You are on page 1of 9

Project: Titanium Tech park , Bangalo

Subject: Fire Fighting system package Work

Sl No Floor

1 Basement 2

A Primer for pipes


Zone-1 (Header-1)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Zone-2 (Header-2)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Water curtain Line
a) Marking and Drilling
b) Header Fabrication
c) Header Primer
d) Header Painting
e) Header Erection

2 Basement 3
A Primer for pipes
Zone-2 (Header-2)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Zone-1 (Header-1)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Water curtain Line
a) Marking and Drilling
b) Header Fabrication
c) Header Primer
d) Header Painting
e) Header Erection

3 Basement 1
A Primer for pipes
Zone-1 (Header-1)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Zone-2 (Header-2)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Water curtain Line
a) Marking and Drilling
b) Header Fabrication
c) Header Primer
d) Header Painting
e) Header Erection
Hydrant & ICV Line
a) Marking and Drilling
b) Primer
c) Painting
d) Erection
e) Final Welding

4 2nd Floor
A Primer for pipes
Zone-1 (Header-1)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding
Zone-2 (Header-2)
a) Marking and Drilling
b) Prefabrication of Branch Pipes
c) Primer for Prefabricated Pipes
d) Painting for Prefabricated Pipes
e) Erection of Branch Pipes
f) Header Fabrication
g) Erection of Header Pipes & Branch Tapping
h) Final Welding

NOTE: Above mentioned dates may change depend on the site clearance.
Project: Titanium Tech park , Bangalore
Subject: Fire Fighting system package Work Schedule
Date : 20.11.202
Start Date Finish Date
No. Of Sprinkler Branches Days
Planned Actual Planned Actual

60 13-Sep-23 13-Sep-23 12-Nov-23


30-Nov-23

6 13-Sep-23 13-Sep-23 19-Sep-23 19-Sep-23

100 Nos 4 13-Sep-23 13-Sep-23 17-Sep-23 17-Sep-23


100 Nos 8 15-Sep-23 15-Sep-23 23-Sep-23 23-Sep-23
100 Nos 2 15-Sep-23 15-Sep-23 17-Sep-23 17-Sep-23
100 Nos 2 15-Sep-23 17-Sep-23 17-Sep-23 17-Sep-23
100 Nos 6 17-Sep-23 17-Sep-23 23-Sep-23 23-Sep-23
6 4-Oct-23 4-Oct-23 10-Oct-23 10-Oct-23
100 Nos 6 12-Oct-23 12-Oct-23 18-Oct-23 18-Oct-23
100 Nos 10 12-Oct-23 12-Oct-23 22-Oct-23

72 Nos 4 18-Sep-23 18-Sep-23 22-Sep-23 22-Sep-23


72 Nos 8 24-Sep-23 24-Sep-23 2-Oct-23 2-Oct-23
72 Nos 2 3-Oct-23 3-Oct-23 5-Oct-23 5-Oct-23
72 Nos 2 3-Oct-23 3-Oct-23 5-Oct-23 5-Oct-23
72 Nos 6 7-Oct-23 7-Oct-23 13-Oct-23 13-Oct-23
6 14-Oct-23 14-Oct-23 20-Oct-23 20-Oct-23
72 Nos 6 25-Oct-23 25-Oct-23 31-Oct-23 31-Oct-23
72 Nos 10 2-Nov-23 2-Nov-23 12-Nov-23 12-Nov-23

2 31-Oct-23 17-Nov-23 19-Nov-23


4 31-Oct-23 18-Nov-23 22-Nov-23
2 18-Nov-23 22-Nov-23 24-Nov-23
2 22-Nov-23 24-Nov-23 26-Nov-23
4 24-Nov-23 26-Nov-23 30-Nov-23

72 27-Sep-23 27-Sep-23 8-Dec-23


6 27-Sep-23 27-Sep-23 3-Oct-23 3-Oct-23

68 Nos 4 27-Sep-23 27-Sep-23 1-Oct-23 1-Oct-23


68 Nos 8 1-Oct-23 1-Oct-23 9-Oct-23 9-Oct-23
68 Nos 2 9-Oct-23 9-Oct-23 11-Oct-23 11-Oct-23
68 Nos 2 11-Oct-23 11-Oct-23 13-Oct-23 13-Oct-23
68 Nos 6 13-Oct-23 13-Oct-23 19-Oct-23 19-Oct-23
6 19-Oct-23 19-Oct-23 25-Oct-23 25-Oct-23
68 Nos 6 25-Oct-23 25-Oct-23 31-Oct-23 31-Oct-23
68 Nos 10 31-Oct-23 31-Oct-23 10-Nov-23 10-Nov-23

86 Nos 4 25-Oct-23 25-Oct-23 29-Oct-23 29-Oct-23


86 Nos 8 25-Oct-23 25-Oct-23 2-Nov-23 2-Nov-23
86 Nos 2 2-Nov-23 2-Nov-23 4-Nov-23 4-Nov-23
86 Nos 2 4-Nov-23 4-Nov-23 6-Nov-23 6-Nov-23
86 Nos 7 6-Nov-23 6-Nov-23 13-Nov-23 13-Nov-23
8 13-Nov-23 13-Nov-23 21-Nov-23 21-Nov-23
86 Nos 7 21-Nov-23 21-Nov-23 28-Nov-23 28-Nov-23
86 Nos 10 28-Nov-23 28-Nov-23 8-Dec-23

2 26-Nov-23 10-Nov-23 12-Nov-23 12-Nov-23


4 26-Nov-23 10-Nov-23 14-Nov-23 14-Nov-23
2 30-Nov-23 14-Nov-23 16-Nov-23 16-Nov-23
2 2-Dec-23 16-Nov-23 18-Nov-23 18-Nov-23
4 4-Dec-23 18-Nov-23 22-Nov-23

90 18-Oct-23 16-Nov-23 16-Jan-24


10 18-Oct-23 10-Dec-23 20-Dec-23

90 Nos 4 27-Oct-23 16-Nov-23 27-Nov-23


90 Nos 8 31-Oct-23 7-Dec-23 15-Dec-23
90 Nos 2 8-Nov-23 15-Dec-23 17-Dec-23
90 Nos 2 10-Nov-23 17-Dec-23 19-Dec-23
90 Nos 6 12-Nov-23 19-Dec-23 25-Dec-23
6 18-Nov-23 25-Dec-23 31-Dec-23
90 Nos 6 24-Nov-23 31-Dec-23 6-Jan-24
90 Nos 10 30-Nov-23 6-Jan-24 16-Jan-24

74 Nos 4 2-Nov-23 16-Nov-23 20-Nov-23


74 Nos 8 9-Nov-23 20-Nov-23 28-Nov-23
74 Nos 2 17-Nov-23 28-Nov-23 30-Nov-23
74 Nos 2 19-Nov-23 30-Nov-23 2-Dec-23
74 Nos 7 21-Nov-23 2-Dec-23 9-Dec-23
8 28-Nov-23 9-Dec-23 17-Dec-23
74 Nos 7 6-Dec-23 17-Dec-23 24-Dec-23
74 Nos 10 13-Dec-23 24-Dec-23 3-Jan-24

2 23-Dec-23 23-Dec-23 25-Dec-23


4 23-Dec-23 23-Dec-23 27-Dec-23
2 27-Dec-23 27-Dec-23 29-Dec-23
2 29-Dec-23 29-Dec-23 31-Dec-23
4 31-Dec-23 31-Dec-23 4-Jan-24

4 27-Dec-23 27-Dec-23 31-Dec-23


2 27-Dec-23 27-Dec-23 29-Dec-23
2 29-Dec-23 29-Dec-23 31-Dec-23
8 31-Dec-23 31-Dec-23 8-Jan-24
8 8-Jan-24 8-Jan-24 16-Jan-24

30 6-Nov-23 16-Nov-23 6-Dec-23


14-Dec-23
6 6-Nov-23 20-Nov-23 26-Nov-23

48 Nos 2 6-Nov-23 16-Nov-23 18-Nov-23


48 Nos 4 10-Nov-23 20-Nov-23 24-Nov-23
48 Nos 2 14-Nov-23 24-Nov-23 26-Nov-23
48 Nos 2 16-Nov-23 26-Nov-23 28-Nov-23
48 Nos 4 18-Nov-23 28-Nov-23 2-Dec-23
2 22-Nov-23 2-Dec-23 4-Dec-23
48 Nos 2 24-Nov-23 4-Dec-23 6-Dec-23
48 Nos 5 26-Nov-23 6-Dec-23 11-Dec-23

56 Nos 2 8-Nov-23 16-Nov-23 18-Nov-23


56 Nos 4 15-Nov-23 23-Nov-23 27-Nov-23
56 Nos 2 19-Nov-23 27-Nov-23 29-Nov-23
56 Nos 2 21-Nov-23 29-Nov-23 1-Dec-23
56 Nos 4 23-Nov-23 1-Dec-23 5-Dec-23
56 Nos 2 27-Nov-23 5-Dec-23 7-Dec-23
56 Nos 2 29-Nov-23 7-Dec-23 9-Dec-23
56 Nos 5 1-Dec-23 9-Dec-23 14-Dec-23

ance.
Date : 20.11.2023
Remarks

Water curtain pipe


supplied on 10-Nov-23

Except Stack parking


Except Stack parking