Tuesday, 16 January 2024 Daily Productivity Report

Average Completed Planned Completion Date Completion date


Total Spot %
No Activity Unit
Quantity Productivity
weekly Quantity Finishing (Spot ( Average Status
Complete
Productivity (Till Today) Date Productivity) productivity)

1 Excavation m3 4,608,951 7,780 8,205 3,608,471 14‐Apr‐24 23‐May‐24 16‐May‐24 in progress 78.29%

2 Blasting m3 450,800 159,160 14‐Mar‐24 in progress 35.31%

Soil improvement (CMC+Soil


3 m2 149,710 84 238 83,175 22‐Apr‐24 18‐Mar‐26 21‐Oct‐24 in progress 55.56%
Replacment)

4 Shoring m2 20,565 102 68 13,660 14‐Apr‐24 23‐Mar‐24 26‐Apr‐24 in progress 66.42%

5 Backfilling m3 4,200,000 ‐ 23‐Jan‐25 Not Start 0.00%

6 Concrete m3 1,027,823 184 670 101,998 01‐Oct‐25 25‐Oct‐37 28‐Oct‐27 in progress 9.92%

7 Rebar Ton 181,626 29 105 20,357 07‐Sep‐25 14‐Jan‐39 04‐Apr‐28 in progress 11.21%

8 Crashers m3 1,499,980 300 2,100 362,300 23‐Jan‐25 04‐Jun‐34 10‐Jul‐25 in progress 24.15%

9 Disposal Material m3 2,844,269 14,360 14,667 2,215,294 14‐Apr‐24 28‐Feb‐24 27‐Feb‐24 in progress 77.89%