Professional Documents
Culture Documents
Turbin Building #2 Continue Bolt Tightening Line and check bolt for inspection
Load Unload Material
Scaffold Installation acsses
Material Inspection
Touch Up Paint
Grouting Check ,and training grouting BASF
Continue Check Verticality ,and girder
Safety Net install for top roof and purlin erection include bolti
continue quality inspection tightening bolt joint JSP samsung
continue erection
Description
Erection TB2 NO ERECTION
Work Summa
Today: 18 December 2019 (Wednesday)
Activity
Material
tion and rafter Bolting tightening inspection joint JSP ,samsung
rm Working , Touchup Paint ,
terial
lation
ment position
k girder coordinate and internal joint survey samsung area piperack
Work Progress
Unit Total Q'ty
1
1
1
2
2
Materials
Item Unit Prev.
Work Summarization
Tomorrow: 19 De
Area
CHC site Office
& Lay down CHC
Turbin Building #1
Turbin Building #2
Work Progress Quantity
Up to Last day Today Accum.
Today Accum.
Title (Job Position)
Indirect
PROJECT MANAGER
SITE MANAGER
QUALITY CONTROL
INSPECTORE SCAFFOLDER
SUPERVISOR LIFTING
SUPERVISOR ERECTION
SITE ADMIN
SURVEY + ASS
LOGISTIK
EHS SAFETY
MEKCANIC
PERMIT HOLDER
DRIVER
Sub Total
Direct
FOREMAN FITTER ERECTION
FITTER ERECTION
WELDER
RIGGER
SCAFFOLDER
SIGHYALMAN
LABOUR/HELPER
FLAGMAN
OPERATOR + ASISTEN + MECANIC
Sub Total
Total
Tomorrow: 19 December 2019 (Thursday)
Activity
cum. Progress Plan Remark
0% 100%
- 0.00% 100%
- 0.00% 100%
- 0.00%
- 0.00%
Manpower Status
On-Site (Number) Total Day time (Hour)
Day Night Prev. Prev. Today Accum.
- -
1 - 10 10
3 - 30 30
1 - 10 10
2 - 20 20
2 - 20 20
1 - 10 10
3 - 30 30
1 - 10 10
3 - 30 30
1 - 10 10
1 10
2 20
21 0 - - 210 180
2 - 20 20
17
2
2
16
6
8
6 - 60 60
13 13 13
72 0 - - 93 93
93 0 - - 303 ###
Prepared by Confirmed by Approved by
18 Desember 2019
Equipments
Item On Site Prev. Today Accum.
Crane Roughter 60 t 1 1 1
Crane Roughter 50 t 1 1 1
Boom Lift 38 m 1 1 1
Boom Lift 26 m 1 1 1
Trcuk Crane TMC 1 1 1
Trailer rental - -
Genset 15 KVA 1 1 1
Genset 10 KVA 1 1 1
Boom Lift 41 m 1 1 1
Level 2 2 2
Total Station 2 2 2
Lifting gear 1 1 1
Crawler crane 90 t 1 1 1
Crane rougther 25t 1 1 1
- - - - -
10 - - - 10
30 - - - 30
10 - - - 10
20 - - - 20
20 - - - 20
10 - - - 10
30 - - - 30
10 - - - 10
30 - - - 30
10 - - - 10
180 180
20 - - - 20
60 - - - 60
13 13
- -
93 - - - 93
- 0 0 0 273
5/7/2019
OFF PROBLEM