Partes de Repuesto Obligatorias CEM
Partes de Repuesto Obligatorias CEM
Continuous
251. chemical Emissions repair kit 1 kit per system
and Monitoring pump supplied
Protection in stack and
Environm air quality
ental
Continuous
252. chemical Emissions Solenoid valves. 4 pieces for each
and Monitoring system
Protection in stack and supplied
Environm air quality
ental
Note 1: The Contractor must deliver a calculation report that justifies the amount to be supplied prior to the
delivery of the Spare Parts, as long as said report is not received, it will be considered that the
Contractor has not delivered the Spare Parts to which it refers
Note 2: Controls and instruments for the above systems shall be supplied as
requested in section 7.2.11.1 Spare Parts, in the Instrumentation and Control area of these Terms of
Reference, except for the System for measuring continuous emissions in the stack and air quality.