MEETING NO.28
JBS ENGINEERING SDN BHD
PROGRESS AS OF 12 September 2020
(Based on Approved EOT No. 02)
Progress as of 12 September 2020
(Based on EOT No. 2)
New Date for Completion : 30st January 2021
PREVIOUS CURRENT
12th July 2020 12nd September 2020
Planned Actual Variance Planned Actual Variance
Ahead/Delay Ahead/Delay
Item Item
% % % (Days) % % % (Days)
Overall Overall
100.00 57.26 -42.74 -97 100.00 57.26 -42.74 -142
progress progress
Physical Physical
100.00 56.93 -43.07 -96 100.00 56.93 -43.07 -135
Progress Progress
Financial Financial
100.00 35.51 -64.49 -131 100.00 35.51 -64.49 -131
Progress Progress
Progress Progress
(Supervision 100.00 25.45 -74.55 (Supervision 100.00 28.31 -71.69
Area) Area)
Progress Progress
(Provisional 100.00 37.80 -62.20 (Provisional 100.00 42.18 -57.82
Sums) Sums)
DAMANSARA – SHAH ALAM ELEVATED EXPRESSWAY
(DASH)
– TP 3: OVERALL S-CURVE
Date_1 Ju1-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Jan-20 16 Feb 20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20
Plan 0.22% 0.57% 0.83% 1.12% 1.41% 4.91% 5.59% 8.94% 13.36% 17.82% 19.39% 20.44% 23.26% 28.22% 32.12% 35.14% 37.68% 39.23% 55.45% 59.93% 67.35% 71.73% 85.40% 93.12% 100.00% 100.00% 100.00%
Actual 0.00% 0.57% 0.83% 1.12% 1.41% 4.91% 5.59% 8.94% 13.36% 17.82% 19.39% 20.44% 23.12% 28.22% 32.12% 35.14% 37.68% 39.22% 53.93% 55.63% 57.26% 57.26% 57.26% 57.26% 57.26% 57.26% 57.26%
DAMANSARA – SHAH ALAM ELEVATED EXPRESSWAY (DASH) –
TP 3
PHYSICAL S-CURVE
Date_1 Ju1-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Jan-20 16 Feb 20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20
Plan 0.00% 0.00% 0.27% 0.29% 0.46% 4.73% 5.53% 8.49% 13.76% 18.97% 20.70% 21.66% 23.85% 27.11% 30.12% 34.85% 35.85% 36.12% 55.47% 57.13% 65.74% 74.12% 87.65% 93.45% 100.00% 100.00% 100.00%
Actual 0.00% 0.00% 0.27% 0.29% 0.46% 4.73% 5.53% 8.49% 13.76% 18.97% 20.70% 21.66% 23.85% 27.11% 30.12% 34.85% 35.85% 36.12% 52.75% 54.66% 56.93% 56.93% 56.93% 56.93% 56.93% 56.93% 56.93%
Forecast Planning 13 - 27 September 2020
Plastering (Skim
Guard House 3 Paxs 13 September 2020 20 September 2020
Coat)
Plastering (Skim
Refuse Chamber 2 Paxs 13 September 2020 16 September 2020
Coat)
External
TNB Sub Station Plastering Skim 4 Paxs 13 September 2020 22 September 2020
Coat
2. Architectural Elements • Supervision, Guard • Rectification for Plastering Guard • Numbers of Workers = 25
House & Refuse House-in progress
Chamber • Internal Plastering for Supervision
Building-In Progress
• Extenal Plastering For Refuse
Chamber
3. Mechanical & Electrical • Supervision, TNB Sub • Copper Tape at deck Installed • Men Power 7 and to increase
Service Station, Guard House • Pipre Sleve At Deck Slab INstalled from time to time to avoid any
further delay
4. Structure Steel Works Structure Steel Works • appointing Sub contractor in progress • Before 17 September 2020 to
Staff Passage Staff Passage Award
Protected Walkway Protected Walkway
Overall Layout
• Toll Canopy
Architecture
•Internal Wall
Plastering GF-70%
Infrawork
•Door Frame-90%
•Setting Out For Sewerage,
•Window-Sub Frame-
Waterac-In progress
90%
•BrickWall - 95%
•Parapet Wall - 85%
M&E
•Conduit- 100%
•Internal Cable -
TNB
100%(GF) SUBSTATION
•Structure-100%
Archietecture
GUARD HOUSE •-Internal and
External Plastering-
Structure 100%
•RC Structure-100% •-Door Panel-90 %
•-Floor Rendering-
Architecture 10%
•Brickwall And
Plastering-100% M&E
•Window-SubFrame- •Copper Tape
100% Installed
OSD
•Floor Rendering-
10%
•-Steel Bar For Base Slab
•Setting Out For OSD
Completed
Progress Work On Site-Toll Plaza
Structure
M&E
-Rebar for Toll Island
-Copper Tape Installed Installed
-Pipe Sleeve Installed
Financial Progress
MONTH CLAIM SUBMITTED CLAIM CERTIFIED PAYMENT RECEIVED
Air Compressor
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Backhoe
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Excavator
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Baby Roller
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Concrete Mixer
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Water Pump
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Crawler Crane
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mobile Crane
(<25T) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Mobile Tower
Light 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Bar Bending
Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Bar Cutting
Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Generator Set
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Lorry 23 Tonne
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Flat Compactor
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Vibratory Roller
Compactor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Rotary Boring
Machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Concrete Pump
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Jack In Pile
Machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Piling Rig
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PROJECT CURRENT ACTIVITIES PHOTOS
TP3 – JBS ENGINEERING SDN BHD
Progress 11 September 2020
Description Plastering TNB Sub Trenches Description Plastering TNB Sub Trenches
Description Bar Bending For Toll Plaza Description Bar Bending For Toll Plaza
CUMULATIVE
This Month (Feb 2020 only)
(July 2018 – 12th June 2020)
0 0 16 16 0 100%
Closed /
Raised Closed Raised Cancel
Pending % Close
0 0 1 1 0 100%
QAQC – Method of Statements
Method
Statements
0 0 61 59 2 34 15 8 2
Notes:
1.Status A : Approved
2.Status B : Approved with Conditions
3.Status C : Rejected
4.Status D : Withdraw
QAQC – Request for Information (RFIn)
Request for
Information 0 0 82 82 0
(RFIn)
QAQC – Request for Information (RFI)
Request for
1 0 777 741 36
Inspection
QAQC – Material Submission
Material
0 0 299 289 10 198 42 27 10 22
Submission
Notes:
1.Status A : Approved
2.Status B : Approved with Conditions
3.Status C : Revise and resubmit
4.Status D : Rejected
Highlighted Issue
NO ISSUE DESCRIPTION STATUS AND MITIGATION
1 Toll Canopy • Deck slab handing over • Construction of Toll Canopy and
planned on 25th May 2019 is associated works will required six (6)
•Deck slab P107 –
due. Expected delay in Toll months upon site possession (deck
P111 access &
Canopy construction. slab).
egress
• New date given on 31st
• Method of mobilization of plant and
January 2019.
materials shall be determined from
• Access and egress for how the deck slab handed over.
delivery and installation of toll
canopy structure and • Access and egress needed for plant
associated works still pending mobilization, material delivery and
work space for installation.
• Latest infro from CRE, MRCB
will handing over the deck • By handing over only 2 bay will create
slab ( 2 bay only P110 to access issues, which are 100m away
P108) on 31 July 2020. from our ROW.
2 Protected Walkway
•Deck slab P105 –
P109 access & • Delivery date for deck slab
• Date confirmation (Pending)
egress handing over
Highlighted Issue
NO ISSUE DESCRIPTION STATUS AND MITIGATION
3 Staff Passage
•Deck slab P105 – • Delivery date for deck slab
• Date confirmation (Pending)
P106 access & handing over
egress
5 PROJECT
BOUNDARY
(SALVIA
• Salvia existing perimeter
APARTMENT SIDE)
fencing & sewerage line are • To confirm on new project fencing line
•Boundary Line over our project boundary.
Highlighted Issue
NO ISSUE DESCRIPTION STATUS AND MITIGATION
6 Extension of Time
• Already submitted letter of intention to
•EOT • Clause 43.1 (h) – Delay by apply for 2nd EOT
other parties engaged by the
Employer • Application for new date for completion
is expected to be in 31st May 2020.
7 Relocation of
Existing Fiber Optic • Third party works to relocate
• Need instruction from consultant/Client
•Sub-Cont request existing fibre optic cable, work
beyond contract scope of
for LoA
works
9 Work during CMCO Have to complies to CIDB & MOH • JBS had prepared SOP for Office Staff
SOP. as well as Site Workers.
• Upon returning from Raya holiday,
some physical works activities will take
place at site.
• Currently we are arranging workers for
COVID 19 test.
All workers must go for COVID- • Sub-contractor asking who bear the
19 test. cost?
END OF SLIDE