Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
0 PS Sirius Project Schedule: Jetty, 79 w Thu 3/31/22 Fri 10/20/23
Tuxpan, Hidalgo and Pipeline
1 PS1 Jetty 60.4 w Thu 3/31/22 Tue 6/13/23
2 PS1.01 Terminal Management System 32.4 w Thu 3/31/22 Tue 11/22/22
3 PS1.01.001 Engineering 9.6 w Thu 3/31/22 Thu 6/9/22
4 PS1.01.001.0001 Inf Requirements 2w Thu 3/31/22 Wed 4/13/22
5 PS1.01.001.0002 Freeze Inf 1w Thu 4/21/22 Wed 4/27/22
6 PS1.01.001.0003 Functional Design Development 3w Thu 4/28/22 Thu 5/19/22
7 PS1.01.001.0004 Approval 3w Fri 5/20/22 Thu 6/9/22
8 PS1.01.002 Manufacturing 21 w Fri 5/20/22 Mon 10/17/22
9 PS1.01.002.0001 Procurement 3w Fri 5/20/22 Thu 6/9/22
10 PS1.01.002.0002 Manufacturing 16 w Fri 6/10/22 Mon 10/3/22
11 PS1.01.002.0003 Transfers / Import 2w Tue 10/4/22 Mon 10/17/22
12 PS1.01.003 Factory Testing 1w Mon 10/17/22 Fri 10/21/22
13 PS1.01.003.0001 FAT 1w Mon 10/17/22 Fri 10/21/22
14 PS1.01.004 Transportation 1w Thu 10/20/22 Wed 10/26/22
15 PS1.01.004.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
16 PS1.01.005 Installation 1w Wed 11/2/22 Tue 11/8/22
17 PS1.01.005.0001 Installation supervision 1w Wed 11/2/22 Tue 11/8/22
18 PS1.01.006 Documentation 1w Tue 11/15/22 Tue 11/22/22
19 PS1.02 Process Control System 50.8 w Thu 3/31/22 Mon 4/3/23
20 PS1.02.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
21 PS1.02.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
22 PS1.02.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
23 PS1.02.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
24 PS1.02.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
25 PS1.02.002 Configuration 6w Tue 7/5/22 Mon 8/15/22
26 PS1.02.002.0001 Configuration 6w Tue 7/5/22 Mon 8/15/22
27 PS1.02.003 Manufacturing 37.6 w Tue 5/31/22 Thu 2/23/23
28 PS1.02.003.0001 Procurement 3w Tue 5/31/22 Mon 6/20/22
29 PS1.02.003.0002 Manufacturing 26 w Tue 7/26/22 Fri 1/27/23
30 PS1.02.003.0003 Transfers / Import 2w Thu 2/2/23 Thu 2/16/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 1
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
31 PS1.02.003.0004 Integration 1w Fri 2/17/23 Thu 2/23/23
32 PS1.02.004 Factory Testing 1.2 w Thu 2/23/23 Thu 3/2/23
33 PS1.02.004.0001 FIT 3d Tue 2/28/23 Thu 3/2/23
34 PS1.02.004.0002 FAT 1w Thu 2/23/23 Wed 3/1/23
35 PS1.02.005 Transportation 1w Wed 3/1/23 Tue 3/7/23
36 PS1.02.005.0001 Shipment 1w Wed 3/1/23 Tue 3/7/23
37 PS1.02.006 Installation 0.2 w Mon 3/13/23 Mon 3/13/23
38 PS1.02.006.0001 Installation supervision 1d Mon 3/13/23 Mon 3/13/23
39 PS1.02.007 Site Services 1w Wed 3/22/23 Tue 3/28/23
40 PS1.02.007.0001 SAT 1d Wed 3/22/23 Wed 3/22/23
41 PS1.02.007.0002 Commissioning 3d Thu 3/23/23 Mon 3/27/23
42 PS1.02.007.0003 Start-up 1d Tue 3/28/23 Tue 3/28/23
43 PS1.02.008 Documentation 1w Tue 3/28/23 Mon 4/3/23
44 PS1.03 Safety Instrumented System 57.8 w Thu 3/31/22 Thu 5/25/23
45 PS1.03.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
46 PS1.03.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
47 PS1.03.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
48 PS1.03.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
49 PS1.03.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
50 PS1.03.002 Configuration 6w Tue 6/21/22 Mon 8/1/22
51 PS1.03.002.0001 Configuration 6w Tue 6/21/22 Mon 8/1/22
52 PS1.03.003 Manufacturing 32 w Tue 6/7/22 Fri 1/20/23
53 PS1.03.003.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
54 PS1.03.003.0002 Manufacturing 26 w Tue 6/28/22 Fri 12/30/22
55 PS1.03.003.0003 Transfers / Import 2w Mon 1/2/23 Fri 1/13/23
56 PS1.03.003.0004 Integration 1w Mon 1/16/23 Fri 1/20/23
57 PS1.03.004 Factory Testing 1.4 w Wed 1/25/23 Thu 2/2/23
58 PS1.03.004.0001 FIT 3d Wed 1/25/23 Fri 1/27/23
59 PS1.03.004.0002 FAT 1w Fri 1/27/23 Thu 2/2/23
60 PS1.03.005 Transportation 1w Wed 2/1/23 Wed 2/8/23
61 PS1.03.005.0001 Shipment 1w Wed 2/1/23 Wed 2/8/23
62 PS1.03.006 Installation 0.2 w Tue 2/14/23 Tue 2/14/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 2
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
63 PS1.03.006.0001 Installation supervision 1d Tue 2/14/23 Tue 2/14/23
64 PS1.03.007 Site Services 11.8 w Wed 2/22/23 Fri 5/19/23
65 PS1.03.007.0001 SAT 1d Wed 2/22/23 Wed 2/22/23
66 PS1.03.007.0002 Commissioning 3d Tue 5/16/23 Thu 5/18/23
67 PS1.03.007.0003 Start-up 1d Fri 5/19/23 Fri 5/19/23
68 PS1.03.008 Documentation 1w Fri 5/19/23 Thu 5/25/23
69 PS1.04 Fire & Gas System 48.2 w Thu 3/31/22 Tue 3/14/23
70 PS1.04.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
71 PS1.04.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
72 PS1.04.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
73 PS1.04.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
74 PS1.04.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
75 PS1.04.002 Configuration 6w Tue 7/5/22 Mon 8/15/22
76 PS1.04.002.0001 Configuration 6w Tue 7/5/22 Mon 8/15/22
77 PS1.04.003 Manufacturing 32 w Tue 6/21/22 Fri 2/3/23
78 PS1.04.003.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
79 PS1.04.003.0002 Manufacturing 26 w Tue 7/12/22 Fri 1/13/23
80 PS1.04.003.0003 Transfers / Import 2w Mon 1/16/23 Fri 1/27/23
81 PS1.04.003.0004 Integration 1w Mon 1/30/23 Fri 2/3/23
82 PS1.04.004 Factory Testing 1.2 w Fri 2/3/23 Mon 2/13/23
83 PS1.04.004.0001 FIT 3d Thu 2/9/23 Mon 2/13/23
84 PS1.04.004.0002 FAT 1w Fri 2/3/23 Fri 2/10/23
85 PS1.04.005 Transportation 1w Fri 2/10/23 Thu 2/16/23
86 PS1.04.005.0001 Shipment 1w Fri 2/10/23 Thu 2/16/23
87 PS1.04.006 Installation 0.2 w Wed 2/22/23 Wed 2/22/23
88 PS1.04.006.0001 Installation supervision 1d Wed 2/22/23 Wed 2/22/23
89 PS1.04.007 Site Services 1w Thu 3/2/23 Wed 3/8/23
90 PS1.04.007.0001 SAT 1d Thu 3/2/23 Thu 3/2/23
91 PS1.04.007.0002 Commissioning 3d Fri 3/3/23 Tue 3/7/23
92 PS1.04.007.0003 Start-up 1d Wed 3/8/23 Wed 3/8/23
93 PS1.04.008 Documentation 1w Wed 3/8/23 Tue 3/14/23
94 PS1.05 Building Fire Systems 11 w Thu 3/31/22 Mon 6/20/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 3
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
95 PS1.05.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
96 PS1.05.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
97 PS1.05.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
98 PS1.05.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
99 PS1.05.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
100 PS1.06 Networking 32.8 w Thu 3/31/22 Thu 11/24/22
101 PS1.06.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
102 PS1.06.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
103 PS1.06.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
104 PS1.06.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
105 PS1.06.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
106 PS1.06.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
107 PS1.06.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
108 PS1.06.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
109 PS1.06.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
110 PS1.06.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
111 PS1.06.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
112 PS1.06.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
113 PS1.06.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
114 PS1.06.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
115 PS1.06.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
116 PS1.06.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
117 PS1.06.006 Documentation 2d Wed 11/23/22 Thu 11/24/22
118 PS1.07 Telecommunications 32.8 w Thu 3/31/22 Thu 11/24/22
119 PS1.07.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
120 PS1.07.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
121 PS1.07.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
122 PS1.07.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
123 PS1.07.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
124 PS1.07.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
125 PS1.07.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
126 PS1.07.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 4
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
127 PS1.07.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
128 PS1.07.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
129 PS1.07.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
130 PS1.07.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
131 PS1.07.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
132 PS1.07.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
133 PS1.07.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
134 PS1.07.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
135 PS1.07.006 Documentation 2d Wed 11/23/22 Thu 11/24/22
136 PS1.08 Process Instrumentation 34.6 w Thu 3/31/22 Wed 12/7/22
137 PS1.08.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
138 PS1.08.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
139 PS1.08.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
140 PS1.08.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
141 PS1.08.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
142 PS1.08.002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
143 PS1.08.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
144 PS1.08.002.0002 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
145 PS1.08.002.0003 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
146 PS1.08.003 Transportation 1w Fri 11/4/22 Thu 11/10/22
147 PS1.08.003.0001 Shipment 1w Fri 11/4/22 Thu 11/10/22
148 PS1.08.004 Installation 0.4 w Wed 11/16/22 Thu 11/17/22
149 PS1.08.004.0001 Installation supervision 2d Wed 11/16/22 Thu 11/17/22
150 PS1.08.005 Site Services 0.8 w Mon 11/28/22 Thu 12/1/22
151 PS1.08.005.0001 SAT 1.75 d Mon 11/28/22 Tue 11/29/22
152 PS1.08.005.0002 Commissioning 1.75 d Tue 11/29/22 Thu 12/1/22
153 PS1.08.005.0003 Start-up 0.5 d Thu 12/1/22 Thu 12/1/22
154 PS1.08.006 Documentation 1d Wed 12/7/22 Wed 12/7/22
155 PS1.09 Automated valves 60.4 w Thu 3/31/22 Tue 6/13/23
156 PS1.09.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
157 PS1.09.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
158 PS1.09.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 5
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
159 PS1.09.001.0003 Engineering Development 4 w Mon 4/18/22 Mon 5/16/22
160 PS1.09.001.0004 Approval 3 w Tue 5/17/22 Mon 6/6/22
161 PS1.09.002 Manufacturing 47.2 w Tue 6/7/22 Mon 5/15/23
162 PS1.09.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
163 PS1.09.002.0002 Manufacturing 39.2 w Tue 6/28/22 Wed 4/5/23
164 PS1.09.002.0002.1 Motor Operated Valves 39.2 w Tue 6/28/22 Wed 4/5/23
(MOV's)
167 PS1.09.002.0002.2 Shutdown Valves (SDV's) 22.4 w Tue 6/28/22 Tue 12/6/22
170 PS1.09.002.0003 Transfers / Import 4w Mon 4/10/23 Mon 5/8/23
171 PS1.09.002.0004 Integration 1w Tue 5/9/23 Mon 5/15/23
172 PS1.09.003 Factory Testing 1w Mon 5/15/23 Fri 5/19/23
173 PS1.09.003.0001 FAT 1w Mon 5/15/23 Fri 5/19/23
174 PS1.09.004 Transportation 2w Mon 5/15/23 Fri 5/26/23
175 PS1.09.004.0001 Shipment 2w Mon 5/15/23 Fri 5/26/23
176 PS1.09.005 Installation 0.6 w Thu 6/1/23 Mon 6/5/23
177 PS1.09.005.0001 Installation supervision 3d Thu 6/1/23 Mon 6/5/23
178 PS1.09.006 Documentation 1d Tue 6/13/23 Tue 6/13/23
179 PS1.10 Metering Skids 45.2 w Thu 3/31/22 Tue 2/21/23
180 PS1.10.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
181 PS1.10.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
182 PS1.10.001.0002 Freeze Inf 1w Tue 4/5/22 Mon 4/11/22
183 PS1.10.001.0003 Engineering Development 7.4 w Tue 4/12/22 Mon 6/6/22
184 PS1.10.001.0004 Approval 3.2 w Mon 5/16/22 Mon 6/6/22
185 PS1.10.002 Manufacturing 33.2 w Mon 5/16/22 Fri 1/6/23
186 PS1.10.002.0001 Procurement 30.6 w Mon 5/16/22 Tue 12/20/22
187 PS1.10.002.0002 Manufacturing 7w Tue 7/12/22 Mon 8/29/22
188 PS1.10.002.0003 Transfers / Import 25 w Tue 7/5/22 Fri 12/30/22
189 PS1.10.002.0004 Integration 17 w Tue 9/6/22 Fri 1/6/23
190 PS1.10.003 Factory Testing 0.6 w Mon 1/9/23 Wed 1/11/23
191 PS1.10.003.0001 FAT 0.6 w Mon 1/9/23 Wed 1/11/23
192 PS1.10.004 Transportation 1w Tue 1/17/23 Mon 1/23/23
193 PS1.10.004.0001 Shipment 5d Tue 1/17/23 Mon 1/23/23
194 PS1.10.005 Installation 0.4 w Fri 1/27/23 Mon 1/30/23
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 6
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
195 PS1.10.005.0001 Installation supervision 2d Fri 1/27/23 Mon 1/30/23
196 PS1.10.006 Site Services 1.2 w Wed 2/8/23 Wed 2/15/23
197 PS1.10.006.0001 SAT 2d Wed 2/8/23 Thu 2/9/23
198 PS1.10.006.0002 Commissioning 2d Fri 2/10/23 Mon 2/13/23
199 PS1.10.006.0003 Start-up 2d Tue 2/14/23 Wed 2/15/23
200 PS1.10.007 Documentation 15 w Mon 11/7/22 Tue 2/21/23
201 PS1.11 Security System 30.7 w Thu 3/31/22 Wed 11/9/22
202 PS1.11.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
203 PS1.11.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
204 PS1.11.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
205 PS1.11.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
206 PS1.11.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
207 PS1.11.002 Manufacturing 17 w Tue 6/7/22 Wed 10/5/22
208 PS1.11.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
209 PS1.11.002.0002 Manufacturing 12 w Tue 6/28/22 Wed 9/21/22
210 PS1.11.002.0003 Transfers / Import 2w Thu 9/22/22 Wed 10/5/22
211 PS1.11.003 Transportation 1w Thu 10/6/22 Wed 10/12/22
212 PS1.11.003.0001 Shipment 5d Thu 10/6/22 Wed 10/12/22
213 PS1.11.004 Installation 0.2 w Tue 10/18/22 Tue 10/18/22
214 PS1.11.004.0001 Installation supervision 1d Tue 10/18/22 Tue 10/18/22
215 PS1.11.005 Site Services 1.1 w Wed 10/26/22 Thu 11/3/22
216 PS1.11.005.0001 Commissioning and testing 5d Wed 10/26/22 Wed 11/2/22
217 PS1.11.005.0002 Start-up 0.5 d Thu 11/3/22 Thu 11/3/22
218 PS1.11.006 Documentation 2d Mon 11/7/22 Wed 11/9/22
219 PS1.12 PAGA 44 w Thu 3/31/22 Mon 2/13/23
220 PS1.12.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
221 PS1.12.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
222 PS1.12.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
223 PS1.12.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
224 PS1.12.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
225 PS1.12.002 Manufacturing 30 w Tue 6/21/22 Fri 1/20/23
226 PS1.12.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 7
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
227 PS1.12.002.0002 Manufacturing 25 w Tue 7/12/22 Fri 1/6/23
228 PS1.12.002.0003 Transfers / Import 2w Mon 1/9/23 Fri 1/20/23
229 PS1.12.003 Transportation 1w Mon 1/23/23 Fri 1/27/23
230 PS1.12.003.0001 Shipment 1w Mon 1/23/23 Fri 1/27/23
231 PS1.12.004 Installation 0.2 w Thu 2/2/23 Thu 2/2/23
232 PS1.12.004.0001 Installation supervision 1d Thu 2/2/23 Thu 2/2/23
233 PS1.12.006 Documentation 1d Mon 2/13/23 Mon 2/13/23
234 PS2 Tuxpan Terminal 64 w Thu 3/31/22 Fri 7/7/23
235 PS2.01 Terminal Management System 59 w Thu 3/31/22 Fri 6/2/23
236 PS2.01.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
237 PS2.01.001.0001 Inf Requirements - FEED 2w Thu 3/31/22 Wed 4/13/22
238 PS2.01.001.0002 Freeze Inf 1w Mon 4/18/22 Fri 4/22/22
239 PS2.01.001.0003 Functional Design Development 3w Mon 4/25/22 Mon 5/16/22
240 PS2.01.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
241 PS2.01.002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
242 PS2.01.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
243 PS2.01.002.0002 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
244 PS2.01.002.0003 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
245 PS2.01.003 Factory Testing 1w Thu 11/3/22 Wed 11/9/22
246 PS2.01.003.0001 FAT 1w Thu 11/3/22 Wed 11/9/22
247 PS2.01.004 Transportation 0.4 w Fri 11/11/22 Mon 11/14/22
248 PS2.01.004.0001 Shipment 2d Fri 11/11/22 Mon 11/14/22
249 PS2.01.005 Installation 1w Fri 11/18/22 Fri 11/25/22
250 PS2.01.005.0001 Installation supervision 1w Fri 11/18/22 Fri 11/25/22
251 PS2.01.006 Site Services 1w Tue 5/23/23 Mon 5/29/23
252 PS2.01.006.0001 SAT 3d Tue 5/23/23 Thu 5/25/23
253 PS2.01.006.0002 Commissioning 1d Fri 5/26/23 Fri 5/26/23
254 PS2.01.006.0003 Start-up 1d Mon 5/29/23 Mon 5/29/23
255 PS2.01.007 Training 3d Mon 11/28/22 Wed 11/30/22
256 PS2.01.008 Documentation 1w Mon 5/29/23 Fri 6/2/23
257 PS2.02 Process Control System 59 w Thu 3/31/22 Fri 6/2/23
258 PS2.02.001 Engineering 9w Thu 3/31/22 Mon 6/6/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 8
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
259 PS2.02.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
260 PS2.02.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
261 PS2.02.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
262 PS2.02.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
263 PS2.02.002 Configuration 14 w Tue 6/7/22 Mon 9/12/22
264 PS2.02.002.0001 Configuration 14 w Tue 6/7/22 Mon 9/12/22
265 PS2.02.003 Manufacturing 32 w Tue 6/7/22 Fri 1/20/23
266 PS2.02.003.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
267 PS2.02.003.0002 Manufacturing 26 w Tue 6/28/22 Fri 12/30/22
268 PS2.02.003.0003 Transfers / Import 2w Mon 1/2/23 Fri 1/13/23
269 PS2.02.003.0004 Integration 3w Mon 1/2/23 Fri 1/20/23
270 PS2.02.004 Factory Testing 4w Wed 1/25/23 Wed 2/22/23
271 PS2.02.004.0001 FIT 1w Wed 1/25/23 Tue 1/31/23
272 PS2.02.004.0002 FAT 3w Wed 2/1/23 Wed 2/22/23
273 PS2.02.005 Transportation 1w Tue 2/21/23 Mon 2/27/23
274 PS2.02.005.0001 Shipment 1w Tue 2/21/23 Mon 2/27/23
275 PS2.02.006 Installation 0.6 w Fri 3/3/23 Tue 3/7/23
276 PS2.02.006.0001 Installation supervision 3d Fri 3/3/23 Tue 3/7/23
277 PS2.02.007 Site Services 10 w Wed 3/15/23 Mon 5/29/23
278 PS2.02.007.0001 SAT 1w Wed 3/15/23 Wed 3/22/23
279 PS2.02.007.0002 Commissioning 8w Thu 3/23/23 Mon 5/22/23
280 PS2.02.007.0003 Start-up 1w Tue 5/23/23 Mon 5/29/23
281 PS2.02.008 Training 5d Wed 3/8/23 Tue 3/14/23
282 PS2.02.009 Documentation 1w Mon 5/29/23 Fri 6/2/23
283 PS2.03 Safety Instrumented System 61.1 w Thu 3/31/22 Mon 6/19/23
284 PS2.03.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
285 PS2.03.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
286 PS2.03.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
287 PS2.03.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
288 PS2.03.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
289 PS2.03.002 Configuration 16 w Tue 6/7/22 Wed 9/28/22
290 PS2.03.002.0001 Configuration 16 w Tue 6/7/22 Wed 9/28/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 9
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
291 PS2.03.003 Manufacturing 32 w Tue 6/7/22 Fri 1/20/23
292 PS2.03.003.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
293 PS2.03.003.0002 Manufacturing 26 w Tue 6/28/22 Fri 12/30/22
294 PS2.03.003.0003 Transfers / Import 2w Mon 1/2/23 Fri 1/13/23
295 PS2.03.003.0004 Integration 3w Mon 1/2/23 Fri 1/20/23
296 PS2.03.004 Factory Testing 4w Tue 2/7/23 Mon 3/6/23
297 PS2.03.004.0001 FIT 1w Tue 2/7/23 Mon 2/13/23
298 PS2.03.004.0002 FAT 3w Tue 2/14/23 Mon 3/6/23
299 PS2.03.005 Transportation 1w Fri 3/3/23 Thu 3/9/23
300 PS2.03.005.0001 Shipment 1w Fri 3/3/23 Thu 3/9/23
301 PS2.03.006 Installation 0.4 w Wed 3/15/23 Thu 3/16/23
302 PS2.03.006.0001 Installation supervision 2d Wed 3/15/23 Thu 3/16/23
303 PS2.03.007 Site Services 9.5 w Mon 3/27/23 Mon 6/5/23
304 PS2.03.007.0001 SAT 1w Mon 3/27/23 Fri 3/31/23
305 PS2.03.007.0002 Commissioning 7.5 w Mon 4/3/23 Mon 5/29/23
306 PS2.03.007.0003 Start-up 1w Mon 5/29/23 Mon 6/5/23
307 PS2.03.008 Training 5d Fri 3/17/23 Fri 3/24/23
308 PS2.03.009 Documentation 1w Mon 6/12/23 Mon 6/19/23
309 PS2.04 Fire & Gas System 60.2 w Thu 3/31/22 Mon 6/12/23
310 PS2.04.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
311 PS2.04.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
312 PS2.04.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
313 PS2.04.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
314 PS2.04.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
315 PS2.04.002 Configuration 16 w Tue 6/21/22 Wed 10/12/22
316 PS2.04.002.0001 Configuration 16 w Tue 6/21/22 Wed 10/12/22
317 PS2.04.003 Manufacturing 32 w Tue 6/21/22 Fri 2/3/23
318 PS2.04.003.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
319 PS2.04.003.0002 Manufacturing 26 w Tue 7/12/22 Fri 1/13/23
320 PS2.04.003.0005 Manufacturing and delivery 14 w Tue 7/12/22 Wed 10/19/22
F&G Instrumentation
321 PS2.04.003.0003 Transfers / Import 2 w Mon 1/16/23 Fri 1/27/23
322 PS2.04.003.0004 Integration 3 w Mon 1/16/23 Fri 2/3/23
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 10
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
323 PS2.04.004 Factory Testing 4w Tue 2/7/23 Mon 3/6/23
324 PS2.04.004.0001 FIT 1w Tue 2/7/23 Mon 2/13/23
325 PS2.04.004.0002 FAT 3w Tue 2/14/23 Mon 3/6/23
326 PS2.04.005 Transportation 1w Fri 3/3/23 Thu 3/9/23
327 PS2.04.005.0001 Shipment 1w Fri 3/3/23 Thu 3/9/23
328 PS2.04.006 Installation 0.4 w Wed 3/15/23 Thu 3/16/23
329 PS2.04.006.0001 Installation supervision 2d Wed 3/15/23 Thu 3/16/23
330 PS2.04.007 Site Services 9.6 w Mon 3/27/23 Mon 6/5/23
331 PS2.04.007.0001 SAT 1w Mon 3/27/23 Fri 3/31/23
332 PS2.04.007.0002 Commissioning 7.5 w Mon 4/3/23 Mon 5/29/23
333 PS2.04.007.0004 Commissioning F&G 16 d Mon 5/8/23 Mon 5/29/23
Instrumentation
334 PS2.04.007.0003 Start-up 1 w Tue 5/30/23 Mon 6/5/23
335 PS2.04.008 Documentation 1w Tue 6/6/23 Mon 6/12/23
336 PS2.05 Building Fire Systems 27.2 w Thu 3/31/22 Thu 10/13/22
337 PS2.05.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
338 PS2.05.001.0001 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
339 PS2.05.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
340 PS2.05.001.0003 Engineering Development 6 w Mon 4/18/22 Mon 5/30/22
341 PS2.05.001.0004 Approval 3 w Tue 5/31/22 Mon 6/20/22
342 PS2.05.002 Manufacturing 13 w Tue 6/21/22 Wed 9/21/22
343 PS2.05.002.0001 Procurement 3 w Tue 6/21/22 Mon 7/11/22
344 PS2.05.002.0002 Manufacturing 8 w Tue 7/12/22 Mon 9/5/22
345 PS2.05.002.0003 Transfers / Import 2w Tue 9/6/22 Wed 9/21/22
346 PS2.05.003 Transportation 1 w Thu 9/22/22 Wed 9/28/22
347 PS2.05.003.0001 Shipment 1 w Thu 9/22/22 Wed 9/28/22
348 PS2.05.004 Installation 0.2 w Tue 10/4/22 Tue 10/4/22
349 PS2.05.004.0001 Installation supervision 1 d Tue 10/4/22 Tue 10/4/22
350 PS2.05.005 Training 3 d Wed 10/5/22 Fri 10/7/22
351 PS2.05.006 Documentation 2 d Wed 10/12/22 Thu 10/13/22
352 PS2.06 Networking 32.8 w Thu 3/31/22 Thu 11/24/22
353 PS2.06.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
354 PS2.06.001.0001 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 11
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
355 PS2.06.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
356 PS2.06.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
357 PS2.06.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
358 PS2.06.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
359 PS2.06.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
360 PS2.06.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
361 PS2.06.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
362 PS2.06.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
363 PS2.06.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
364 PS2.06.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
365 PS2.06.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
366 PS2.06.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
367 PS2.06.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
368 PS2.06.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
369 PS2.06.006 Training 3d Tue 11/22/22 Thu 11/24/22
370 PS2.06.007 Documentation 2d Wed 11/23/22 Thu 11/24/22
371 PS2.07 Telecommunications 33.4 w Thu 3/31/22 Tue 11/29/22
372 PS2.07.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
373 PS2.07.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
374 PS2.07.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
375 PS2.07.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
376 PS2.07.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
377 PS2.07.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
378 PS2.07.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
379 PS2.07.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
380 PS2.07.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
381 PS2.07.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
382 PS2.07.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
383 PS2.07.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
384 PS2.07.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
385 PS2.07.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
386 PS2.07.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 12
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
387 PS2.07.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
388 PS2.07.006 Training 3d Fri 11/18/22 Wed 11/23/22
389 PS2.07.007 Documentation 2d Mon 11/28/22 Tue 11/29/22
390 PS2.08 Radio Backup System 32.8 w Thu 3/31/22 Thu 11/24/22
391 PS2.08.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
392 PS2.08.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
393 PS2.08.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
394 PS2.08.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
395 PS2.08.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
396 PS2.08.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
397 PS2.08.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
398 PS2.08.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
399 PS2.08.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
400 PS2.08.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
401 PS2.08.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
402 PS2.08.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
403 PS2.08.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
404 PS2.08.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
405 PS2.08.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
406 PS2.08.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
407 PS2.08.006 Training 1d Fri 11/18/22 Fri 11/18/22
408 PS2.08.007 Documentation 2d Wed 11/23/22 Thu 11/24/22
409 PS2.09 Tank Gauging System 38.2 w Thu 3/31/22 Mon 1/2/23
410 PS2.09.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
411 PS2.09.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
412 PS2.09.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
413 PS2.09.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
414 PS2.09.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
415 PS2.09.002 Manufacturing 23 w Tue 6/7/22 Thu 11/17/22
416 PS2.09.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
417 PS2.09.002.0002 Manufacturing 18 w Tue 6/28/22 Thu 11/3/22
418 PS2.09.002.0003 Transfers / Import 2w Fri 11/4/22 Thu 11/17/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 13
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
419 PS2.09.003 Transportation 1w Fri 11/18/22 Fri 11/25/22
420 PS2.09.003.0001 Shipment 1w Fri 11/18/22 Fri 11/25/22
421 PS2.09.004 Installation 0.6 w Thu 12/1/22 Mon 12/5/22
422 PS2.09.004.0001 Installation supervision 3d Thu 12/1/22 Mon 12/5/22
423 PS2.09.005 Site Services 2.2 w Tue 12/13/22 Tue 12/27/22
424 PS2.09.005.0001 SAT 3d Tue 12/13/22 Thu 12/15/22
425 PS2.09.005.0002 Commissioning 5d Fri 12/16/22 Thu 12/22/22
426 PS2.09.005.0003 Start-up 3d Fri 12/23/22 Tue 12/27/22
427 PS2.09.006 Training 5d Tue 12/6/22 Mon 12/12/22
428 PS2.09.007 Documentation 2d Fri 12/30/22 Mon 1/2/23
429 PS2.10 Process Instrumentation 37.5 w Thu 3/31/22 Wed 12/28/22
430 PS2.10.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
431 PS2.10.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
432 PS2.10.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
433 PS2.10.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
434 PS2.10.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
435 PS2.10.002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
436 PS2.10.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
437 PS2.10.002.0002 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
438 PS2.10.002.0003 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
439 PS2.10.003 Transportation 1w Fri 11/4/22 Thu 11/10/22
440 PS2.10.003.0001 Shipment 1w Fri 11/4/22 Thu 11/10/22
441 PS2.10.004 Installation 0.6 w Wed 11/16/22 Fri 11/18/22
442 PS2.10.004.0001 Installation supervision 3d Wed 11/16/22 Fri 11/18/22
443 PS2.10.005 Site Services 3.5 w Tue 11/29/22 Thu 12/22/22
444 PS2.10.005.0001 SAT 1.75 d Tue 11/29/22 Wed 11/30/22
445 PS2.10.005.0002 Commissioning 2.25 d Wed 11/30/22 Fri 12/2/22
446 PS2.10.005.0003 Start-up 0.5 d Thu 12/22/22 Thu 12/22/22
447 PS2.10.006 Training 5d Tue 11/22/22 Mon 11/28/22
448 PS2.10.007 Documentation 1d Tue 12/27/22 Wed 12/28/22
449 PS2.11 Automated valves 56.2 w Thu 3/31/22 Mon 5/15/23
450 PS2.11.001 Engineering 9w Thu 3/31/22 Mon 6/6/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 14
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
451 PS2.11.001.0001 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
452 PS2.11.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
453 PS2.11.001.0003 Engineering Development 4 w Mon 4/18/22 Mon 5/16/22
454 PS2.11.001.0004 Approval 3 w Tue 5/17/22 Mon 6/6/22
455 PS2.11.002 Manufacturing 45.2 w Tue 5/17/22 Wed 4/5/23
456 PS2.11.002.0001 Procurement 3 w Tue 5/17/22 Mon 6/6/22
457 PS2.11.002.0002 Manufacturing 39.2 w Tue 6/7/22 Tue 3/14/23
458 PS2.11.002.0002.1 Control Valves 39.2 w Tue 6/7/22 Tue 3/14/23
460 PS2.11.002.0002.2 Motor Operated Valves 39.2 w Tue 6/7/22 Tue 3/14/23
(MOV's)
463 PS2.11.002.0002.3 Shutdown Valves (SDV's) 22.4 w Tue 6/7/22 Mon 11/14/22
466 PS2.11.002.0003 Transfers / Import 2w Wed 3/15/23 Wed 3/29/23
467 PS2.11.002.0004 Integration 1w Thu 3/30/23 Wed 4/5/23
468 PS2.11.003 Factory Testing 2w Wed 3/29/23 Thu 4/13/23
469 PS2.11.003.0001 FAT 2w Wed 3/29/23 Thu 4/13/23
470 PS2.11.004 Transportation 1w Wed 4/12/23 Tue 4/18/23
471 PS2.11.004.0001 Shipment 1w Wed 4/12/23 Tue 4/18/23
472 PS2.11.005 Installation 1w Mon 4/24/23 Fri 4/28/23
473 PS2.11.005.0001 Installation supervision 1w Mon 4/24/23 Fri 4/28/23
474 PS2.11.006 Training 5d Tue 5/2/23 Mon 5/8/23
475 PS2.11.007 Documentation 1w Tue 5/9/23 Mon 5/15/23
476 PS2.12 Metering Skids 51.1 w Thu 3/31/22 Wed 4/5/23
477 PS2.12.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
478 PS2.12.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
479 PS2.12.001.0002 Freeze Inf 1w Tue 4/5/22 Mon 4/11/22
480 PS2.12.001.0003 Engineering Development 7.4 w Tue 4/12/22 Mon 6/6/22
481 PS2.12.001.0004 Approval 3.2 w Mon 5/16/22 Mon 6/6/22
482 PS2.12.002 Manufacturing 38.3 w Mon 5/16/22 Tue 2/14/23
483 PS2.12.002.0001 Procurement 35.4 w Mon 5/16/22 Mon 1/23/23
484 PS2.12.002.0002 Manufacturing 15 w Tue 7/12/22 Wed 10/26/22
485 PS2.12.002.0003 Transfers / Import 25 w Wed 8/3/22 Mon 1/30/23
486 PS2.12.002.0004 Integration 15.1 w Thu 10/27/22 Tue 2/14/23
487 PS2.12.003 Factory Testing 2w Fri 2/3/23 Mon 2/20/23
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 15
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
488 PS2.12.003.0001 FAT 2w Fri 2/3/23 Mon 2/20/23
489 PS2.12.004 Transportation 1.8 w Fri 2/10/23 Thu 2/23/23
490 PS2.12.004.0001 Shipment 9d Fri 2/10/23 Thu 2/23/23
491 PS2.12.005 Installation 0.8 w Tue 2/28/23 Mon 3/6/23
492 PS2.12.005.0001 Installation supervision 4d Tue 2/28/23 Mon 3/6/23
493 PS2.12.006 Site Services 2.4 w Mon 3/13/23 Thu 3/30/23
494 PS2.12.006.0001 SAT 4d Mon 3/13/23 Fri 3/17/23
495 PS2.12.006.0002 Commissioning 4d Fri 3/17/23 Fri 3/24/23
496 PS2.12.006.0003 Start-up 4d Fri 3/24/23 Thu 3/30/23
497 PS2.12.007 Training 3d Mon 3/6/23 Thu 3/9/23
498 PS2.12.008 Documentation 15 w Mon 12/19/22 Wed 4/5/23
499 PS2.13 Pipeline Leak Detection 19.4 w Thu 3/31/22 Wed 8/17/22
500 PS2.13.001 Engineering 9.4 w Thu 3/31/22 Wed 6/8/22
501 PS2.13.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
502 PS2.13.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
503 PS2.13.001.0003 Engineering Development 7.4 w Mon 4/18/22 Wed 6/8/22
504 PS2.13.001.0004 Approval 3w Thu 5/19/22 Wed 6/8/22
505 PS2.13.002 Configuration 4w Thu 6/9/22 Wed 7/6/22
506 PS2.13.002.0001 Configuration 4w Thu 6/9/22 Wed 7/6/22
507 PS2.13.003 Manufacturing 4w Thu 6/9/22 Wed 7/6/22
508 PS2.13.003.0001 Procurement 1w Thu 6/9/22 Wed 6/15/22
509 PS2.13.003.0002 Manufacturing 1w Thu 6/16/22 Wed 6/22/22
510 PS2.13.003.0003 Transfers / Import 2w Thu 6/23/22 Wed 7/6/22
511 PS2.13.004 Factory Testing 1w Thu 7/7/22 Wed 7/13/22
512 PS2.13.004.0001 FAT 1w Thu 7/7/22 Wed 7/13/22
513 PS2.13.005 Transportation 1w Tue 7/19/22 Mon 7/25/22
514 PS2.13.005.0001 Shipment 1w Tue 7/19/22 Mon 7/25/22
515 PS2.13.006 Installation 0.4 w Fri 7/29/22 Mon 8/1/22
516 PS2.13.006.0001 Installation supervision 2d Fri 7/29/22 Mon 8/1/22
517 PS2.13.007 Site Services 0.6 w Tue 8/9/22 Thu 8/11/22
518 PS2.13.007.0001 SAT 1d Tue 8/9/22 Tue 8/9/22
519 PS2.13.007.0002 Commissioning 1d Wed 8/10/22 Wed 8/10/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 16
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
520 PS2.13.007.0003 Start-up 1d Thu 8/11/22 Thu 8/11/22
521 PS2.13.008 Training 3d Tue 8/2/22 Thu 8/4/22
522 PS2.13.009 Documentation 1w Thu 8/11/22 Wed 8/17/22
523 PS2.14 Security System 31.2 w Thu 3/31/22 Fri 11/11/22
524 PS2.14.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
525 PS2.14.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
526 PS2.14.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
527 PS2.14.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
528 PS2.14.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
529 PS2.14.002 Manufacturing 17 w Tue 6/7/22 Wed 10/5/22
530 PS2.14.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
531 PS2.14.002.0002 Manufacturing 12 w Tue 6/28/22 Wed 9/21/22
532 PS2.14.002.0003 Transfers / Import 2w Thu 9/22/22 Wed 10/5/22
533 PS2.14.003 Transportation 1w Thu 10/6/22 Wed 10/12/22
534 PS2.14.003.0001 Shipment 1w Thu 10/6/22 Wed 10/12/22
535 PS2.14.004 Installation 0.2 w Tue 10/18/22 Tue 10/18/22
536 PS2.14.004.0001 Installation supervision 1d Tue 10/18/22 Tue 10/18/22
537 PS2.14.005 Site Services 1.8 w Wed 10/26/22 Tue 11/8/22
538 PS2.14.005.0001 Commissioning and testing 5.5 d Wed 10/26/22 Thu 11/3/22
539 PS2.14.005.0002 Start-up 0.5 d Thu 11/3/22 Thu 11/3/22
540 PS2.14.005.0003 Training 3d Fri 11/4/22 Tue 11/8/22
541 PS2.14.006 Documentation 2d Thu 11/10/22 Fri 11/11/22
542 PS2.15 Emissions Monitoring 64 w Thu 3/31/22 Fri 7/7/23
543 PS2.15.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
544 PS2.15.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
545 PS2.15.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
546 PS2.15.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
547 PS2.15.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
548 PS2.15.002 Manufacturing 49 w Tue 6/7/22 Fri 5/26/23
549 PS2.15.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
550 PS2.15.002.0002 Manufacturing 44 w Tue 6/28/22 Fri 5/12/23
551 PS2.15.002.0003 Transfers / Import 2w Mon 5/15/23 Fri 5/26/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 17
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
552 PS2.15.003 Factory Testing 0.4 w Mon 5/29/23 Tue 5/30/23
553 PS2.15.003.0001 FAT 2d Mon 5/29/23 Tue 5/30/23
554 PS2.15.004 Transportation 1w Mon 6/5/23 Fri 6/9/23
555 PS2.15.004.0001 Shipment 5d Mon 6/5/23 Fri 6/9/23
556 PS2.15.005 Installation 0.4 w Thu 6/15/23 Fri 6/16/23
557 PS2.15.005.0001 Installation supervision 2d Thu 6/15/23 Fri 6/16/23
558 PS2.15.006 Site Services 1.2 w Mon 6/26/23 Mon 7/3/23
559 PS2.15.006.0001 SAT 2d Mon 6/26/23 Tue 6/27/23
560 PS2.15.006.0002 Commissioning 2d Wed 6/28/23 Thu 6/29/23
561 PS2.15.006.0003 Start-up 2d Fri 6/30/23 Mon 7/3/23
562 PS2.15.007 Training 2d Mon 6/19/23 Tue 6/20/23
563 PS2.15.008 Documentation 1w Mon 7/3/23 Fri 7/7/23
564 PS2.16 PAGA 43.6 w Thu 3/31/22 Thu 2/9/23
565 PS2.16.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
566 PS2.16.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
567 PS2.16.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
568 PS2.16.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
569 PS2.16.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
570 PS2.16.002 Manufacturing 30 w Tue 6/21/22 Fri 1/20/23
571 PS2.16.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
572 PS2.16.002.0002 Manufacturing 25 w Tue 7/12/22 Fri 1/6/23
573 PS2.16.002.0003 Transfers / Import 2w Mon 1/9/23 Fri 1/20/23
574 PS2.16.003 Transportation 1w Mon 1/23/23 Fri 1/27/23
575 PS2.16.003.0001 Shipment 1w Mon 1/23/23 Fri 1/27/23
576 PS2.16.004 Installation 0.2 w Thu 2/2/23 Thu 2/2/23
577 PS2.16.004.0001 Installation supervision 1d Thu 2/2/23 Thu 2/2/23
578 PS2.16.006 Training 3d Fri 2/3/23 Wed 2/8/23
579 PS2.16.007 Documentation 1d Thu 2/9/23 Thu 2/9/23
580 PS3 Hidalgo Terminal 79 w Thu 3/31/22 Fri 10/20/23
581 PS3.01 Terminal Management System 79 w Thu 3/31/22 Fri 10/20/23
582 PS3.01.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
583 PS3.01.001.0001 Inf Requirements - FEED 2w Thu 3/31/22 Wed 4/13/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 18
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
584 PS3.01.001.0002 Freeze Inf 1w Mon 4/18/22 Fri 4/22/22
585 PS3.01.001.0003 Functional Design Development 3w Mon 4/25/22 Mon 5/16/22
586 PS3.01.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
587 PS3.01.002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
588 PS3.01.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
589 PS3.01.002.0002 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
590 PS3.01.002.0003 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
591 PS3.01.003 Factory Testing 1w Thu 11/3/22 Wed 11/9/22
592 PS3.01.003.0001 FAT 1w Thu 11/3/22 Wed 11/9/22
593 PS3.01.004 Transportation 1w Tue 11/8/22 Mon 11/14/22
594 PS3.01.004.0001 Shipment 1w Tue 11/8/22 Mon 11/14/22
595 PS3.01.005 Installation 1w Fri 11/18/22 Fri 11/25/22
596 PS3.01.005.0001 Installation supervision 1w Fri 11/18/22 Fri 11/25/22
597 PS3.01.006 Site Services 1w Tue 10/10/23 Mon 10/16/23
598 PS3.01.006.0001 SAT 3d Tue 10/10/23 Thu 10/12/23
599 PS3.01.006.0002 Commissioning 1d Fri 10/13/23 Fri 10/13/23
600 PS3.01.006.0003 Start-up 1d Mon 10/16/23 Mon 10/16/23
601 PS3.01.007 Training 3d Mon 11/28/22 Wed 11/30/22
602 PS3.01.008 Documentation 1w Mon 10/16/23 Fri 10/20/23
603 PS3.02 Process Control System 79 w Thu 3/31/22 Fri 10/20/23
604 PS3.02.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
605 PS3.02.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
606 PS3.02.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
607 PS3.02.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
608 PS3.02.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
609 PS3.02.002 Configuration 20 w Tue 6/7/22 Wed 10/26/22
610 PS3.02.002.0001 Configuration 20 w Tue 6/7/22 Wed 10/26/22
611 PS3.02.003 Manufacturing 34 w Thu 10/27/22 Fri 6/30/23
612 PS3.02.003.0001 Procurement 3w Thu 10/27/22 Thu 11/17/22
613 PS3.02.003.0002 Manufacturing 26 w Fri 11/18/22 Fri 5/26/23
614 PS3.02.003.0003 Transfers / Import 2w Mon 5/29/23 Fri 6/9/23
615 PS3.02.003.0004 Integration 5w Mon 5/29/23 Fri 6/30/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 19
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
616 PS3.02.004 Factory Testing 4w Wed 7/5/23 Tue 8/1/23
617 PS3.02.004.0001 FIT 1w Wed 7/5/23 Tue 7/11/23
618 PS3.02.004.0002 FAT 3w Wed 7/12/23 Tue 8/1/23
619 PS3.02.005 Transportation 1w Mon 7/31/23 Fri 8/4/23
620 PS3.02.005.0001 Shipment 1w Mon 7/31/23 Fri 8/4/23
621 PS3.02.006 Installation 0.6 w Thu 8/10/23 Mon 8/14/23
622 PS3.02.006.0001 Installation supervision 3d Thu 8/10/23 Mon 8/14/23
623 PS3.02.007 Site Services 8w Tue 8/22/23 Mon 10/16/23
624 PS3.02.007.0001 SAT 1w Tue 8/22/23 Mon 8/28/23
625 PS3.02.007.0002 Commissioning 6w Tue 8/29/23 Mon 10/9/23
626 PS3.02.007.0003 Start-up 1w Tue 10/10/23 Mon 10/16/23
627 PS3.02.009 Training 1w Tue 8/15/23 Mon 8/21/23
628 PS3.02.008 Documentation 1w Mon 10/16/23 Fri 10/20/23
629 PS3.03 Safety Instrumented System 68.6 w Thu 3/31/22 Wed 8/9/23
630 PS3.03.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
631 PS3.03.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
632 PS3.03.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
633 PS3.03.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
634 PS3.03.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
635 PS3.03.002 Configuration 20 w Tue 6/21/22 Thu 11/10/22
636 PS3.03.002.0001 Configuration 20 w Tue 6/21/22 Thu 11/10/22
637 PS3.03.003 Manufacturing 34 w Tue 6/21/22 Mon 2/20/23
638 PS3.03.003.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
639 PS3.03.003.0002 Manufacturing 26 w Tue 7/12/22 Fri 1/13/23
640 PS3.03.003.0005 Manufacturing and delivery 14 w Tue 7/12/22 Wed 10/19/22
F&G Instrumentation
641 PS3.03.003.0003 Transfers / Import 2w Mon 1/16/23 Fri 1/27/23
642 PS3.03.003.0004 Integration 5w Mon 1/16/23 Mon 2/20/23
643 PS3.03.004 Factory Testing 3w Wed 2/15/23 Tue 3/7/23
644 PS3.03.004.0001 FIT 1w Thu 2/23/23 Wed 3/1/23
645 PS3.03.004.0002 FAT 3w Wed 2/15/23 Tue 3/7/23
646 PS3.03.005 Transportation 1w Mon 3/6/23 Fri 3/10/23
647 PS3.03.005.0001 Shipment 1w Mon 3/6/23 Fri 3/10/23
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 20
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
648 PS3.03.006 Installation 0.4 w Thu 3/16/23 Fri 3/17/23
649 PS3.03.006.0001 Installation supervision 0.4 w Thu 3/16/23 Fri 3/17/23
650 PS3.03.007 Site Services 18 w Tue 3/28/23 Thu 8/3/23
651 PS3.03.007.0001 SAT 1 w Tue 3/28/23 Mon 4/3/23
652 PS3.03.007.0002 Commissioning 6w Tue 4/4/23 Thu 5/18/23
653 PS3.03.007.0005 Commissioning F&G 5.6 w Tue 6/20/23 Thu 7/27/23
Instrumentation
654 PS3.03.007.0003 Start-up 1w Fri 7/28/23 Thu 8/3/23
655 PS3.03.009 Training 1 w Tue 3/21/23 Mon 3/27/23
656 PS3.03.008 Documentation 1w Thu 8/3/23 Wed 8/9/23
657 PS3.04 Fire & Gas System 61.2 w Thu 3/31/22 Mon 6/19/23
658 PS3.04.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
659 PS3.04.001.0001 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
660 PS3.04.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
661 PS3.04.001.0003 Engineering Development 6 w Mon 4/18/22 Mon 5/30/22
662 PS3.04.001.0004 Approval 3 w Tue 5/31/22 Mon 6/20/22
663 PS3.04.002 Configuration 20 w Tue 6/21/22 Thu 11/10/22
664 PS3.04.002.0001 Configuration 20 w Tue 6/21/22 Thu 11/10/22
665 PS3.04.003 Manufacturing 36 w Tue 6/21/22 Mon 3/6/23
666 PS3.04.003.0001 Procurement 3 w Tue 6/21/22 Mon 7/11/22
667 PS3.04.003.0002 Manufacturing 26 w Tue 7/12/22 Fri 1/13/23
668 PS3.04.003.0005 Manufacturing and delivery F&G Instrumentation
14 w Tue 7/12/22 Wed 10/19/22
669 PS3.04.003.0003 Transfers / Import 2 w Mon 1/16/23 Fri 1/27/23
670 PS3.04.003.0004 Integration 5 w Mon 1/30/23 Mon 3/6/23
671 PS3.04.004 Factory Testing 3 w Wed 3/1/23 Wed 3/22/23
672 PS3.04.004.0001 FIT 1w Thu 3/9/23 Wed 3/15/23
673 PS3.04.004.0002 FAT 3 w Wed 3/1/23 Wed 3/22/23
674 PS3.04.005 Transportation 1 w Tue 3/21/23 Mon 3/27/23
675 PS3.04.005.0001 Shipment 1 w Tue 3/21/23 Mon 3/27/23
676 PS3.04.006 Installation 1w Fri 3/31/23 Mon 4/10/23
677 PS3.04.006.0001 Installation supervision 1w Fri 3/31/23 Mon 4/10/23
678 PS3.04.007 Site Services 8 w Tue 4/18/23 Tue 6/13/23
679 PS3.04.007.0001 SAT 1 w Tue 4/18/23 Mon 4/24/23
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 21
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
680 PS3.04.007.0002 Commissioning 6w Tue 4/25/23 Tue 6/6/23
681 PS3.04.007.0004 Commissioning F & G Instrumentation28 d Tue 4/25/23 Fri 6/2/23
682 PS3.04.007.0003 Start-up 1w Wed 6/7/23 Tue 6/13/23
683 PS3.04.008 Documentation 1w Tue 6/13/23 Mon 6/19/23
684 PS3.05 Building Fire Systems 27 w Thu 3/31/22 Wed 10/12/22
685 PS3.05.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
686 PS3.05.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
687 PS3.05.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
688 PS3.05.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
689 PS3.05.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
690 PS3.05.002 Manufacturing 13 w Tue 6/21/22 Wed 9/21/22
691 PS3.05.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
692 PS3.05.002.0002 Manufacturing 8w Tue 7/12/22 Mon 9/5/22
693 PS3.05.002.0003 Transfers / Import 2w Tue 9/6/22 Wed 9/21/22
694 PS3.05.003 Transportation 1w Thu 9/22/22 Wed 9/28/22
695 PS3.05.003.0001 Shipment 1w Thu 9/22/22 Wed 9/28/22
696 PS3.05.004 Installation 0.2 w Tue 10/4/22 Tue 10/4/22
697 PS3.05.004.0001 Installation supervision 1d Tue 10/4/22 Tue 10/4/22
698 PS3.05.006 Training 3d Thu 10/6/22 Mon 10/10/22
699 PS3.05.007 Documentation 2d Tue 10/11/22 Wed 10/12/22
700 PS3.06 Networking 32.8 w Thu 3/31/22 Thu 11/24/22
701 PS3.06.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
702 PS3.06.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
703 PS3.06.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
704 PS3.06.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
705 PS3.06.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
706 PS3.06.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
707 PS3.06.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
708 PS3.06.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
709 PS3.06.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
710 PS3.06.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
711 PS3.06.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 22
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
712 PS3.06.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
713 PS3.06.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
714 PS3.06.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
715 PS3.06.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
716 PS3.06.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
717 PS3.06.006 Training 3d Fri 11/4/22 Tue 11/8/22
718 PS3.06.007 Documentation 2d Wed 11/23/22 Thu 11/24/22
719 PS3.07 Telecommunications 32.8 w Thu 3/31/22 Thu 11/24/22
720 PS3.07.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
721 PS3.07.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
722 PS3.07.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
723 PS3.07.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
724 PS3.07.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
725 PS3.07.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
726 PS3.07.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
727 PS3.07.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
728 PS3.07.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
729 PS3.07.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
730 PS3.07.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
731 PS3.07.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
732 PS3.07.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
733 PS3.07.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
734 PS3.07.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
735 PS3.07.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
736 PS3.07.006 Training 3d Fri 11/4/22 Tue 11/8/22
737 PS3.07.007 Documentation 2d Wed 11/23/22 Thu 11/24/22
738 PS3.08 Radio Backup System 32.8 w Thu 3/31/22 Thu 11/24/22
739 PS3.08.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
740 PS3.08.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
741 PS3.08.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
742 PS3.08.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
743 PS3.08.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 23
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
744 PS3.08.002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
745 PS3.08.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
746 PS3.08.002.0002 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
747 PS3.08.002.0003 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
748 PS3.08.003 Transportation 1w Thu 10/20/22 Wed 10/26/22
749 PS3.08.003.0001 Shipment 1w Thu 10/20/22 Wed 10/26/22
750 PS3.08.004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
751 PS3.08.004.0001 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
752 PS3.08.005 Site Services 1w Fri 11/11/22 Thu 11/17/22
753 PS3.08.005.0001 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
754 PS3.08.005.0002 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
755 PS3.08.006 Training 1d Fri 11/4/22 Fri 11/4/22
756 PS3.08.007 Documentation 2d Wed 11/23/22 Thu 11/24/22
757 PS3.09 Tank Gauging System 38.2 w Thu 3/31/22 Mon 1/2/23
758 PS3.09.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
759 PS3.09.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
760 PS3.09.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
761 PS3.09.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
762 PS3.09.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
763 PS3.09.002 Manufacturing 23 w Tue 6/7/22 Thu 11/17/22
764 PS3.09.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
765 PS3.09.002.0002 Manufacturing 18 w Tue 6/28/22 Thu 11/3/22
766 PS3.09.002.0003 Transfers / Import 2w Fri 11/4/22 Thu 11/17/22
767 PS3.09.003 Transportation 1w Fri 11/18/22 Fri 11/25/22
768 PS3.09.003.0001 Shipment 1w Fri 11/18/22 Fri 11/25/22
769 PS3.09.004 Installation 0.6 w Thu 12/1/22 Mon 12/5/22
770 PS3.09.004.0001 Installation supervision 3d Thu 12/1/22 Mon 12/5/22
771 PS3.09.005 Site Services 2.2 w Tue 12/13/22 Tue 12/27/22
772 PS3.09.005.0001 SAT 3d Tue 12/13/22 Thu 12/15/22
773 PS3.09.005.0002 Commissioning 5d Fri 12/16/22 Thu 12/22/22
774 PS3.09.005.0003 Start-up 3d Fri 12/23/22 Tue 12/27/22
775 PS3.09.006 Training 5d Tue 12/6/22 Mon 12/12/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 24
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
776 PS3.09.007 Documentation 2d Fri 12/30/22 Mon 1/2/23
777 PS3.10 Process Instrumentation 34.6 w Thu 3/31/22 Wed 12/7/22
778 PS3.10.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
779 PS3.10.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
780 PS3.10.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
781 PS3.10.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
782 PS3.10.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
783 PS3.10.002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
784 PS3.10.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
785 PS3.10.002.0002 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
786 PS3.10.002.0003 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
787 PS3.10.003 Transportation 1w Fri 11/4/22 Thu 11/10/22
788 PS3.10.003.0001 Shipment 1w Fri 11/4/22 Thu 11/10/22
789 PS3.10.004 Installation 0.6 w Wed 11/16/22 Fri 11/18/22
790 PS3.10.004.0001 Installation supervision 3d Wed 11/16/22 Fri 11/18/22
791 PS3.10.005 Site Services 0.6 w Tue 11/29/22 Thu 12/1/22
792 PS3.10.005.0001 SAT 1.25 d Tue 11/29/22 Wed 11/30/22
793 PS3.10.005.0002 Commissioning 1.25 d Wed 11/30/22 Thu 12/1/22
794 PS3.10.005.0003 Start-up 0.5 d Thu 12/1/22 Thu 12/1/22
795 PS3.10.006 Documentation 1d Wed 12/7/22 Wed 12/7/22
796 PS3.11 Automated valves 59.2 w Thu 3/31/22 Mon 6/5/23
797 PS3.11.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
798 PS3.11.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
799 PS3.11.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
800 PS3.11.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
801 PS3.11.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
802 PS3.11.002 Manufacturing 45.2 w Tue 6/7/22 Fri 4/28/23
803 PS3.11.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
804 PS3.11.002.0002 Manufacturing 39.2 w Tue 6/28/22 Wed 4/5/23
805 PS3.11.002.0002.1 Control Valves 39.2 w Tue 6/28/22 Wed 4/5/23
807 PS3.11.002.0002.2 Motor Operated Valves 39.2 w Tue 6/28/22 Wed 4/5/23
(MOV's)
810 PS3.11.002.0002.3 Shutdown Valves (SDV's) 22.4 w Tue 6/28/22 Tue 12/6/22
Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 25
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
813 PS3.11.002.0003 Transfers / Import 2w Mon 4/10/23 Fri 4/21/23
814 PS3.11.002.0004 Integration 1w Mon 4/24/23 Fri 4/28/23
815 PS3.11.003 Factory Testing 2w Fri 4/21/23 Fri 5/5/23
816 PS3.11.003.0001 FAT 2w Fri 4/21/23 Fri 5/5/23
817 PS3.11.004 Transportation 1w Thu 5/4/23 Wed 5/10/23
818 PS3.11.004.0001 Shipment 1w Thu 5/4/23 Wed 5/10/23
819 PS3.11.005 Installation 1w Tue 5/16/23 Mon 5/22/23
820 PS3.11.005.0001 Installation supervision 1w Tue 5/16/23 Mon 5/22/23
821 PS3.11.006 Training 5d Tue 5/23/23 Mon 5/29/23
822 PS3.11.007 Documentation 1w Tue 5/30/23 Mon 6/5/23
823 PS3.12 Metering Skids 59.8 w Thu 3/31/22 Thu 6/8/23
824 PS3.12.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
825 PS3.12.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
826 PS3.12.001.0002 Freeze Inf 1w Tue 4/5/22 Mon 4/11/22
827 PS3.12.001.0003 Engineering Development 7.4 w Tue 4/12/22 Mon 6/6/22
828 PS3.12.001.0004 Approval 3.2 w Mon 5/16/22 Mon 6/6/22
829 PS3.12.002 Manufacturing 42.2 w Mon 5/16/22 Mon 3/13/23
830 PS3.12.002.0001 Procurement 36.1 w Mon 5/16/22 Fri 1/27/23
831 PS3.12.002.0002 Manufacturing 18 w Tue 7/12/22 Thu 11/17/22
832 PS3.12.002.0003 Transfers / Import 25 w Mon 8/8/22 Fri 2/3/23
833 PS3.12.002.0004 Integration 16 w Fri 11/18/22 Mon 3/13/23
834 PS3.12.003 Factory Testing 4w Wed 2/22/23 Wed 3/22/23
835 PS3.12.003.0001 FAT 4w Wed 2/22/23 Wed 3/22/23
836 PS3.12.004 Transportation 3.2 w Wed 3/8/23 Thu 3/30/23
837 PS3.12.004.0001 Shipment 16 d Wed 3/8/23 Thu 3/30/23
838 PS3.12.005 Installation 2w Wed 4/5/23 Thu 4/20/23
839 PS3.12.005.0001 Installation supervision 2w Wed 4/5/23 Thu 4/20/23
840 PS3.12.006 Site Services 5w Fri 4/28/23 Fri 6/2/23
841 PS3.12.006.0001 SAT 2w Fri 4/28/23 Fri 5/12/23
842 PS3.12.006.0002 Commissioning 1w Mon 5/15/23 Fri 5/19/23
843 PS3.12.006.0003 Start-up 2w Mon 5/22/23 Fri 6/2/23
844 PS3.12.007 Training 3d Fri 4/21/23 Tue 4/25/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 26
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
845 PS3.12.008 Documentation 20 w Fri 1/13/23 Thu 6/8/23
846 PS3.13 Pipeline Leak Detection 22.4 w Thu 3/31/22 Wed 9/7/22
847 PS3.13.001 Engineering 12.4 w Thu 3/31/22 Wed 6/29/22
848 PS3.13.001.0001 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
849 PS3.13.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
850 PS3.13.001.0003 Engineering Development 7.4 w Mon 4/18/22 Wed 6/8/22
851 PS3.13.001.0004 Approval 3w Thu 6/9/22 Wed 6/29/22
852 PS3.13.002 Manufacturing 4 w Thu 6/30/22 Wed 7/27/22
853 PS3.13.002.0001 Procurement 1 w Thu 6/30/22 Wed 7/6/22
854 PS3.13.002.0002 Manufacturing 1w Thu 7/7/22 Wed 7/13/22
855 PS3.13.002.0003 Transfers / Import 2 w Thu 7/14/22 Wed 7/27/22
856 PS3.13.003 Factory Testing 1 w Thu 7/28/22 Wed 8/3/22
857 PS3.13.003.0001 FAT 1 w Thu 7/28/22 Wed 8/3/22
858 PS3.13.004 Transportation 1w Tue 8/9/22 Mon 8/15/22
859 PS3.13.004.0001 Shipment 1w Tue 8/9/22 Mon 8/15/22
860 PS3.13.005 Installation 0.4 w Fri 8/19/22 Mon 8/22/22
861 PS3.13.005.0001 Installation supervision 2d Fri 8/19/22 Mon 8/22/22
862 PS3.13.006 Site Services 0.6 w Tue 8/30/22 Thu 9/1/22
863 PS3.13.006.0001 SAT 1 d Tue 8/30/22 Tue 8/30/22
864 PS3.13.006.0002 Commissioning 1 d Wed 8/31/22 Wed 8/31/22
865 PS3.13.006.0003 Start-up 1d Thu 9/1/22 Thu 9/1/22
866 PS3.13.007 Documentation 1w Thu 9/1/22 Wed 9/7/22
867 PS3.14 Security System 30.8 w Thu 3/31/22 Wed 11/9/22
868 PS3.14.001 Engineering 9 w Thu 3/31/22 Mon 6/6/22
869 PS3.14.001.0001 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
870 PS3.14.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
871 PS3.14.001.0003 Engineering Development 4 w Mon 4/18/22 Mon 5/16/22
872 PS3.14.001.0004 Approval 3 w Tue 5/17/22 Mon 6/6/22
873 PS3.14.002 Manufacturing 17 w Tue 6/7/22 Wed 10/5/22
874 PS3.14.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
875 PS3.14.002.0002 Manufacturing 12 w Tue 6/28/22 Wed 9/21/22
876 PS3.14.002.0003 Transfers / Import 2 w Thu 9/22/22 Wed 10/5/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 27
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
877 PS3.14.003 Transportation 1w Thu 10/6/22 Wed 10/12/22
878 PS3.14.003.0001 Shipment 1w Thu 10/6/22 Wed 10/12/22
879 PS3.14.004 Installation 0.2 w Tue 10/18/22 Tue 10/18/22
880 PS3.14.004.0001 Installation supervision 1d Tue 10/18/22 Tue 10/18/22
881 PS3.14.005 Site Services 1.2 w Wed 10/26/22 Thu 11/3/22
882 PS3.14.005.0001 Commissioning and testing 5.5 d Wed 10/26/22 Thu 11/3/22
883 PS3.14.005.0002 Start-up 0.5 d Thu 11/3/22 Thu 11/3/22
884 PS3.14.006 Training 3d Wed 10/19/22 Fri 10/21/22
885 PS3.14.007 Documentation 2d Tue 11/8/22 Wed 11/9/22
886 PS3.15 Emissions Monitoring 64 w Thu 3/31/22 Fri 7/7/23
887 PS3.15.001 Engineering 9w Thu 3/31/22 Mon 6/6/22
888 PS3.15.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
889 PS3.15.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
890 PS3.15.001.0003 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
891 PS3.15.001.0004 Approval 3w Tue 5/17/22 Mon 6/6/22
892 PS3.15.002 Manufacturing 49 w Tue 6/7/22 Fri 5/26/23
893 PS3.15.002.0001 Procurement 3w Tue 6/7/22 Mon 6/27/22
894 PS3.15.002.0002 Manufacturing 44 w Tue 6/28/22 Fri 5/12/23
895 PS3.15.002.0003 Transfers / Import 2w Mon 5/15/23 Fri 5/26/23
896 PS3.15.003 Factory Testing 0.4 w Mon 5/29/23 Tue 5/30/23
897 PS3.15.003.0001 FAT 2d Mon 5/29/23 Tue 5/30/23
898 PS3.15.004 Transportation 1w Mon 6/5/23 Fri 6/9/23
899 PS3.15.004.0001 Shipment 5d Mon 6/5/23 Fri 6/9/23
900 PS3.15.005 Installation 0.4 w Thu 6/15/23 Fri 6/16/23
901 PS3.15.005.0001 Installation supervision 2d Thu 6/15/23 Fri 6/16/23
902 PS3.15.006 Site Services 1.2 w Mon 6/26/23 Mon 7/3/23
903 PS3.15.006.0001 SAT 2d Mon 6/26/23 Tue 6/27/23
904 PS3.15.006.0002 Commissioning 2d Wed 6/28/23 Thu 6/29/23
905 PS3.15.006.0003 Start-up 2d Fri 6/30/23 Mon 7/3/23
906 PS3.15.007 Training 2d Mon 6/19/23 Tue 6/20/23
907 PS3.15.008 Documentation 1w Mon 7/3/23 Fri 7/7/23
908 PS3.16 PAGA 44 w Thu 3/31/22 Mon 2/13/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 28
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
909 PS3.16.001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
910 PS3.16.001.0001 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
911 PS3.16.001.0002 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
912 PS3.16.001.0003 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
913 PS3.16.001.0004 Approval 3w Tue 5/31/22 Mon 6/20/22
914 PS3.16.002 Manufacturing 30 w Tue 6/21/22 Fri 1/20/23
915 PS3.16.002.0001 Procurement 3w Tue 6/21/22 Mon 7/11/22
916 PS3.16.002.0002 Manufacturing 25 w Tue 7/12/22 Fri 1/6/23
917 PS3.16.002.0003 Transfers / Import 2w Mon 1/9/23 Fri 1/20/23
918 PS3.16.003 Transportation 1w Mon 1/23/23 Fri 1/27/23
919 PS3.16.003.0001 Shipment 1w Mon 1/23/23 Fri 1/27/23
920 PS3.16.004 Installation 0.2 w Thu 2/2/23 Thu 2/2/23
921 PS3.16.004.0001 Installation supervision 1d Thu 2/2/23 Thu 2/2/23
922 PS3.16.005 Training 3d Fri 2/3/23 Wed 2/8/23
923 PS3.16.006 Documentation 1d Mon 2/13/23 Mon 2/13/23
924 PS4 Sirius Pipeline 55.3 w Thu 3/31/22 Tue 5/9/23
925 PS4.01 Intermediate Pumping Stations 55.3 w Thu 3/31/22 Tue 5/9/23
926 PS4.01.001 Process Control System 53.3 w Thu 3/31/22 Mon 4/24/23
927 PS4.01.001.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
928 PS4.01.001.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
929 PS4.01.001.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
930 PS4.01.001.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
931 PS4.01.001.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
932 PS4.01.001.0002 Manufacturing 29 w Tue 6/7/22 Fri 12/30/22
933 PS4.01.001.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
934 PS4.01.001.0002.2 Manufacturing 26 w Tue 6/7/22 Fri 12/9/22
935 PS4.01.001.0002.3 Transfers / Import 2w Mon 12/12/22 Fri 12/23/22
936 PS4.01.001.0002.4 Integration 1w Mon 12/26/22 Fri 12/30/22
937 PS4.01.001.0003 Factory Testing 1.4 w Wed 1/4/23 Thu 1/12/23
938 PS4.01.001.0003.1 FIT 3d Wed 1/4/23 Fri 1/6/23
939 PS4.01.001.0003.2 FAT 1w Fri 1/6/23 Thu 1/12/23
940 PS4.01.001.0004 Transportation 1w Wed 1/11/23 Tue 1/17/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 29
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
941 PS4.01.001.0004.1 Shipment 1w Wed 1/11/23 Tue 1/17/23
942 PS4.01.001.0005 Installation 0.2 w Mon 1/23/23 Mon 1/23/23
943 PS4.01.001.0005.1 Installation supervision 1d Mon 1/23/23 Mon 1/23/23
944 PS4.01.001.0006 Site Services 1w Tue 4/11/23 Tue 4/18/23
945 PS4.01.001.0006.1 SAT 1d Tue 4/11/23 Wed 4/12/23
946 PS4.01.001.0006.2 Commissioning 3d Wed 4/12/23 Mon 4/17/23
947 PS4.01.001.0006.3 Start-up 1d Mon 4/17/23 Tue 4/18/23
948 PS4.01.001.0007 Documentation 1w Mon 4/17/23 Mon 4/24/23
949 PS4.01.002 Safety Instrumented System 46.8 w Thu 3/31/22 Fri 3/3/23
950 PS4.01.002.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
951 PS4.01.002.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
952 PS4.01.002.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
953 PS4.01.002.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
954 PS4.01.002.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
955 PS4.01.002.0002 Manufacturing 32 w Tue 6/7/22 Fri 1/20/23
956 PS4.01.002.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
957 PS4.01.002.0002.2 Manufacturing 26 w Tue 6/28/22 Fri 12/30/22
958 PS4.01.002.0002.3 Transfers / Import 2w Mon 1/2/23 Fri 1/13/23
959 PS4.01.002.0002.4 Integration 1w Mon 1/16/23 Fri 1/20/23
960 PS4.01.002.0003 Factory Testing 1.4 w Wed 1/25/23 Thu 2/2/23
961 PS4.01.002.0003.1 FIT 3d Wed 1/25/23 Fri 1/27/23
962 PS4.01.002.0003.2 FAT 1w Fri 1/27/23 Thu 2/2/23
963 PS4.01.002.0004 Transportation 1w Wed 2/1/23 Wed 2/8/23
964 PS4.01.002.0004.1 Shipment 1w Wed 2/1/23 Wed 2/8/23
965 PS4.01.002.0005 Installation 0.2 w Tue 2/14/23 Tue 2/14/23
966 PS4.01.002.0005.1 Installation supervision 1d Tue 2/14/23 Tue 2/14/23
967 PS4.01.002.0006 Site Services 0.8 w Wed 2/22/23 Mon 2/27/23
968 PS4.01.002.0006.1 SAT 1d Wed 2/22/23 Wed 2/22/23
969 PS4.01.002.0006.2 Commissioning 2d Thu 2/23/23 Fri 2/24/23
970 PS4.01.002.0006.3 Start-up 1d Mon 2/27/23 Mon 2/27/23
971 PS4.01.002.0007 Documentation 1w Mon 2/27/23 Fri 3/3/23
972 PS4.01.003 Fire & Gas System 49.6 w Thu 3/31/22 Fri 3/24/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 30
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
973 PS4.01.003.0001 Engineering 9 w Thu 3/31/22 Mon 6/6/22
974 PS4.01.003.0001.1 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
975 PS4.01.003.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
976 PS4.01.003.0001.3 Engineering Development 4 w Mon 4/18/22 Mon 5/16/22
977 PS4.01.003.0001.4 Approval 3 w Tue 5/17/22 Mon 6/6/22
978 PS4.01.003.0002 Manufacturing 32 w Tue 6/7/22 Fri 1/20/23
979 PS4.01.003.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
980 PS4.01.003.0002.2 Manufacturing 26 w Tue 6/28/22 Fri 12/30/22
981 PS4.01.003.0002.5 Manufacturing and delivery 14 w Tue 6/28/22 Wed 10/5/22
F&G Instrumentation
982 PS4.01.003.0002.3 Transfers / Import 2w Mon 1/2/23 Fri 1/13/23
983 PS4.01.003.0002.4 Integration 1w Mon 1/16/23 Fri 1/20/23
984 PS4.01.003.0003 Factory Testing 1.4 w Wed 1/25/23 Thu 2/2/23
985 PS4.01.003.0003.1 FIT 3d Wed 1/25/23 Fri 1/27/23
986 PS4.01.003.0003.2 FAT 1w Fri 1/27/23 Thu 2/2/23
987 PS4.01.003.0004 Transportation 1w Wed 2/1/23 Wed 2/8/23
988 PS4.01.003.0004.1 Shipment 1w Wed 2/1/23 Wed 2/8/23
989 PS4.01.003.0005 Installation 0.2 w Tue 2/14/23 Tue 2/14/23
990 PS4.01.003.0005.1 Installation supervision 1d Tue 2/14/23 Tue 2/14/23
991 PS4.01.003.0006 Site Services 3.6 w Wed 2/22/23 Fri 3/17/23
992 PS4.01.003.0006.1 SAT 1d Wed 2/22/23 Wed 2/22/23
993 PS4.01.003.0006.2 Commissioning 3d Thu 2/23/23 Mon 2/27/23
994 PS4.01.003.0006.4 Commissioning F & G 16 d Thu 2/23/23 Thu 3/16/23
Instrumentation
995 PS4.01.003.0006.3 Start-up 1d Fri 3/17/23 Fri 3/17/23
996 PS4.01.003.0007 Documentation 1w Fri 3/17/23 Fri 3/24/23
997 PS4.01.004 Building Fire Systems 11 w Thu 3/31/22 Mon 6/20/22
998 PS4.01.004.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
999 PS4.01.004.0001.1 Inf Requirements 1 w Thu 3/31/22 Wed 4/6/22
1000 PS4.01.004.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1001 PS4.01.004.0001.3 Engineering Development 6 w Mon 4/18/22 Mon 5/30/22
1002 PS4.01.004.0001.4 Approval 3 w Tue 5/31/22 Mon 6/20/22
1003 PS4.01.005 Networking 33.6 w Thu 3/31/22 Wed 11/30/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 31
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1004 PS4.01.005.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1005 PS4.01.005.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1006 PS4.01.005.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1007 PS4.01.005.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1008 PS4.01.005.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1009 PS4.01.005.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1010 PS4.01.005.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1011 PS4.01.005.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1012 PS4.01.005.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1013 PS4.01.005.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1014 PS4.01.005.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1015 PS4.01.005.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1016 PS4.01.005.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1017 PS4.01.005.0005 Site Services 1.8 w Fri 11/11/22 Thu 11/24/22
1018 PS4.01.005.0005.1 Commissioning and testing 7.5 d Fri 11/11/22 Wed 11/23/22
1019 PS4.01.005.0005.2 Start-up 1.5 d Wed 11/23/22 Thu 11/24/22
1020 PS4.01.005.0007 Documentation 2d Tue 11/29/22 Wed 11/30/22
1021 PS4.01.006 Telecommunications 32 w Thu 3/31/22 Thu 11/17/22
1022 PS4.01.006.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1023 PS4.01.006.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1024 PS4.01.006.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1025 PS4.01.006.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1026 PS4.01.006.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1027 PS4.01.006.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1028 PS4.01.006.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1029 PS4.01.006.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1030 PS4.01.006.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1031 PS4.01.006.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1032 PS4.01.006.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1033 PS4.01.006.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1034 PS4.01.006.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1035 PS4.01.006.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 32
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1036 PS4.01.006.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1037 PS4.01.006.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1038 PS4.01.006.0006 Documentation 2d Thu 3/31/22 Fri 4/1/22
1039 PS4.01.007 Radio Backup System 32.8 w Thu 3/31/22 Thu 11/24/22
1040 PS4.01.007.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1041 PS4.01.007.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1042 PS4.01.007.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1043 PS4.01.007.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1044 PS4.01.007.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1045 PS4.01.007.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1046 PS4.01.007.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1047 PS4.01.007.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1048 PS4.01.007.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1049 PS4.01.007.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1050 PS4.01.007.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1051 PS4.01.007.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1052 PS4.01.007.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1053 PS4.01.007.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1054 PS4.01.007.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1055 PS4.01.007.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1056 PS4.01.007.0007 Documentation 2d Wed 11/23/22 Thu 11/24/22
1057 PS4.01.008 Process Instrumentation 35.6 w Thu 3/31/22 Wed 12/14/22
1058 PS4.01.008.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1059 PS4.01.008.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1060 PS4.01.008.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1061 PS4.01.008.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1062 PS4.01.008.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1063 PS4.01.008.0002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
1064 PS4.01.008.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1065 PS4.01.008.0002.2 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
1066 PS4.01.008.0002.3 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
1067 PS4.01.008.0003 Transportation 1w Fri 11/4/22 Thu 11/10/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 33
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1068 PS4.01.008.0003.1 Shipment 1w Fri 11/4/22 Thu 11/10/22
1069 PS4.01.008.0004 Installation 0.4 w Wed 11/16/22 Thu 11/17/22
1070 PS4.01.008.0004.1 Installation supervision 2d Wed 11/16/22 Thu 11/17/22
1071 PS4.01.008.0005 Site Services 1.8 w Mon 11/28/22 Thu 12/8/22
1072 PS4.01.008.0005.1 SAT 3d Mon 11/28/22 Wed 11/30/22
1073 PS4.01.008.0005.2 Commissioning 4.5 d Thu 12/1/22 Wed 12/7/22
1074 PS4.01.008.0005.3 Start-up 1.5 d Wed 12/7/22 Thu 12/8/22
1075 PS4.01.008.0006 Documentation 1d Wed 12/14/22 Wed 12/14/22
1076 PS4.01.009 Metering Skids 55.3 w Thu 3/31/22 Tue 5/9/23
1077 PS4.01.009.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1078 PS4.01.009.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1079 PS4.01.009.0001.2 Freeze Inf 1w Tue 4/5/22 Mon 4/11/22
1080 PS4.01.009.0001.3 Engineering Development 7.4 w Tue 4/12/22 Mon 6/6/22
1081 PS4.01.009.0001.4 Approval 3.2 w Mon 5/16/22 Mon 6/6/22
1082 PS4.01.009.0002 Manufacturing 37.7 w Mon 5/16/22 Thu 2/9/23
1083 PS4.01.009.0002.1 Procurement 34 w Mon 5/16/22 Thu 1/12/23
1084 PS4.01.009.0002.2 Manufacturing 18 w Tue 7/12/22 Thu 11/17/22
1085 PS4.01.009.0002.3 Transfers / Import 11 w Thu 11/3/22 Thu 1/19/23
1086 PS4.01.009.0002.4 Integration 11.5 w Fri 11/18/22 Thu 2/9/23
1087 PS4.01.009.0003 Factory Testing 2w Thu 2/2/23 Fri 2/17/23
1088 PS4.01.009.0003.1 FAT 2w Thu 2/2/23 Fri 2/17/23
1089 PS4.01.009.0004 Transportation 2w Mon 2/13/23 Mon 2/27/23
1090 PS4.01.009.0004.1 Shipment 10 d Mon 2/13/23 Mon 2/27/23
1091 PS4.01.009.0005 Installation 2w Thu 3/2/23 Thu 3/16/23
1092 PS4.01.009.0005.1 Installation supervision 2w Thu 3/2/23 Thu 3/16/23
1093 PS4.01.009.0006 Site Services 5w Fri 3/24/23 Wed 5/3/23
1094 PS4.01.009.0006.1 SAT 2w Fri 3/24/23 Tue 4/11/23
1095 PS4.01.009.0006.2 Commissioning 1w Tue 4/11/23 Tue 4/18/23
1096 PS4.01.009.0006.3 Start-up 2w Tue 4/18/23 Wed 5/3/23
1097 PS4.01.009.0007 Documentation 17 w Tue 1/3/23 Tue 5/9/23
1098 PS4.01.010 Pipeline Leak Detection 23.4 w Thu 3/31/22 Wed 9/14/22
1099 PS4.01.010.0001 Engineering 9.4 w Thu 3/31/22 Wed 6/8/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 34
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1100 PS4.01.010.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1101 PS4.01.010.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1102 PS4.01.010.0001.3 Engineering Development 7.4 w Mon 4/18/22 Wed 6/8/22
1103 PS4.01.010.0001.4 Approval 3.2 w Wed 5/18/22 Wed 6/8/22
1104 PS4.01.010.0002 Configuration 4w Thu 6/9/22 Wed 7/6/22
1105 PS4.01.010.0002.1 Configuration 4w Thu 6/9/22 Wed 7/6/22
1106 PS4.01.010.0003 Manufacturing 4w Thu 7/7/22 Wed 8/3/22
1107 PS4.01.010.0003.1 Procurement 1w Thu 7/7/22 Wed 7/13/22
1108 PS4.01.010.0003.2 Manufacturing 1w Thu 7/14/22 Wed 7/20/22
1109 PS4.01.010.0003.3 Transfers / Import 2w Thu 7/21/22 Wed 8/3/22
1110 PS4.01.010.0004 Factory Testing 1w Thu 8/4/22 Wed 8/10/22
1111 PS4.01.010.0004.1 FAT 1w Thu 8/4/22 Wed 8/10/22
1112 PS4.01.010.0005 Transportation 1w Tue 8/16/22 Mon 8/22/22
1113 PS4.01.010.0005.1 Shipment 1w Tue 8/16/22 Mon 8/22/22
1114 PS4.01.010.0006 Installation 0.4 w Fri 8/26/22 Mon 8/29/22
1115 PS4.01.010.0006.1 Installation supervision 2d Fri 8/26/22 Mon 8/29/22
1116 PS4.01.010.0007 Site Services 0.6 w Tue 9/6/22 Thu 9/8/22
1117 PS4.01.010.0007.1 SAT 1d Tue 9/6/22 Tue 9/6/22
1118 PS4.01.010.0007.2 Commissioning 1d Wed 9/7/22 Wed 9/7/22
1119 PS4.01.010.0007.3 Start-up 1d Thu 9/8/22 Thu 9/8/22
1120 PS4.01.010.0008 Documentation 1w Thu 9/8/22 Wed 9/14/22
1121 PS4.01.011 Security System 49.6 w Thu 3/31/22 Fri 3/24/23
1122 PS4.01.011.0001 Engineering 9.4 w Thu 3/31/22 Wed 6/8/22
1123 PS4.01.011.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1124 PS4.01.011.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1125 PS4.01.011.0001.3 Engineering Development 7.4 w Mon 4/18/22 Wed 6/8/22
1126 PS4.01.011.0001.4 Approval 3.2 w Wed 5/18/22 Wed 6/8/22
1127 PS4.01.011.0002 Manufacturing 34 w Thu 6/9/22 Wed 2/8/23
1128 PS4.01.011.0002.1 Procurement 3w Thu 6/9/22 Wed 6/29/22
1129 PS4.01.011.0002.2 Manufacturing 12 w Thu 6/30/22 Fri 9/23/22
1130 PS4.01.011.0002.3 Transfers / Import 2w Mon 9/26/22 Fri 10/7/22
1131 PS4.01.011.0002.4 Integration 17 w Mon 10/10/22 Wed 2/8/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 35
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1132 PS4.01.011.0003 Factory Testing 0.6 w Thu 2/9/23 Mon 2/13/23
1133 PS4.01.011.0003.1 FAT 0.6 w Thu 2/9/23 Mon 2/13/23
1134 PS4.01.011.0004 Transportation 1w Fri 2/17/23 Thu 2/23/23
1135 PS4.01.011.0004.1 Shipment 5d Fri 2/17/23 Thu 2/23/23
1136 PS4.01.011.0005 Installation 0.4 w Wed 3/1/23 Thu 3/2/23
1137 PS4.01.011.0005.1 Installation supervision 2d Wed 3/1/23 Thu 3/2/23
1138 PS4.01.011.0006 Site Services 1.2 w Fri 3/10/23 Fri 3/17/23
1139 PS4.01.011.0006.2 Commissioning and testing 5.5 d Fri 3/10/23 Fri 3/17/23
1140 PS4.01.011.0006.3 Start-up 0.5 d Fri 3/17/23 Fri 3/17/23
1141 PS4.01.011.0007 Documentation 1d Fri 3/24/23 Fri 3/24/23
1142 PS4.02 MLV Stations 55 w Thu 3/31/22 Fri 5/5/23
1143 PS4.02.001 Remote Terminal Units 55 w Thu 3/31/22 Fri 5/5/23
1144 PS4.02.001.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1145 PS4.02.001.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1146 PS4.02.001.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1147 PS4.02.001.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1148 PS4.02.001.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1149 PS4.02.001.0002 Manufacturing 33 w Tue 6/7/22 Fri 1/27/23
1150 PS4.02.001.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1151 PS4.02.001.0002.2 Manufacturing 20 w Tue 6/28/22 Thu 11/17/22
1152 PS4.02.001.0002.3 Transfers / Import 2w Fri 11/18/22 Fri 12/2/22
1153 PS4.02.001.0002.4 Integration 8w Mon 12/5/22 Fri 1/27/23
1154 PS4.02.001.0003 Factory Testing 1w Mon 1/30/23 Fri 2/3/23
1155 PS4.02.001.0003.1 FAT 1w Mon 1/30/23 Fri 2/3/23
1156 PS4.02.001.0004 Transportation 1w Thu 2/2/23 Thu 2/9/23
1157 PS4.02.001.0004.1 Shipment 1w Thu 2/2/23 Thu 2/9/23
1158 PS4.02.001.0005 Installation 1w Wed 2/15/23 Tue 2/21/23
1159 PS4.02.001.0005.1 Installation supervision 1w Wed 2/15/23 Tue 2/21/23
1160 PS4.02.001.0006 Site Services 8w Wed 3/1/23 Fri 4/28/23
1161 PS4.02.001.0006.1 SAT 5w Wed 3/1/23 Wed 4/5/23
1162 PS4.02.001.0006.2 Commissioning 2w Mon 4/10/23 Fri 4/21/23
1163 PS4.02.001.0006.3 Start-up 1w Mon 4/24/23 Fri 4/28/23

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 36
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1164 PS4.02.001.0007 Documentation 1d Fri 5/5/23 Fri 5/5/23
1165 PS4.02.002 Building Fire Systems 11 w Thu 3/31/22 Mon 6/20/22
1166 PS4.02.002.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1167 PS4.02.002.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1168 PS4.02.002.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1169 PS4.02.002.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1170 PS4.02.002.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1171 PS4.02.003 Networking 32.8 w Thu 3/31/22 Thu 11/24/22
1172 PS4.02.003.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1173 PS4.02.003.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1174 PS4.02.003.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1175 PS4.02.003.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1176 PS4.02.003.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1177 PS4.02.003.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1178 PS4.02.003.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1179 PS4.02.003.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1180 PS4.02.003.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1181 PS4.02.003.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1182 PS4.02.003.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1183 PS4.02.003.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1184 PS4.02.003.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1185 PS4.02.003.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1186 PS4.02.003.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1187 PS4.02.003.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1188 PS4.02.003.0006 Documentation 2d Wed 11/23/22 Thu 11/24/22
1189 PS4.02.004 Telecommunications 32.8 w Thu 3/31/22 Thu 11/24/22
1190 PS4.02.004.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1191 PS4.02.004.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1192 PS4.02.004.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1193 PS4.02.004.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1194 PS4.02.004.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1195 PS4.02.004.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 37
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1196 PS4.02.004.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1197 PS4.02.004.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1198 PS4.02.004.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1199 PS4.02.004.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1200 PS4.02.004.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1201 PS4.02.004.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1202 PS4.02.004.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1203 PS4.02.004.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1204 PS4.02.004.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1205 PS4.02.004.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1206 PS4.02.004.0006 Documentation 2d Wed 11/23/22 Thu 11/24/22
1207 PS4.02.005 Radio Backup System 32.8 w Thu 3/31/22 Thu 11/24/22
1208 PS4.02.005.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1209 PS4.02.005.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1210 PS4.02.005.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1211 PS4.02.005.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1212 PS4.02.005.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1213 PS4.02.005.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1214 PS4.02.005.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1215 PS4.02.005.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1216 PS4.02.005.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1217 PS4.02.005.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1218 PS4.02.005.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1219 PS4.02.005.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1220 PS4.02.005.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1221 PS4.02.005.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1222 PS4.02.005.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1223 PS4.02.005.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1224 PS4.02.005.0006 Documentation 2d Wed 11/23/22 Thu 11/24/22
1225 PS4.02.006 Process Instrumentation 38.8 w Thu 3/31/22 Thu 1/5/23
1226 PS4.02.006.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1227 PS4.02.006.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 38
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1228 PS4.02.006.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1229 PS4.02.006.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1230 PS4.02.006.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1231 PS4.02.006.0002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
1232 PS4.02.006.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1233 PS4.02.006.0002.2 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
1234 PS4.02.006.0002.3 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
1235 PS4.02.006.0003 Transportation 1w Fri 11/4/22 Thu 11/10/22
1236 PS4.02.006.0003.1 Shipment 1w Fri 11/4/22 Thu 11/10/22
1237 PS4.02.006.0004 Installation 0.4 w Wed 11/16/22 Thu 11/17/22
1238 PS4.02.006.0004.1 Installation supervision 2d Wed 11/16/22 Thu 11/17/22
1239 PS4.02.006.0005 Site Services 5w Mon 11/28/22 Fri 12/30/22
1240 PS4.02.006.0005.1 Commissioning and testing 20 d Mon 11/28/22 Fri 12/23/22
1241 PS4.02.006.0005.2 Start-up 5d Mon 12/26/22 Fri 12/30/22
1242 PS4.02.006.0006 Documentation 1d Thu 1/5/23 Thu 1/5/23
1243 PS4.02.007 Security System 32.6 w Thu 3/31/22 Wed 11/23/22
1244 PS4.02.007.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1245 PS4.02.007.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1246 PS4.02.007.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1247 PS4.02.007.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1248 PS4.02.007.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1249 PS4.02.007.0002 Manufacturing 17 w Tue 6/7/22 Wed 10/5/22
1250 PS4.02.007.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1251 PS4.02.007.0002.2 Manufacturing 12 w Tue 6/28/22 Wed 9/21/22
1252 PS4.02.007.0002.3 Transfers / Import 2w Thu 9/22/22 Wed 10/5/22
1253 PS4.02.007.0003 Factory Testing 1w Thu 10/6/22 Wed 10/12/22
1254 PS4.02.007.0003.1 FAT 5d Thu 10/6/22 Wed 10/12/22
1255 PS4.02.007.0004 Transportation 1w Tue 10/18/22 Mon 10/24/22
1256 PS4.02.007.0004.1 Shipment 5d Tue 10/18/22 Mon 10/24/22
1257 PS4.02.007.0005 Installation 0.4 w Fri 10/28/22 Mon 10/31/22
1258 PS4.02.007.0005.1 Installation supervision 2d Fri 10/28/22 Mon 10/31/22
1259 PS4.02.007.0006 Site Services 1.2 w Wed 11/9/22 Wed 11/16/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 39
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1260 PS4.02.007.0006.1 Commissioning and testing 4d Wed 11/9/22 Mon 11/14/22
1261 PS4.02.007.0006.2 Start-up 2d Tue 11/15/22 Wed 11/16/22
1262 PS4.02.007.0007 Documentation 2d Tue 11/22/22 Wed 11/23/22
1263 PS4.03 MLV Stations - Vulnerable 45 w Thu 3/31/22 Mon 2/20/23
1264 PS4.03.001 Remote Terminal Units 45 w Thu 3/31/22 Mon 2/20/23
1265 PS4.03.001.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1266 PS4.03.001.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1267 PS4.03.001.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1268 PS4.03.001.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1269 PS4.03.001.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1270 PS4.03.001.0002 Manufacturing 23 w Tue 6/7/22 Thu 11/17/22
1271 PS4.03.001.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1272 PS4.03.001.0002.2 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22
1273 PS4.03.001.0002.3 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
1274 PS4.03.001.0002.4 Integration 2w Fri 11/4/22 Thu 11/17/22
1275 PS4.03.001.0003 Factory Testing 1w Fri 11/18/22 Fri 11/25/22
1276 PS4.03.001.0003.1 FAT 1w Fri 11/18/22 Fri 11/25/22
1277 PS4.03.001.0004 Transportation 1w Thu 11/24/22 Wed 11/30/22
1278 PS4.03.001.0004.1 Shipment 1w Thu 11/24/22 Wed 11/30/22
1279 PS4.03.001.0005 Installation 1w Tue 12/6/22 Mon 12/12/22
1280 PS4.03.001.0005.1 Installation supervision 1w Tue 12/6/22 Mon 12/12/22
1281 PS4.03.001.0006 Site Services 8w Tue 12/20/22 Tue 2/14/23
1282 PS4.03.001.0006.1 SAT 5w Tue 12/20/22 Mon 1/23/23
1283 PS4.03.001.0006.2 Commissioning 2w Tue 1/24/23 Tue 2/7/23
1284 PS4.03.001.0006.3 Start-up 1w Wed 2/8/23 Tue 2/14/23
1285 PS4.03.001.0007 Documentation 1d Mon 2/20/23 Mon 2/20/23
1286 PS4.03.002 Building Fire Systems 11 w Thu 3/31/22 Mon 6/20/22
1287 PS4.03.002.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1288 PS4.03.002.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1289 PS4.03.002.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1290 PS4.03.002.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1291 PS4.03.002.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 40
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1292 PS4.03.003 Networking 32.8 w Thu 3/31/22 Thu 11/24/22
1293 PS4.03.003.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1294 PS4.03.003.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1295 PS4.03.003.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1296 PS4.03.003.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1297 PS4.03.003.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1298 PS4.03.003.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1299 PS4.03.003.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1300 PS4.03.003.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1301 PS4.03.003.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1302 PS4.03.003.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1303 PS4.03.003.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1304 PS4.03.003.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1305 PS4.03.003.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1306 PS4.03.003.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1307 PS4.03.003.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1308 PS4.03.003.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1309 PS4.03.003.0006 Documentation 2d Wed 11/23/22 Thu 11/24/22
1310 PS4.03.004 Telecommunications 32.8 w Thu 3/31/22 Thu 11/24/22
1311 PS4.03.004.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1312 PS4.03.004.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1313 PS4.03.004.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1314 PS4.03.004.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1315 PS4.03.004.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1316 PS4.03.004.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1317 PS4.03.004.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1318 PS4.03.004.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1319 PS4.03.004.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1320 PS4.03.004.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1321 PS4.03.004.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1322 PS4.03.004.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1323 PS4.03.004.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 41
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1324 PS4.03.004.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1325 PS4.03.004.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1326 PS4.03.004.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1327 PS4.03.004.0006 Documentation 2d Wed 11/23/22 Thu 11/24/22
1328 PS4.03.005 Radio Backup System 32.8 w Thu 3/31/22 Thu 11/24/22
1329 PS4.03.005.0001 Engineering 11 w Thu 3/31/22 Mon 6/20/22
1330 PS4.03.005.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1331 PS4.03.005.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1332 PS4.03.005.0001.3 Engineering Development 6w Mon 4/18/22 Mon 5/30/22
1333 PS4.03.005.0001.4 Approval 3w Tue 5/31/22 Mon 6/20/22
1334 PS4.03.005.0002 Manufacturing 17 w Tue 6/21/22 Wed 10/19/22
1335 PS4.03.005.0002.1 Procurement 3w Tue 6/21/22 Mon 7/11/22
1336 PS4.03.005.0002.2 Manufacturing 12 w Tue 7/12/22 Wed 10/5/22
1337 PS4.03.005.0002.3 Transfers / Import 2w Thu 10/6/22 Wed 10/19/22
1338 PS4.03.005.0003 Transportation 1w Thu 10/20/22 Wed 10/26/22
1339 PS4.03.005.0003.1 Shipment 1w Thu 10/20/22 Wed 10/26/22
1340 PS4.03.005.0004 Installation 0.4 w Wed 11/2/22 Thu 11/3/22
1341 PS4.03.005.0004.1 Installation supervision 2d Wed 11/2/22 Thu 11/3/22
1342 PS4.03.005.0005 Site Services 1w Fri 11/11/22 Thu 11/17/22
1343 PS4.03.005.0005.1 Commissioning and testing 4.5 d Fri 11/11/22 Thu 11/17/22
1344 PS4.03.005.0005.2 Start-up 0.5 d Thu 11/17/22 Thu 11/17/22
1345 PS4.03.005.0007 Training 1d Fri 11/18/22 Fri 11/18/22
1346 PS4.03.005.0006 Documentation 2d Wed 11/23/22 Thu 11/24/22
1347 PS4.03.006 Process Instrumentation 35 w Thu 3/31/22 Fri 12/9/22
1348 PS4.03.006.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1349 PS4.03.006.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1350 PS4.03.006.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1351 PS4.03.006.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1352 PS4.03.006.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1353 PS4.03.006.0002 Manufacturing 21 w Tue 6/7/22 Thu 11/3/22
1354 PS4.03.006.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1355 PS4.03.006.0002.2 Manufacturing 16 w Tue 6/28/22 Wed 10/19/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 42
Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline

ID WBS Task Name Duration Start FinishQtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1356 PS4.03.006.0002.3 Transfers / Import 2w Thu 10/20/22 Thu 11/3/22
1357 PS4.03.006.0003 Transportation 1w Fri 11/4/22 Thu 11/10/22
1358 PS4.03.006.0003.1 Shipment 1w Fri 11/4/22 Thu 11/10/22
1359 PS4.03.006.0004 Installation 0.6 w Wed 11/16/22 Fri 11/18/22
1360 PS4.03.006.0004.1 Installation supervision 3d Wed 11/16/22 Fri 11/18/22
1361 PS4.03.006.0005 Site Services 1w Tue 11/29/22 Mon 12/5/22
1362 PS4.03.006.0005.1 SAT 2d Tue 11/29/22 Wed 11/30/22
1363 PS4.03.006.0005.2 Commissioning 2d Thu 12/1/22 Fri 12/2/22
1364 PS4.03.006.0005.3 Start-up 1d Mon 12/5/22 Mon 12/5/22
1365 PS4.03.006.0006 Documentation 1d Fri 12/9/22 Fri 12/9/22
1366 PS4.03.007 Security System 30.2 w Thu 3/31/22 Fri 11/4/22
1367 PS4.03.007.0001 Engineering 9w Thu 3/31/22 Mon 6/6/22
1368 PS4.03.007.0001.1 Inf Requirements 1w Thu 3/31/22 Wed 4/6/22
1369 PS4.03.007.0001.2 Freeze Inf 1w Thu 4/7/22 Wed 4/13/22
1370 PS4.03.007.0001.3 Engineering Development 4w Mon 4/18/22 Mon 5/16/22
1371 PS4.03.007.0001.4 Approval 3w Tue 5/17/22 Mon 6/6/22
1372 PS4.03.007.0002 Manufacturing 17 w Tue 6/7/22 Wed 10/5/22
1373 PS4.03.007.0002.1 Procurement 3w Tue 6/7/22 Mon 6/27/22
1374 PS4.03.007.0002.2 Manufacturing 12 w Tue 6/28/22 Wed 9/21/22
1375 PS4.03.007.0002.3 Transfers / Import 2w Thu 9/22/22 Wed 10/5/22
1376 PS4.03.007.0003 Transportation 1w Thu 10/6/22 Wed 10/12/22
1377 PS4.03.007.0003.1 Shipment 1w Thu 10/6/22 Wed 10/12/22
1378 PS4.03.007.0004 Installation 0.2 w Thu 10/13/22 Thu 10/13/22
1379 PS4.03.007.0004.1 Installation supervision 1d Thu 10/13/22 Thu 10/13/22
1380 PS4.03.007.0005 Site Services 1.6 w Fri 10/21/22 Wed 11/2/22
1381 PS4.03.007.0005.1 Commissioning and testing 4.5 d Fri 10/21/22 Thu 10/27/22
1382 PS4.03.007.0005.2 Start-up 0.5 d Thu 10/27/22 Thu 10/27/22
1383 PS4.03.007.0005.3 Training 3d Fri 10/28/22 Wed 11/2/22
1384 PS4.03.007.0006 Documentation 2d Thu 11/3/22 Fri 11/4/22

Task Inactive Task Manual Summary Rollup External Milestone

Project: Sirius Project Schedule: Jetty, Tuxpan, Hidalgo and Pipeline . Split Inactive Milestone Manual Summary Deadline

Date: 12/17/2021 Milestone Inactive Summary Start-only Progress


This program considers only working days from Monday to Friday. Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Note: This schedule is preliminary for this bidding, the official schedule will be updated between Customer and Emerson once the contract has been awarded, and it will be present a program at the detailed level of the concept. Page 43