
Bedding Works 25 15-Oct-23 12-Nov-23 Bedding Works
EU-D9-WU-CO-AWC.120
Pipe Laying with Valves & Fittings 30 13-Nov-23 17-Dec-23 Pipe Laying with Valves & Fittings
EU-D9-WU-CO-AWC.125
Backfilling Works 10 01-Apr-24 15-Apr-24 Backfilling Works
EU-D9-WU-CO-AWC.130
Leakage Test 5 26-Feb-24 02-Mar-24 Leakage Test
EU-D9-WU-CO-AWC.135
Hydrotest 4 16-Apr-24 20-Apr-24 Hydrotest
EU-D9-WU-CO-AWC.140
Precast Manhole with Backdrop 30 22-Jan-24 25-Feb-24 Precast Manhole with Backdrop
EU-D9-WU-CO-AWC.145
House Conncetion Chamber 30 26-Feb-24 31-Mar-24 House Conncetion Chamber
EU-D9-WU-CO-AWC.150
Precast Manholes 30 18-Dec-23 21-Jan-24 Precast Manholes
EU-D10-WU-CO-AWC.117
Bedding Works 25 10-Jun-23 11-Jul-23 Bedding Works
EU-D10-WU-CO-AWC.122
Pipe Laying with Valves & Fittings 30 13-Nov-23 17-Dec-23 Pipe Laying with Valves & Fittings
EU-D10-WU-CO-AWC.127
Backfilling Works 10 01-Apr-24 15-Apr-24 Backfilling Works
EU-D10-WU-CO-AWC.132
Leakage Test 5 26-Feb-24 02-Mar-24 Leakage Test
EU-D10-WU-CO-AWC.137
Hydrotest 4 16-Apr-24 20-Apr-24 Hydrotest
EU-D10-WU-CO-AWC.142
Precast Manhole with Backdrop 30 22-Jan-24 25-Feb-24 Precast Manhole with Backdrop
EU-D10-WU-CO-AWC.147
House Conncetion Chamber 30 26-Feb-24 31-Mar-24 House Conncetion Chamber
EU-D10-WU-CO-AWC.152
Precast Manholes 30 18-Dec-23 21-Jan-24 Precast Manholes
NORTH SIDE AUTOMATIC WASTE COLLECTION SYSTEM(S1&S2&S3&S4&S5&S7$S8) 279 03-Jul-23 27-May-24 27-May-24, NORTH SIDE AUTOMATIC WASTE COLLECTION SYSTEM(S1&S2&S3&S4&S5&S7$S
CONSTRUCTION 279 03-Jul-23 27-May-24 27-May-24, CONSTRUCTION
EU-WU-CO-AWCS112
Trench Excavation 15 03-Jul-23 19-Jul-23 Trench Excavation
EU-WU-CO-AWCS117
Bedding Works 25 20-Jul-23 17-Aug-23 Bedding Works
EU-WU-CO-AWCS122
Pipe Laying with Valves & Fittings 30 20-Dec-23 23-Jan-24 Pipe Laying with Valves & Fittings
EU-WU-CO-AWCS127
Backfilling Works 10 12-May-24 22-May-24 Backfilling Works
EU-WU-CO-AWCS132
Leakage Test 5 03-Apr-24 08-Apr-24 Leakage Test
EU-WU-CO-AWCS137
Hydrotest 4 23-May-24 27-May-24 Hydrotest
EU-WU-CO-AWCS142
Precast Manhole with Backdrop 30 28-Feb-24 02-Apr-24 Precast Manhole with Backdrop
EU-WU-CO-AWCS147
House Conncetion Chamber 30 03-Apr-24 11-May-24 House Conncetion Chamber
EU-WU-CO-AWCS152
Precast Manholes 30 24-Jan-24 27-Feb-24 Precast Manholes
Actual Work
Remaining Work
3 of 3
Critical Remaining Work
Milestone