Civil Work Plan for MWP-19 Projects

The document outlines the work breakdown structure (WBS) codes, original and baseline start and finish dates, and actual start and finish dates for various projects for MWP-19. Key projects include the alkali, surfactant, and polymer preparation systems. The pipeline civil work has the longest original duration at 188 days from March 16 to September 7. Some projects are waiting on vendor information or contractor finalization.

Uploaded by

Manoj Sinha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views2 pages

Civil Work Plan for MWP-19 Projects

The document outlines the work breakdown structure (WBS) codes, original and baseline start and finish dates, and actual start and finish dates for various projects for MWP-19. Key projects include the alkali, surfactant, and polymer preparation systems. The pipeline civil work has the longest original duration at 188 days from March 16 to September 7. Some projects are waiting on vendor information or contractor finalization.

Uploaded by

Manoj Sinha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Actual /

WBS Code Original BL BL Planned


Duration Start Finish Start Date
Alkali Preparation System - MWP-19 23 17-Apr-23 13-May-23
Surfactant Preparation System - MWP-19 39 7-Apr-23 13-May-23
Polymer Preparation System -MWP-19 27 21-Apr-23 23-May-23
ASP Injection System Pump- MWP-19&01 44 26-Apr-23 6-Jun-23
ASP Storage Tank at MWP-19 & 01 20 6-May-23 25-May-23
Soft Water Storage Tank at MWP-19 & 01 15 2-Mar-23 15-Mar-23 20-Jan-23

Soft Water Transfer Pump at MWP-19 & 01 15 23-Mar-23 6-Apr-23

TDS Increase Package at MWP-19 & 01 10 9-Mar-23 18-Mar-23


IDBH Bath Heater Package-MWP-19 38 20-Mar-23 24-Apr-23 27-Mar-23

Pipeline Civil Work 188 16-Mar-23 7-Sep-23

Piping Civil Work 30 13-May-23 16-Jun-23

Pig Launcher & Pig Receiver 27 14-Mar-23 14-Apr-23

Chemical Injection Skids at MWP 19 & 01 14 8-Apr-23 21-Apr-23


IA & N2 IA & N2 Package 21 19-Apr-23 8-May-23
Trenches and Culverts 35 11-Apr-23 12-May-23
Transformer Foundation 50 1-May-23 15-Jun-23
Substation cum Control Room Building 95 15-Mar-23 10-Jun-23 17-Mar-23
Remark

Waiting for GAD from


Pump Vendor

Contractor Finalization is
in progress

Waiting for confimation


on Production pipeline
size 10"/12"