Project Name : JAWA-1 Combined Cycle Gas Turbine Power Plant (1760MW

Company : PT. CIGADING HABEAM CENTRE


Work Classification : Erection And Contruction Steel Structure

Today: 14 December 2019 (Sat


Area Ac
CHC Site Office
and Lay Down CHC Prepare Material And Equipment For Erection Tb1&Tb2
Continue Bolt tightening
Load Unload Material Tb1&2
Prepare Erection
Inspection Qc Material Unload

Turbin Building #1 Load Unload Material


Continue erection and Bolting tightening
Scaffold Flatform Working , Touchup Paint ,
Inspection Material
Scaffold Installation
continue Alignment position
continue 4D-4E LINE CUPPING AND Padding inspection an
Crane 180t mobilize from tb2 to tb1
Turbin Building #2 Continue Bolt Tightening Line and check bolt for inspection
Load Unload Material
Scaffold Installation acsses
Material Inspection
Touch Up Paint
continue erection
Continue Check Verticality ,and girder

Description
Erection TB2 SB12-15
HBR56S-9
HBR56S-113
SB13-125
HBR56S-80
HBR56S-105
HBR56S-43
SC13-12
VBR44-36

Erection TB1
Materials
Item

SEE packing list, 0486/SCT/CHC-1/XII/2019 (1 TON)


SEE packing list, 0485/SCT/CHC-1/XII/2019 (16,9 TON)
Daily R
bined Cycle Gas Turbine Power Plant (1760MW)
G HABEAM CENTRE
Contruction Steel Structure

Work Summa
Today: 14 December 2019 (Saturday)
Activity

ial And Equipment For Erection Tb1&Tb2


tightening
Material Tb1&2
on
Material Unload

Material
tion and Bolting tightening
rm Working , Touchup Paint ,
terial
lation
ment position
E LINE CUPPING AND Padding inspection and coordinate
obilize from tb2 to tb1
Tightening Line and check bolt for inspection
Material
lation acsses
ction
nt
ion
ck Verticality ,and girder

Work Progress
Unit Total Q'ty
1
2
1
2
2
1
1
1
2
Materials
Item Unit Prev.

019 (1 TON) 1
019 (16,9 TON) 1
Daily Report

Work Summarization
Tomorrow: 15 D
Area
CHC site Office
& Lay down CHC

Turbin Building #1

Turbin Building #2
Work Progress Quantity
Up to Last day Today Accum.
ERECT ON 13 DES 19
ERECT ON 13 DES 19
ERECT ON 13 DES 19
Today Accum.
Title (Job Position)
Indirect
PROJECT MANAGER
SITE MANAGER
QUALITY CONTROL
INSPECTORE SCAFFOLDER
SUPERVISOR LIFTING
SUPERVISOR ERECTION
SITE ADMIN
SURVEY + ASS
LOGISTIK
EHS SAFETY
MEKCANIC
PERMIT HOLDER
DRIVER

Sub Total

Direct
FOREMAN FITTER ERECTION
FITTER ERECTION
WELDER
RIGGER
SCAFFOLDER
SIGHYALMAN
LABOUR/HELPER
FLAGMAN
OPERATOR + ASISTEN + MECANIC

Sub Total
Total
Tomorrow: 15 December 2019 (Sunday)
Activity
cum. Progress Plan Remark
0% 100%
- 0.00% 100%
- 0.00% 100%

- 0.00%
- 0.00%
Manpower Status
On-Site (Number) Total Day time (Hour)
Day Night Prev. Prev. Today Accum.

- -
1 - 10 10
3 - 30 30
1 - 10 10
2 - 20 20
2 - 20 20
1 - 10 10
3 - 30 30
1 - 10 10
3 - 30 30
1 - 10 10
1 10
2 20

21 0 - - 210 180

2 - 20 20
15
2
2
12
6
6
6 - 60 60
10 10 10

61 0 - - 90 90
82 0 - - 300 ###
Prepared by Confirmed by Approved by

Teten H Husein H Lukman Hakim

14 Desember 2019

Equipments
Item On Site Prev. Today Accum.
Crane Roughter 60 t 1 1 1
Crane Roughter 50 t 1 1 1
Boom Lift 38 m 1 1 1
Boom Lift 26 m 1 1 1
Trcuk Crane TMC 1 1 1
Trailer rental - -
Genset 15 KVA 1 1 1
Genset 10 KVA 1 1 1
Boom Lift 41 m 1 1 1

Level 2 2 2
Total Station 2 2 2
Lifting gear 1 1 1
Crawler crane 90 t 1 1 1
Crane rougther 25t 1 1 1

crawler crane 180t 1 1 1


(Hour) Night Time (Hour) Total
Accum. Prev. Today Accum. Accum.

- - - - -
10 - - - 10
30 - - - 30
10 - - - 10
20 - - - 20
20 - - - 20
10 - - - 10
30 - - - 30
10 - - - 10
30 - - - 30
10 - - - 10

180 180

20 - - - 20
60 - - - 60
10 10
- -
90 - - - 90
- 0 0 0 270
5/7/2019

OFF PROBLEM