HACH Project_MWP_Nov 23

Status as on 06-Nov-23
Controller Mr.LV Goni
Sr.no Work description Responsible person Target date Today Progress Status Remarks
Acheieved
R0 R1 06-11-2023
1 Construction work (Preliminary work)
Precasting work
i Precast BOX Culverts, 150 Nos 31-Dec-23 Precasting is being done at HACH,
ii Precast PSC girder , 1 Nos Mr.Ashok Kr. Singh 30-Dec-23
iii C&G , 10 Km 30-Nov-23
2 Mix design
2.1 Mix design with fly ash
i PCC_M-15 30-Nov-23
ii RCC M-35 for precast box culvert (Pakona plant) 05-Dec-23
iii RCC_M-35 (For wall,Bottom slab & Deck slab) 10-Dec-23 Mix design not started Design Mix done at BEHU to be followed by HACH
Mr.KM Prashant Kumar
iv RCC_M-40 (Precast RCC beam, C/S 600X250MM) 10-Dec-23 till month of Dec. 2023. HACH to start design mix
v RCC M-40 (Precast RCC Plank-120 MM thick) 10-Dec-23 from 03.11.2023
vi RCC_M-50 (For precast PSC girder) 15-Dec-23
vii CTSB 15-Dec-23
3 Delayed Activity
i Borrow Area 3000Cum/5400 Cum 11-Nov-23
Approval pending
ii Borrow area permission- 2 Lacs Cum Mr.LV Goni 11-Nov-23
iii Disbursement of 3G Award amount 30-Oct-23 20-Nov-23
4 Environmental clearance
i Dist- Belgaum public hearing 29-Nov-23
ii Dist- Raichur public hearing 17-Nov-23
Mr.Bhimrao
iii Dist- Bhagalkote public hearing 16-Nov-23
4.1 Environmental clearance 25-Dec-23
5 LA 30 Oct /30 Nov 23
i 3A (SIRWAR) Publication in News Paper 30-Oct-23

ii 3D(SIRWAR) 27-Nov-23
iii 3A (BASAPUR) Publication in News Paper 09-Nov-23 Done

iv 3D(BASAPUR) 07-Dec-23 Done

vi 3G approval for RO office-Balance 5 nos village 15-Oct-23 30-Oct-23 2 nos village completed & 3 nos pending

Total 17 Village :-
(1) 4 nos. Village-Target date 02 Nov 23 ,
v Disbursement to be completed Mr. Basavaj 30-Oct-23 20-Nov-23 WIP (2) 11 nos. Village - Target date-20 Nov 23)
Disbursement target -43.2 km Project scope out of
44.9 km

Total 17 Village :-
(1) 4 nos. Village-Target date 03 Nov 23 ,
vi ROW possession (Govt & Private) 30 Oct /30 Nov 23 31-Dec-23 (2) 11 nos. Village - Target date-21 Nov 23)

Balance stretch including BASAPUR, SIRWAR ROW


Possession by 31 Dec'23

vii Diff in ROW vs Present L.Aq 05-Oct-23

6 Quarry & Crusher 15-Nov-23


i Drilling & Blasting Permission 15-Oct-23 15-Nov-23 Letter Submission pending for NOC
ii Quarry Permission 25-Oct-23 25-Nov-23
iii Crushing Start date Mr.Bhimrao 15-Nov-23 24-Dec-23
iv CFE 30-Oct-23 15-Nov-23 Pending
V CFO 15-Dec-23
7 Borrow Area 12-Oct-23
3000 cum/5400 Cum soil approval for Govt + Private
i 12-Oct-23 11-Nov-23 Paper submission wip for approval
(Royalty submission)

Pond ash procurement letter-NTPC-Raichur & Kudgi Mr.Bhimrao


ii 19-Oct-23 27-Oct-23 Done
(Qty-5 Lacks Cum from each source)

iii Borrow area permission- 2 Lacs Cum 12-Oct-23 11-Nov-23 Paper collection in progress
8 Tree cutting 30-Dec-23

i Tree cutting valuation to be done (RFO-ACFO-DCFO) 05-Oct-23 01-Nov-23 Valuation work in progress-Pending at RFO
ii NHAI to deposit money with in a 1 week Mr. Bhimrao 12-Oct-23 08-Nov-23
iii Tree cutting permission 27-Oct-23 20-Nov-23
iv Tree cutting 30-Dec-23
9 Electric utility shifting
i Joint Inspection to be done 07-Oct-23 Done
9.1 Estimates from the respective sub division
i Lingsugur Sub division 19-Oct-23
Mr.LV Goni
ii Sirwar Sub division 20-Nov-23 Done
iii Mhaski sub division 19-Oct-23 20-Nov-23
9.2 Estimates for Shifting HT/LT Lines 30-Nov-23
10 Water utility shifting
i Joint Inspection to be done 08-Oct-23 Completed 25-Oct-23
10.1 Estimate to be done 15-Oct-23 15-Nov-23
i Lingsugur Sub division Mr.LV Goni 13-Nov-23
Eastimate prepration wip
ii Manvi sub division 15-Nov-23
10.2 Sub -con finalisation from CO 30-Oct-23
11 HACH-Mess contractor to be finalised from CO 07-Oct-23 Done
12 CAMP Electric connection
10 KVA temporary
i 07-Oct-23 28-Oct-23 Done
Cost benefit analysis to be done wrt DG
ii 850 KVA connection
iii Load details to be shared with site Mr.LV Goni 05-Oct-23 Done
iv Contractor quotations from site to be submitted 12-Oct-23 02-Nov-23
v Contractor Finalization to be done at CO 19-Oct-23 10-Nov-23
vi Connection at site 18-Nov-23 25-Dec-23
13 ROW verification to be done Mr. Vishwajit mondal 10-Oct-23 Completed
14 Soil investigation Mr.Prashant 24-Oct-23 10-Nov-23 16 Nos bore hole balance.
15 Applicable Permits
i Tempory NA Mr. Ajay manawat 20-Oct-23 15-Nov-23 Paper submission WIP
ii CFE permission for plants 30-Oct-23 15-Nov-23 WIP
Mr. Ajay manawat
iii CFO permission for plants 30-Oct-23 15-Dec-23

iv Village panchyat NOC (BP,HMP,WMM etc.) 10-Oct-23 02-Nov-23 Done

v Village panchyat/Govt NOC (Borrow earth extraction) Mr. Ravi raju 10-Oct-23 02-Nov-23
NHAI PIU was requested to Issue Form-3 on
vi Labour licence 10-Oct-23 10-Nov-23 12.10.2023. NHAI PIU is being persued to issue Form-
3
RTO NOC for the vehicles transferred from other site
vii RTO Mr.Bhimrao 15-Oct-23 05-Nov-23 awaited, presently temp. NOC Karnatka state is taken
on monthly basis
18 Camp construction
i Lab completion 30-Oct-23 30-Nov-23 WIP
Mr.LV Goni
ii Staff shifting 30-Oct-23 30-Nov-23
19 HSD Pump Installation
i Peso Class B License Mr. Ravi raju 30-Nov-23
20 Project work

1 Identification of priority stretches Mr.LV Goni 09-Oct-23 Done

2 Design priority Mr. Rajeev Naryal 10-Oct-23 Done

On 27 Oct ,4 set avl at site,2 each of existing road


and borrow area will be tested,24 nos mould
3 CBR testing report Mr.Prashant 12 oct to 30 Oct 27-Oct-23 5 Borrow area testing & report- completed
required for further testing will follow the same
sequence.

MS-1 Achievement plan as per Schedule-G along with


4 Mr.LV Goni 09-Oct-23 02-Nov-23
Qty & material requirement.