Professional Documents
Culture Documents
00
DUBAI - UAE - BL
Activity ID Activity Description Orig. Start Finish Late Start Late Finish Total 2024 2025 2026
Dur Float Jan F Mar Apr M Jun Jul A S Oct N Dec Jan F Mar Apr May Jun Jul A S Oct Nov D Jan F Mar
562 -04-Mar-24
G+1 RESIDENTIAL VILLA (Villa 5E)_NAD AL SHEBA FIRST, DUBAI - UAE BL 16-Sep-25 04-Mar-24 16-Sep-25 0
Early Work Actual Work Commencement Date : 04-Mar-24 G+1 RESIDENTIAL VILLA (Villa 5E)_NAD AL SHEBA FIRST,
Critical Work Contractual Completion : 16-Sep-25 DUBAI - UAE - BL Page 1 of 3
Milestone Duration : 562 Days incl Mobilization 2 Wks
Baseline Program Rev.00
Summary
G+1 RESIDENTIAL VILLA (Villa 5E)_NAD AL SHEBA FIRST, BASELINE PROGRAM Rev.00
DUBAI - UAE - BL
Activity ID Activity Description Orig. Start Finish Late Start Late Finish Total 2024 2025 2026
Dur Float Jan F Mar Apr M Jun Jul A S Oct N Dec Jan F Mar Apr May Jun Jul A S Oct Nov D Jan F Mar
V5E_C_SUB.V_FC_1090 Backfilling Arround Footing 4 13-May-24 16-May-24 13-May-24 16-May-24 0 Backfilling Arround Footing
Tie Beams 19 17-May-24 07-Jun-24 17-May-24 07-Jun-24 0
V5E_C_SUB.V_PC_1010 Plain Insitu Concrete Under Tie Beams 2 17-May-24 18-May-24 17-May-24 18-May-24 0 Plain Insitu Concrete Under Tie Beams
V5E_C_SUB.V_FC_1040 Formworks for Tie Beams 6 20-May-24 25-May-24 20-May-24 25-May-24 0 Formworks for Tie Beams
V5E_C_SUB.V_FC_1050 Reinforcement steel bars for Tie Beams 6 23-May-24 29-May-24 23-May-24 29-May-24 0 Reinforcement steel bars for Tie Beams
V5E_C_SUB.V_FC_1060 Reinforcement Concrete Pouring for Tie Beams 1 30-May-24 30-May-24 30-May-24 30-May-24 0 Reinforcement Concrete Pouring for Tie Beams
V5E_C_SUB.V_FC_1070 Formworks Removal for Tie Beams 2 31-May-24 01-Jun-24 31-May-24 01-Jun-24 0 Formworks Removal for Tie Beams
V5E_C_SUB.V_FC_1100 Water Proofin g for Sub-Masonary & Tie Beam 3 31-May-24 03-Jun-24 31-May-24 03-Jun-24 0 Water Proofin g for Sub-Masonary & Tie Beam
V5E_C_SUB.V_FC_1110 Backfilling up to SOG Level 4 04-Jun-24 07-Jun-24 04-Jun-24 07-Jun-24 0 Backfilling up to SOG Level
Slab on Grade_Ground Floor Level 11 08-Jun-24 24-Jun-24 08-Jun-24 24-Jun-24 0
V5E_C_SUB.V_PC_1020 Plain Insitu Concrete Under Slab on Grade 2 08-Jun-24 10-Jun-24 08-Jun-24 10-Jun-24 0 Plain Insitu Concrete Under Slab on Grade
V5E_C_SUB.V_PC_1030 Water Proofin g 2 11-Jun-24 12-Jun-24 11-Jun-24 12-Jun-24 0 Water Proofin g
V5E_C_SUB.V_SG_1000 Formworks for Slab on Grade 1 13-Jun-24 13-Jun-24 13-Jun-24 13-Jun-24 0 Formworks for Slab on Grade
V5E_C_SUB.V_SG_1020 MEP Pipes & Mesh for Slab on Grade 5 14-Jun-24 22-Jun-24 14-Jun-24 22-Jun-24 0 MEP Pipes & Mesh for Slab on Grade
V5E_C_SUB.V_SG_1030 Reinforcement Concrete Pouring for Slab on Grade 1 24-Jun-24 24-Jun-24 24-Jun-24 24-Jun-24 0 Reinforcement Concrete Pouring for Slab on Grade
Super- Structure 72 25-Jun-24 16-Sep-24 25-Jun-24 16-Sep-24 0
First Floor Level 43 25-Jun-24 13-Aug-24 25-Jun-24 13-Aug-24 0
Column & Core Wall 15 25-Jun-24 11-Jul-24 25-Jun-24 11-Jul-24 0
V5E_C_SUP.V_CL_1000 Formworks for Column @ Ground Floor 10 25-Jun-24 05-Jul-24 25-Jun-24 05-Jul-24 0 Formworks for Column @ Ground Floor
V5E_C_SUP.V_CL_1010 Reinforcement steel bars for Column @ Ground Floor 8 28-Jun-24 06-Jul-24 28-Jun-24 06-Jul-24 0 Reinforcement steel bars for Column @ Ground Floor
V5E_C_SUP.V_CL_1020 Reinforcement Concrete Pouring for Column @ Ground Floor 1 08-Jul-24 08-Jul-24 08-Jul-24 08-Jul-24 0 Reinforcement Concrete Pouring for Column @ Ground Floor
V5E_C_SUP.V_CL_1030 Formworks Removal for Column @ Ground Floor 3 09-Jul-24 11-Jul-24 09-Jul-24 11-Jul-24 0 Formworks Removal for Column @ Ground Floor
Slab 28 12-Jul-24 13-Aug-24 12-Jul-24 13-Aug-24 0
V5E_C_SUP.V_SB_1040 Formworks for Slab @ First Floor 8 12-Jul-24 20-Jul-24 12-Jul-24 20-Jul-24 0 Formworks for Slab @ First Floor
V5E_C_SUP.V_SB_1050 Reinforcement steel bars for Slab including MEP Coduits @ Ground Floor
8 16-Jul-24 24-Jul-24 16-Jul-24 24-Jul-24 0 Reinforcement steel bars for Slab including MEP Coduits @ Ground Floor
V5E_C_SUP.V_SB_1060 Reinforcement Concrete Pouring for slab @ First Floor 1 25-Jul-24 25-Jul-24 25-Jul-24 25-Jul-24 0 Reinforcement Concrete Pouring for slab @ First Floor
V5E_C_SUP.V_SB_1070 Formworks Removal for slab @ First Floor 16 26-Jul-24 13-Aug-24 26-Jul-24 13-Aug-24 0 Formworks Removal for slab @ First Floor
Roof Level 29 14-Aug-24 16-Sep-24 14-Aug-24 16-Sep-24 0
Slab 29 14-Aug-24 16-Sep-24 14-Aug-24 16-Sep-24 0
V5E_C_SUP.V_SB_1120 Formworks for Slab @ Roof Floor 8 14-Aug-24 22-Aug-24 14-Aug-24 22-Aug-24 0 Formworks for Slab @ Roof Floor
V5E_C_SUP.V_SB_1130 Reinforcement steel bars for Slab including MEP Coduits @ 8 17-Aug-24 26-Aug-24 17-Aug-24 26-Aug-24 0 Reinforcement steel bars for Slab including MEP Coduits @ Roof Floor
Roof Floor
V5E_C_SUP.V_SB_1140 Reinforcement Concrete Pouring for slab @ Roof Floor 1 27-Aug-24 27-Aug-24 27-Aug-24 27-Aug-24 0 Reinforcement Concrete Pouring for slab @ Roof Floor
V5E_C_SUP.V_SB_1150 Formworks Removal for slab @ Roof Floor 16 29-Aug-24 16-Sep-24 29-Aug-24 16-Sep-24 0 Formworks Removal for slab @ Roof Floor
Waterproofing Works 42 22-Oct-24 11-Dec-24 22-Oct-24 11-Dec-24 0
Super Structure 42 22-Oct-24 11-Dec-24 22-Oct-24 11-Dec-24 0
V5E_C_WP.V_1050 Roof Water proofing 42 22-Oct-24 11-Dec-24 22-Oct-24 11-Dec-24 0 Roof Water proofing
Internal Finishes 110 21-Jan-25 31-May-25 21-Jan-25 31-May-25 0
Wet Area 30 21-Jan-25 24-Feb-25 21-Jan-25 24-Feb-25 0
Walls Finishes 14 21-Jan-25 05-Feb-25 21-Jan-25 05-Feb-25 0
Porcelain / Marble Tiles 14 21-Jan-25 05-Feb-25 21-Jan-25 05-Feb-25 0
Ground Floor 14 21-Jan-25 05-Feb-25 21-Jan-25 05-Feb-25 0
V5E_C_WLT.WP.V_1000 Porcelain / Marble Wall Tiles Installation @ Ground Floor - Wet 14 21-Jan-25 05-Feb-25 21-Jan-25 05-Feb-25 0 Porcelain / Marble Wall Tiles Installation @ Ground Floor - Wet Area
Area
Ceiling Finishes 10 06-Feb-25 17-Feb-25 06-Feb-25 17-Feb-25 0
Suspended ceiling 10 06-Feb-25 17-Feb-25 06-Feb-25 17-Feb-25 0
Ground Floor 10 06-Feb-25 17-Feb-25 06-Feb-25 17-Feb-25 0
V5E_C_SPD.WP.V_1000 Gypsum board ceiling Fixiation @ Ground Floor - Wet Area 10 06-Feb-25 17-Feb-25 06-Feb-25 17-Feb-25 0 Gypsum board ceiling Fixiation @ Ground Floor - Wet Area
Activity ID Activity Description Orig. Start Finish Late Start Late Finish Total 2024 2025 2026
Dur Float Jan F Mar Apr M Jun Jul A S Oct N Dec Jan F Mar Apr May Jun Jul A S Oct Nov D Jan F Mar
Ground Floor 6 18-Feb-25 24-Feb-25 18-Feb-25 24-Feb-25 0
V5E_C_FPR.WP.V_1000 Porcelain Floor Tiles Fixiation @ Ground Floor - Wet Area 6 18-Feb-25 24-Feb-25 18-Feb-25 24-Feb-25 0 Porcelain Floor Tiles Fixiation @ Ground Floor - Wet Area