Sewerage

Sewerline
Length
600mm RCP = 330.00
plus 10% = 363.00
= 370.00

Length
450mm RCP = 720.00
plus 10% = 792.00
= 800.00

450mm DI = 390.00 m
plus10% = 429.00 m
= 430.00 m

Excavation(sewerline)
average depth = 3m
width = 3.2 m
length = 1,440.00 m
= 13,824.00 m3
plus 20% = 16,588.80 m3
16,600.00 m3

Backfill (Sewerline)
average depth = 1.85 m
width = 3.2 m
length = 1,440.00 m
= 8,524.80 m3
plus 15% = 9,803.52 m3
9,900.00 m3

Sand Compacted
average depth = 0.85 m
width = 1.1 m
area = 0.493213533088935 m2
length = 1,440.00 m
= 710.23 m3
plus 15% = 816.76 m3
900.00 m3

Concrete Slab (Sewerline)


Slab
depth = 0.30 m
width = 1.20 m
length = 1,440.00 m
= 518.40 m3
plus 20% = 622.08 m3
700.00 m3
Surround
depth = 0.75 m
width = 1.20 m
void = 0.28 m2
length = 1,440.00 m
= 888.85 m3
plus 20% = 1,066.62 m3
1,100.00 m3

Total Concrete Volume = 1,800.00 m3


Lean Concrete(Sewerline)
width = 1.05 m
length = 1,440.00 m
= 1,512.00 m2
plus 20% = 1,814.40 m2
1,900.00 m2

Formwork
Slab
depth = 0.30 m
width = 1.20 m
length = 1,440.00 m
area = 864.72 m2
plus 20% = 1,037.66 m2
1,100.00 m2
Surround
depth = 0.75 m
width = 1.20 m
length = 1,440.00 m
area = 2,161.80 m2
plus 20% = 2,594.16 m2
2,600.00 m2

Total Formwork Area = 3,700.00

Reinforcement (Sewerline)
T 12
slab width = 1.05 m
slab length = 1100 m
spacing x = 0.15 m
spacing y = 0.15 m
nos x = 7
nos y = 7333.33333333333
length x = 7707 m
length y = 15033.3333333333 m
bar size = 12 m
nos = 7340.33333333333
total length = 22740.3333333333 m
top&bottom = 45480.6666666667 m
weight = 40378.3764120315 kg
40.3783764120315 tonne
plus 20% = 48.45 tonne

Excavation (Manhole)
average depth = 3m
width = 4.4 m
length = 4.40 m
= 58.08 m3
plus 20% = 69.70 m3
Concrete Slab (Manhole)
depth = 0.40 m
width = 2.40 m
length = 2.40 m
= 2.30 m3
plus 20% = 2.76 m3

Concrete Encase (Manhole)


depth = 2.60 m
width = 2.40 m
length = 2.40 m
thickness = 0.15 m
= 0.77 m3
plus 20% = 0.93 m3

Total Concrete Volume = 3.69

Lean Concrete(Manhole)
width = 2.40 m
length = 2.40 m
= 5.76 m2
plus 20% = 6.91 m2
7.00 m2

Reinforcement (Manhole)
T 12
slab width = 2.4 m
slab length = 2.4 m
spacing x = 0.15 m
spacing y = 0.15 m
nos x = 16
nos y = 16
length x = 54.4 m
length y = 54.4 m
bar size = 12 m
nos = 32
total length = 108.8 m
top&bottom = 217.6 m
weight = 193.188344657614 kg
0.193188344657614 tonne
plus 20% = 0.23 tonne

Total Length = 1,170.00