TP3 FORTNIGHTLY

MEETING NO.28
JBS ENGINEERING SDN BHD
PROGRESS AS OF 12 September 2020
(Based on Approved EOT No. 02)
Progress as of 12 September 2020
(Based on EOT No. 2)
New Date for Completion : 30st January 2021

PREVIOUS CURRENT
12th July 2020 12nd September 2020
Planned Actual Variance Planned Actual Variance
Ahead/Delay Ahead/Delay
Item Item
% % % (Days) % % % (Days)

Overall Overall
100.00 57.26 -42.74 -97 100.00 57.26 -42.74 -142
progress progress
Physical Physical
100.00 56.93 -43.07 -96 100.00 56.93 -43.07 -135
Progress Progress
Financial Financial
100.00 35.51 -64.49 -131 100.00 35.51 -64.49 -131
Progress Progress
Progress Progress
(Supervision 100.00 25.45 -74.55 (Supervision 100.00 28.31 -71.69
Area) Area)

Progress (Toll Progress (Toll


100.00 0.25 -99.75 100.00 0.25 -99.75
Plaza Area) Plaza Area)

Progress Progress
(Provisional 100.00 37.80 -62.20 (Provisional 100.00 42.18 -57.82
Sums) Sums)
DAMANSARA – SHAH ALAM ELEVATED EXPRESSWAY
(DASH)
– TP 3: OVERALL S-CURVE

Date_1 Ju1-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Jan-20 16 Feb 20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20

Plan 0.22% 0.57% 0.83% 1.12% 1.41% 4.91% 5.59% 8.94% 13.36% 17.82% 19.39% 20.44% 23.26% 28.22% 32.12% 35.14% 37.68% 39.23% 55.45% 59.93% 67.35% 71.73% 85.40% 93.12% 100.00% 100.00% 100.00%

Actual 0.00% 0.57% 0.83% 1.12% 1.41% 4.91% 5.59% 8.94% 13.36% 17.82% 19.39% 20.44% 23.12% 28.22% 32.12% 35.14% 37.68% 39.22% 53.93% 55.63% 57.26% 57.26% 57.26% 57.26% 57.26% 57.26% 57.26%
DAMANSARA – SHAH ALAM ELEVATED EXPRESSWAY (DASH) –
TP 3
PHYSICAL S-CURVE

Date_1 Ju1-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Jan-20 16 Feb 20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20

Plan 0.00% 0.00% 0.27% 0.29% 0.46% 4.73% 5.53% 8.49% 13.76% 18.97% 20.70% 21.66% 23.85% 27.11% 30.12% 34.85% 35.85% 36.12% 55.47% 57.13% 65.74% 74.12% 87.65% 93.45% 100.00% 100.00% 100.00%

Actual 0.00% 0.00% 0.27% 0.29% 0.46% 4.73% 5.53% 8.49% 13.76% 18.97% 20.70% 21.66% 23.85% 27.11% 30.12% 34.85% 35.85% 36.12% 52.75% 54.66% 56.93% 56.93% 56.93% 56.93% 56.93% 56.93% 56.93%
Forecast Planning 13 - 27 September 2020

Location Task Forecast Planning

Men Power Date Start Date End

OSD Slab Prep


RC Slab
OSD 6 Paxs 13 September 2020 17 October 2020
RC Wall
RC Slab Cover
Plastering
13 September 2020 27 September 2020
Internal
Supervision
10 Paxs *Due to P.E design for
Building Plastering 21 September 2020
Submission
External

Plastering (Skim
Guard House 3 Paxs 13 September 2020 20 September 2020
Coat)
Plastering (Skim
Refuse Chamber 2 Paxs 13 September 2020 16 September 2020
Coat)
External
TNB Sub Station Plastering Skim 4 Paxs 13 September 2020 22 September 2020
Coat

TOTAL WORKERS 25 Paxs


Planning Activities
TRADE /
NO LOCATION DESCRIPTION MITIGATION
ELEMENT
1. Structural Elements • OSD • To Be complete on 17 October 2020- • Special gang allocated
At present (11 September 2020) Base
Slab Preparation In progress

2. Architectural Elements • Supervision, Guard • Rectification for Plastering Guard • Numbers of Workers = 25
House & Refuse House-in progress
Chamber • Internal Plastering for Supervision
Building-In Progress
• Extenal Plastering For Refuse
Chamber
3. Mechanical & Electrical • Supervision, TNB Sub • Copper Tape at deck Installed • Men Power 7 and to increase
Service Station, Guard House • Pipre Sleve At Deck Slab INstalled from time to time to avoid any
further delay

4. Structure Steel Works Structure Steel Works • appointing Sub contractor in progress • Before 17 September 2020 to
Staff Passage Staff Passage Award
Protected Walkway Protected Walkway
Overall Layout

• Toll Canopy

• Super Vision Building


• Refuse Chamber
• Guard House
• TNB Substation
• OSD
REFUSE CHAMBER
Progress Work On Site- Structure
SuperVision Building •-RC Structure-100%
Architecture
•Brickwall And Plastering-100%
•Floor Rendering 10%
SUPERVISION
BUILDING

Architecture
•Internal Wall
Plastering GF-70%
Infrawork
•Door Frame-90%
•Setting Out For Sewerage,
•Window-Sub Frame-
Waterac-In progress
90%
•BrickWall - 95%
•Parapet Wall - 85%

M&E
•Conduit- 100%
•Internal Cable -
TNB
100%(GF) SUBSTATION
•Structure-100%

Archietecture
GUARD HOUSE •-Internal and
External Plastering-
Structure 100%
•RC Structure-100% •-Door Panel-90 %
•-Floor Rendering-
Architecture 10%
•Brickwall And
Plastering-100% M&E
•Window-SubFrame- •Copper Tape
100% Installed
OSD
•Floor Rendering-
10%
•-Steel Bar For Base Slab
•Setting Out For OSD
Completed
Progress Work On Site-Toll Plaza

Structure
M&E
-Rebar for Toll Island
-Copper Tape Installed Installed
-Pipe Sleeve Installed
Financial Progress
MONTH CLAIM SUBMITTED CLAIM CERTIFIED PAYMENT RECEIVED

  Claim Amount Certified Accum. Amount Accum.


(RM) Amount (RM) Amount (RM) Received (RM) Amount (RM)
Nov-18 182,508.21 150,600.00 150,600.00 150,600.00 150,600.00
Dec-18 215,027.47 135,200.00 285,800.00 135,200.00 285,800.00
Jan-19 177,711.63 96,200.00 382,000.00 96,200.00 382,000.00
Feb-19 170,178.06 170,700.00 552,700.00 170,700.00 552,700.00
Mar-19 639,900.00 607,500.00 1,160,200.00 607,500.00 1,160,200.00
Apr-19 550,100.00 553,100.00 1,173,300.00 553,100.00 1,713,300.00
May-19 531,000.00 416,400.00 2,129,700.00 416,400.00 2,129,700.00
Jun-19 158,100.00 39,000.00 2,168,700.00 39,000.00 2,168,700.00
Jul-19 396,500.00 191,900.00 2,360,600.00 191,900.00 2,360,600.00
Aug-19 483,500.00 213,265.64 2,573,865.64 213,200.00 2,534,800.00
Sep-19 476,200.00 171,157.89 2,745,023.53 171,100.00 2,705,900.00
Oct-19 380,300.00 199,300.00 2,905,200.00 199,300.00 2,905,200.00
Nov-19 0 0 2,905,200.00 0 2,905,200.00
Dec-19 81,100.00 81,100.00 2,986,300.00 81,100.00 2,986,300.00
Jan-20 218,600.00 218,600.00 3,204,900.00 218,600.00 3,204,900.00
Feb-20 0 0 3,204,900.00 0 3,204,900.00
Mar-20 0 0 3,204,900.00 0 3,204,900.00
Apr-20 0 0 3,204,900.00 0 3,204,900.00
May-20 0 0 3,204,900.00 0 3,204,900.00
June-20 0 0 3,204,900.00 0 3,204,900.00
DAMANSARA – SHAH ALAM ELEVATED EXPRESSWAY (DASH)
– TP 3
FINANCIAL S-CURVE
Manpower
Designation/Date(August) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Project Director 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Project Manager 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Construction Manager - - - - - -
Contract Manager - - - - - -
HSSE Manager - - - - - -
QAQC Manager - - - - - -
Site Manager - - - - - -
Project Scheduler - - - - - -
Assistant Planner - - - - - -
Technical Engineer - - - - - -
QAQC Engineer - - - - - -
Site Engineer 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Site Supervisor 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Document Controller - - - - - -
Clerk 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Liaison Officer - - - - - -
Camp Warden - - - - - -
Assistant Camp Warden - - - - - -
HSSE Supervisor - - - - - -
Environmental Engineer - - - - - -
Medical Assistant - - - - - -
Quantity Surveyor 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 2 3 4 5 6 - -
Lab Technician - - - - - -
Site Engineer 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Land Surveyor - - - - - -
Draughtsman - - - - - -
Environmental Supervisor - - - - - -
Construction Supervisor - - - - - -
Inventory Assistant - - - - - -
Purchasing Clerk - - - - - -
M&E Coordinator 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Gang Pusher - - - - - -
Mechanic - - - - - -
Chainman - - - - - -
HR And Admin Officer - - - - - -
Chief Mechanic - - - - - -
General Workers 7 - - - - 4 5 6 - 6 5 5 6 - - - 4 5 5 4 5 6 - 8 7 9 7 6 5 - -
Machine Operator 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - -
Electrical Team 4 - 3 2 4 1 4 4 - 1 4 2 4 0 2 - 2 2 4 3 1 4 - 1 0 2 0 4 4 - -
Lorry Driver - - - - - -
Welder - - - - - -
Chief Welder - - - - - -
Machinery
  August 2020
 
  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Plant &
Machinery

Air Compressor
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Backhoe
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Excavator
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Baby Roller
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Concrete Mixer
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Water Pump
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Crawler Crane
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mobile Crane
(<25T) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mobile Tower
Light 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Bar Bending
Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Bar Cutting
Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Generator Set
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Lorry 23 Tonne
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Flat Compactor
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Vibratory Roller
Compactor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Rotary Boring
Machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Concrete Pump
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Jack In Pile
Machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Piling Rig
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location TNB SubStation Location TNB SubStation

Description Plastering TNB Sub Trenches Description Plastering TNB Sub Trenches

Date 7.9.2020 Date 7.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location OSD Location OSD

Description OSD Slab Preparation Description OSD Slab Preparation

Date 12.9.2020 Date 12.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location External Works Location External Works

Description Bar Bending For Toll Plaza Description Bar Bending For Toll Plaza

Date 5.9.2020 Date 5.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location Deck Slab Location Deck Slab

Description Re Bar installation Description Re Bar Installation

Date 5.9.2020 Date 8.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location Deck Slab Location Deck Slab

Description Re Bar installation Description Re Bar Installation

Date 10.9.2020 Date 10.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location Guard House Location Guard House

Description Rectification To Install Corner Bead Description Install Corner Bead

Date 9.9.2020 Date 9.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location Toll Plaza Location Toll Plaza

Description Installation Of Pipe Sleeve Description Copper Tape Installation

Date 14.8.2020 Date 1.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location Supervision Building Location External Utilities

Description Clearing water stagnent Description Repair Hoarding

Date 10.9.2020 Date 9.9.2020


PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020

Location Supervision Building Location Refuse Chamber

Description Continuity Test Description Plastering work

Date 14.8.2020 Date 28.7.2020


QAQC – Non Conformance Report (NCR)

•Non-Conformance Report (NCR) - INTERNAL

CUMULATIVE
This Month (Feb 2020 only)
(July 2018 – 12th June 2020)

Received Closed Received Closed Pending % Close

0 0 16 16 0 100%

•Non-Conformance Report (NCR) - EXTERNAL

This Month (Jan 2020 CUMULATIVE


only) (July 2018 – 12th June 2020)

Closed /
Raised Closed Raised Cancel
Pending % Close

0 0 1 1 0 100%
QAQC – Method of Statements

This Month CUMULATIVE


(September 2020 (July 2018 – 12thSeptember
only) 2020) Status Status Status With-
Submission
A B C drawn
Raised Reply Raised Reply Pending

Method
Statements
0 0 61 59 2 34 15 8 2

Notes:
1.Status A : Approved
2.Status B : Approved with Conditions
3.Status C : Rejected
4.Status D : Withdraw
QAQC – Request for Information (RFIn)

This Month (June 2020 CUMULATIVE


only) (July 2018 – 12th September 2020)
Submission
Raised Reply Raised Reply Pending

Request for
Information 0 0 82 82 0
(RFIn)
QAQC – Request for Information (RFI)

This Month (June 2020 CUMULATIVE


only) (July 2018 – 13th September 2020)
Submission
Raised Reply Raised Reply Pending

Request for
1 0 777 741 36
Inspection
QAQC – Material Submission

This Month CUMULATIVE


(September (July 2018 – 12th
2020 only) September 2020) Status Status Status Status With-
Submission
A B C D drawn
Raised Reply Raised Replied Pending

Material
0 0 299 289 10 198 42 27 10 22
Submission

Notes:
1.Status A : Approved
2.Status B : Approved with Conditions
3.Status C : Revise and resubmit
4.Status D : Rejected
Highlighted Issue
NO ISSUE DESCRIPTION STATUS AND MITIGATION
1 Toll Canopy • Deck slab handing over • Construction of Toll Canopy and
planned on 25th May 2019 is associated works will required six (6)
•Deck slab P107 –
due. Expected delay in Toll months upon site possession (deck
P111 access &
Canopy construction. slab).
egress
• New date given on 31st
• Method of mobilization of plant and
January 2019.
materials shall be determined from
• Access and egress for how the deck slab handed over.
delivery and installation of toll
canopy structure and • Access and egress needed for plant
associated works still pending mobilization, material delivery and
work space for installation.
• Latest infro from CRE, MRCB
will handing over the deck • By handing over only 2 bay will create
slab ( 2 bay only P110 to access issues, which are 100m away
P108) on 31 July 2020. from our ROW.

2 Protected Walkway
•Deck slab P105 –
P109 access & • Delivery date for deck slab
• Date confirmation (Pending)
egress handing over
Highlighted Issue
NO ISSUE DESCRIPTION STATUS AND MITIGATION
3 Staff Passage
•Deck slab P105 – • Delivery date for deck slab
• Date confirmation (Pending)
P106 access & handing over
egress

4 TCS & TCSS


• Shop drawings are essential
•Service Duct for interfacing works
(Trunking) for TCS &
TCSS • Service duct (trunking) from • TBA
Supervision Building to Toll
Plaza area is not in our
Contract.

5 PROJECT
BOUNDARY
(SALVIA
• Salvia existing perimeter
APARTMENT SIDE)
fencing & sewerage line are • To confirm on new project fencing line
•Boundary Line over our project boundary.
Highlighted Issue
NO ISSUE DESCRIPTION STATUS AND MITIGATION
6 Extension of Time
• Already submitted letter of intention to
•EOT • Clause 43.1 (h) – Delay by apply for 2nd EOT
other parties engaged by the
Employer • Application for new date for completion
is expected to be in 31st May 2020.

7 Relocation of
Existing Fiber Optic • Third party works to relocate
• Need instruction from consultant/Client
•Sub-Cont request existing fibre optic cable, work
beyond contract scope of
for LoA
works

8 ON SITE • Ned to demolish the existing rubble


• OSD location need to shift
DETENTION POND wall and concrete base and re install re
towards the main road,
otherwise OSD wall will be on bars.
the road blocking ramp at
TNB Substation
Highlighted Issue (new)
NO ISSUE DESCRIPTION STATUS AND MITIGATION
8 Mitigation Plan To set new target date for overall • We are still working on our mitigation
completion for each building plan due to uncertainty on the day to
To provide milestone for target start physical works.
handing over to TCS & TNB

9 Work during CMCO Have to complies to CIDB & MOH • JBS had prepared SOP for Office Staff
SOP. as well as Site Workers.
• Upon returning from Raya holiday,
some physical works activities will take
place at site.
• Currently we are arranging workers for
COVID 19 test.

All workers must go for COVID- • Sub-contractor asking who bear the
19 test. cost?
END OF SLIDE