ADI STATION STATUS

S.NO Pier Id Structure Con Forecasted date Starter Start Finish Reinforceme Shutter Bulk head Casting Actual Remarks D N Workers Date CL-1st Lift CL-2st Lift Transvers Beam &
as on 31.07.2023 Staging Staging nt & insert Casting e Beam Slab
fixing Date Row Labels Count of Pier Id
1 X21-Y1-C1 CL-1st Lift RRR 23-Jul-23 17-07-23 18-07-23 19-07-23 22-07-23 20-07-23 23-07-23 NS Beam & Slab 10 P A P A P A P A
2 X21-Y1-C2 CL-1st Lift RRR 22-Jul-23 16-07-23 17-07-23 18-07-23 21-07-23 19-07-23 22-07-23 NS R/F WIP 1 01-07-23
3 X21-Y4-C1 CL-1st Lift RRR 21-Jul-23 15-07-23 16-07-23 17-07-23 20-07-23 18-07-23 21-07-23 NS Staging WIP 6 02-07-23
4 X21-Y4-C2 CL-1st Lift RRR 14-Jul-23 08-07-23 09-07-23 10-07-23 13-07-23 11-07-23 14-07-23 NS (blank) 3 03-07-23 2 1
5 X22-Y1 CL-1st Lift RRR 09-Jul-23 06-07-23 07-07-23 08-07-23 11-07-23 09-07-23 12-07-23 NS CL-1st Lift 15 04-07-23 1
6 X22-Y4 CL-1st Lift RRR 08-Jul-23 02-07-23 03-07-23 04-07-23 07-07-23 05-07-23 08-07-23 Staging WIP Insert WIP 1 05-07-23 1
7 X23-Y4 CL-1st Lift RRR 07-Jul-23 23-06-23 01-07-23 03-07-23 05-07-23 03-07-23 06-07-23 Insert WIP NS 11 06-07-23 1
8 X24-Y4 CL-1st Lift RRR 11-Jul-23 05-07-23 30-07-23 02-07-23 03-07-23 03-07-23 03-07-23 03-07-23 Casting Comp 18 12 30 Staging WIP 1 07-07-23 1 1
9 X22-Y1 CL-1st Lift RRR 13-Jul-23 07-07-23 08-07-23 09-07-23 12-07-23 10-07-23 13-07-23 NS Casting Comp 2 08-07-23 1
10 X26-Y1-C2 CL-1st Lift RRR 19-Jul-23 30-05-23 14-07-23 15-07-23 18-07-23 16-07-23 19-07-23 NS Transverse Beam 14 09-07-23 1 1
11 X26-Y4-C1 CL-1st Lift RRR 15-Jul-23 09-07-23 10-07-23 11-07-23 14-07-23 12-07-23 15-07-23 NS R/F WIP 2 10-07-23
12 X26-Y4-C2 CL-1st Lift RRR 05-Jul-23 19-06-23 Full Lift 21-06-23 01-07-23 02-07-23 02-07-23 03-07-23 03-07-23 Casting Comp Staging Comp 2 11-07-23 1 1
13 X30-Y1-C2 CL-1st Lift RRR 16-Jul-23 30-05-23 11-07-23 12-07-23 15-07-23 13-07-23 16-07-23 NS Staging WIP 1 12-07-23 1
14 X30-Y4-C1 CL-1st Lift RRR 17-Jul-23 30-05-23 12-07-23 13-07-23 16-07-23 14-07-23 17-07-23 NS (blank) 7 13-07-23 1 1 1
15 X30-Y4-C2 CL-1st Lift RRR 18-Jul-23 30-05-23 13-07-23 14-07-23 17-07-23 15-07-23 18-07-23 NS Dowels WIP 1 14-07-23 1
16 X21-Y1-C1 CL-2nd Lift RRR 27-Jul-23 24-07-23 25-07-23 26-07-23 27-07-23 NS Ready for casting 1 15-07-23 1 1
17 X21-Y1-C2 CL-2nd Lift RRR 26-Jul-23 23-07-23 24-07-23 25-07-23 26-07-23 NS CL-2nd Lift 15 16-07-23 1 1
18 X21-Y4-C1 CL-2nd Lift RRR 25-Jul-23 22-07-23 23-07-23 24-07-23 25-07-23 NS NS 15 17-07-23 1 1 1
19 X21-Y4-C2 CL-2nd Lift RRR 18-Jul-23 15-07-23 16-07-23 17-07-23 18-07-23 NS Grand Total 54 18-07-23 1 1 1
20 X22-Y1 CL-2nd Lift RRR 13-Jul-23 13-07-23 14-07-23 15-07-23 16-07-23 NS 19-07-23 1 1 1 1
21 X22-Y4 CL-2nd Lift RRR 12-Jul-23 09-07-23 10-07-23 11-07-23 12-07-23 NS 20-07-23 1 2
22 X23-Y4 CL-2nd Lift RRR 11-Jul-23 07-07-23 08-07-23 09-07-23 10-07-23 NS 21-07-23 1 1 1
23 X24-Y4 CL-2nd Lift RRR 15-Jul-23 04-07-23 05-07-23 06-07-23 07-07-23 NS 22-07-23 1 1 1 1
24 X22-Y1 CL-2nd Lift RRR 17-Jul-23 14-07-23 15-07-23 16-07-23 17-07-23 NS 23-07-23 1 1
25 X26-Y1-C2 CL-2nd Lift RRR 23-Jul-23 20-07-23 21-07-23 22-07-23 23-07-23 NS Completed 2 24-07-23 1
26 X26-Y4-C1 CL-2nd Lift RRR 19-Jul-23 16-07-23 17-07-23 18-07-23 19-07-23 NS Balance -2 25-07-23 1 1
27 X26-Y4-C4 CL-2nd Lift RRR 09-Jul-23 04-07-23 05-07-23 06-07-23 07-07-23 NS CL-2st Lift 26-07-23 1 1
28 X30-Y1-C2 CL-2nd Lift RRR 20-Jul-23 17-07-23 18-07-23 19-07-23 20-07-23 NS Plan FTM 15 27-07-23 1 2
29 X30-Y4-C1 CL-2nd Lift RRR 21-Jul-23 18-07-23 19-07-23 20-07-23 21-07-23 NS Plan as on date 28-07-23 1
30 X30-Y4-C2 CL-2nd Lift RRR 22-Jul-23 19-07-23 20-07-23 21-07-23 22-07-23 NS Completed 29-07-23 2
1 R1-X01 Transverse Beam NHCC 16-Jul-23 5-Jul-23 10-Jul-23 16-Jul-23 18-Jul-23 19-Jul-23 19-Jul-23 Balance 15 30-07-23 1
2 R1-X02 Transverse Beam NHCC 07-Jul-23 30-May-23 12-Jun-23 4-Jul-23 5-Jul-23 6-Jul-23 7-Jul-23 Ready for casting Transverse Beam 31-07-23
3 R3-X05 Transverse Beam NHCC 19-Jul-23 5-Jul-23 10-Jul-23 16-Jul-23 18-Jul-23 19-Jul-23 19-Jul-23 Plan FTM 13 Total 15 2 15 13 11
4 R3-X06 Transverse Beam NHCC 20-Jul-23 6-Jul-23 11-Jul-23 17-Jul-23 19-Jul-23 20-Jul-23 20-Jul-23 Plan as on date
5 R3-X07 Transverse Beam NHCC 25-Jul-23 11-Jul-23 16-Jul-23 22-Jul-23 24-Jul-23 25-Jul-23 25-Jul-23 81 29 110 Completed Toal Manpower
6 R3-X11 Transverse Beam RRR 6-Jul-23 Staging WIP Balance 13 Requried 370
7 R3-X13 Transverse Beam RRR 22-Jul-23 9-Jul-23 14-Jul-23 20-Jul-23 20-Jul-23 21-Jul-23 22-Jul-23 Beam & Slab Available 393
8 R5 - X17 Transverse Beam RRR 13-Jul-23 3-Jul-23 8-Jul-23 14-Jul-23 14-Jul-23 15-Jul-23 16-Jul-23 Staging Comp Plan FTM 11 Balance -23
9 R5 - X18 Transverse Beam RRR 03-Jul-23 15-Jun-23 20-Jun-23 1-Jul-23 1-Jul-23 2-Jul-23 3-Jul-23 R/F WIP Plan as on date NHCC RRR Worker
10 R7-X26 (T) Transverse Beam RRR 20-Jul-23 7-Jul-23 12-Jul-23 18-Jul-23 18-Jul-23 19-Jul-23 20-Jul-23 Completed CL-1st Lift 9
11 R7-X27 (T) Transverse Beam RRR 06-Jul-23 4-Jun-23 9-Jun-23 4-Jul-23 4-Jul-23 5-Jul-23 6-Jul-23 R/F WIP Balance 11 CL-2st Lift 11 23
12 R7-X28 (T) Transverse Beam RRR 04-Jul-23 2-Jun-23 7-Jun-23 4-Jul-23 5-Jul-23 6-Jul-23 7-Jul-23 Dowels WIP Transverse Beam 5 8 70 112
13 R7-X29 (T) Transverse Beam RRR 17-Jul-23 3-Jul-23 6-Jul-23 12-Jul-23 12-Jul-23 13-Jul-23 14-Jul-23 Staging Comp Labour Count Transverse Beam 4 6 56 84
14 R7-X30 (T) Transverse Beam RRR 18-Jul-23 5-Jul-23 10-Jul-23 16-Jul-23 16-Jul-23 17-Jul-23 18-Jul-23 CL-1st Lift Total Manpower 126 219
1 R1-X01-X02 Beam & Slab NHCC 22-Jul-23 5-Jul-23 10-Jul-23 16-Jul-23 20-Jul-23 21-Jul-23 22-Jul-23 Staging WIP Required
2 R1-X02-X03 Beam & Slab NHCC 28-Jul-23 11-Jul-23 16-Jul-23 22-Jul-23 26-Jul-23 27-Jul-23 28-Jul-23 Staging WIP Available 30 Destaging
3 R1-X04-X05 Beam & Slab NHCC 27-Jul-23 13-Jul-23 18-Jul-23 24-Jul-23 28-Jul-23 29-Jul-23 30-Jul-23 Balance -30 stressing
186 67 253
4 R1-X05-X06 Beam & Slab NHCC 30-Jul-23 14-Jul-23 19-Jul-23 25-Jul-23 29-Jul-23 30-Jul-23 31-Jul-23 CL-2nd Lift
5 R3-X12-X13 Beam & Slab RRR 6-Jul-23 Staging WIP
6 R4-X16-X17 Beam & Slab RRR 6-Jul-23 Staging WIP
7 R4-X17-X18 Beam & Slab RRR 29-Jul-23 12-Jul-23 17-Jul-23 23-Jul-23 27-Jul-23 28-Jul-23 29-Jul-23 R/F WIP Required 23
8 R6-X18-X19 Beam & Slab RRR 27-Jul-23 10-Jul-23 15-Jul-23 21-Jul-23 25-Jul-23 26-Jul-23 27-Jul-23 Available
9 R6-X19-X20 Beam & Slab RRR 24-Jul-23 7-Jul-23 12-Jul-23 18-Jul-23 22-Jul-23 23-Jul-23 24-Jul-23 Staging WIP Balance 23
10 R6-X20-X21 Beam & Slab RRR 19-Jul-23 2-Jul-23 7-Jul-23 13-Jul-23 17-Jul-23 18-Jul-23 19-Jul-23 Staging WIP Transverse Beam
11 R7-X26-X27(T) Beam & Slab RRR 29-Jul-23 12-Jul-23 17-Jul-23 23-Jul-23 27-Jul-23 28-Jul-23 29-Jul-23 Required 182
12 R7-X27-X28(T) Beam & Slab RRR 21-Jul-23 4-Jul-23 9-Jul-23 15-Jul-23 19-Jul-23 20-Jul-23 21-Jul-23 Staging WIP Available 363
13 R7-X28-X29(T) Beam & Slab RRR 26-Jul-23 9-Jul-23 14-Jul-23 20-Jul-23 24-Jul-23 25-Jul-23 26-Jul-23 Staging WIP Balance -181
Beam & Slab
Required 165
Available
Balance 165