SL No Activity UOM Qty. Start Date Finish Date Duration Remarks

A Column
1 Column Starter Done
3 Column Modification 7-Jan-24 12-Jan-24
4 Column Reinforcement MT 9 8-Jan-24 13-Jan-24 5
5 Column Shuttering Sqm 240 9-Jan-24 14-Jan-24 5
6 Column RCC Cum 53 9-Jan-24 14-Jan-24 5
B Retaining wall
1 Stagging for 1st lift Started 7-Jan-24
2 Reinforcement for 1st lift MT 6 5-Jan-24 8-Jan-24 3
3 Shuttering for 1st lift SQM 694 6-Jan-24 17-Jan-24 11
4 RCC for 1st lift CUM 163 8-Jan-24 19-Jan-24 11
5 Stagging for2nd lift 10-Jan-24 21-Jan-24 11
6 Reinforcement for 2nd lift MT 11-Jan-24 22-Jan-24 11
7 Shuttering for2nd lift SQM 694 12-Jan-24 23-Jan-24 11
8 RCC for 2nd lift CUM 163 13-Jan-24 24-Jan-24 11
C Water tank
1 Stagging for 1st lift Started 8-Jan-24
2 Reinforcement for 1st lift MT 3 Done
3 Shuttering for 1st lift SQM 369 Started 12-Jan-24
4 RCC for 1st lift CUM 76 5-Jan-24 13-Jan-24 8
5 Stagging for2nd lift 8-Jan-24 16-Jan-24 8
6 Reinforcement for 2nd lift MT 3 10-Jan-24 18-Jan-24 8
7 Shuttering for2nd lift SQM 369 11-Jan-24 19-Jan-24 8
8 RCC for 2nd lift CUM 76 12-Jan-24 20-Jan-24 8
D STP
1 Stagging for 1st lift LS 1 6-Jan-24 7-Jan-24 1
2 Reinforcement for 1st lift MT 1 7-Jan-24 8-Jan-24 1
3 Shuttering for 1st lift SQM 158 11-Jan-24 13-Jan-24 3
4 RCC for 1st lift CUM 33 14-Jan-24 14-Jan-24 1
5 Stagging for2nd lift LS 1 14-Jan-24 15-Jan-24 1
6 Reinforcement for 2nd lift MT 1 16-Jan-24 18-Jan-24 2
7 Shuttering for2nd lift SQM 158 19-Jan-24 22-Jan-24 3
8 RCC for 2nd lift CUM 33 23-Jan-24 24-Jan-24 1
E Stagging for slab & beam LS 1 5-Jan-24 26-Jan-24 21
F Shuttering for slab & beam SQM 2269.775 8-Jan-24 28-Jan-24 20
G Reinforcement of beam 15-Jan-24 30-Jan-24 15
MT 75
I Reinforcement of slab 19-Jan-24 31-Jan-24 12
J Bolt fixing/ Pocket LS 1 22-Jan-24 1-Feb-24 10
K Out side Shuttering SQM 567 30-Jan-24 1-Feb-24 2
L Checking & cleaning LS 1 2-Feb-24 2-Feb-24 1
M Casting CUM 498 3-Feb-24 4-Feb-24