Executive Summary:
The project was non-compliant with following appraisals of the criteria under GRIHA
Version 2019 that were checked at this stage.
• Criterion 1 - Green Infrastructure
• Criterion 4 - Air and Soil Pollution Control
•
Please note:
1. All the observations and actions to be taken were communicated to the project management team
during the site visit.
2. Compliance with Criteria 4, 5, 6, 23 (partly) and 26 (partly) will be evaluated based on the site visit,
compliance reports and documents submitted after the Due Diligence (DD) I and II site visits. There
will be no further submission for these criteria during the final evaluation stage.
3. The document-based compliance will be verified upon submission of relevant documents as per
GRIHA V.2019, at the time of preliminary and final evaluations.
4. Non-compliance with any mandatory criteria under GRIHA V.2019 shall render the project ineligible
for award of GRIHA Rating.
5. The compliance on site status has the following interpretation:
• Yes – On site observation was found to be compliant. However, periodic date-stamped photographs
must be recorded by the project team for the entire course of construction. In addition, supporting
documents will be verified after submission of relevant documents during the evaluation stage.
• No – On site observation was found to be non-compliant. Project team must submit date-stamped
contextual photographs for compliance. In addition, supporting documents will be verified after
submission of relevant documents during the evaluation stage.
• Partly – Appraisal requirement was partly being met. Project team must submit date-stamped
contextual photographs for compliance. In addition, supporting documents will be verified after
submission of relevant documents during the evaluation stage.
• To be verified – Appraisal requirements will be verified after submission of relevant documents. In
addition, supporting documents will be verified after submission of relevant documents during the
evaluation stage.
Due Diligence II Site Visit Report
Refer Images:
Action to be taken:
Project team must ensure all mature trees within
the site boundary are protected. After taking the
aforementioned measure, submit date stamped.
photographs of the same to demonstrate
compliance.
Image 3: A few existing trees were found to be unbarricaded and construction materials were
stored near them.
Image 4: Certain sections of the roof were treated with SRI paints.
Action to be taken:
Project team must ensure to provide wheel washing
facility on all vehicular entrances and exits of the
site. Submit date stamped photographs of the same
to demonstrate compliance.
DG sets have an exhaust Not applicable Project team stated that DG sets were not used on
with stack height of at site. The demand is being met though the campus
least 2-meter from the level facility.
top of the generator with
a cowl.
(Mandatory)
At least 3 additional Yes Following measures were observed to be adopted
measures adopted on during the site visit:
site to control air • Speed limit on site has been restricted to
pollution from the list 10km/hr. Signages for the same were
below: observed during the visit.
• DGs are in compliance • Fine aggregates on site were covered with
with CPCB norms tarpaulin sheets.
• Adoption of spill • Vehicles carrying construction materials are
prevention measures covered.
• Covering of fine As per due diligence I report, the following
aggregates on site observations were made:
• Sprinkling of water on • Spill prevention measures were
unpaved pathways on implemented on site.
the site with non- • Fine aggregates were covered and sprinkled
potable water with water on site.
• Limit vehicular speed
to 10 kmph on site Refer Image:
©GRIHA Council Page 6 of 47
Due Diligence II Site Visit Report
• Covering of vehicles
carrying waste
(Mandatory)
Appraisal 4.1.2 Ensure that the soil erosion channels are constructed, and they are connected to a
sedimentation tank in order to reduce movement of soil outside the site throughout the
construction phase of the project.
Soil erosion channels are Partly Due to the advanced stage of the project, this could
constructed on site, and not be observed during the site visit.
they are connected to a As per the due diligence I compliance report,
sedimentation tank. permanent trenches for storm water were used as
soil erosion channels which is further connected to
a centralised sedimentation / recharge pit for the
project.
Image 7: Temporary barricading made of Geo textile sheets was observed in the project.
Image 9: Permanent boundary wall was constructed along the site periphery.
Image 10: Speed limit signages were put around the site.
Refer Images: 7 to 9
On-site/off-site recycling To be verified Project Team stated that recyclable steel scrap was
of construction waste is being sold off the site. Trolleys carrying waste
developed and material from the site were observed during the
implemented visit. However, challans of construction wastes
were not available during the site visit.
Refer Image: 10
Appraisal 6.1.2: Adopt at least two strategies from the list, as given in GRIHA V.2019, to minimize
water consumption during construction, with the first strategy being mandatory.
Use gunny bags, ponding Yes Due to the advanced stage of the project, this could
technique or curing not be verified. However as per compliance report
compound. received against due diligence I site visit report,
(Mandatory, if gunny bags and ponding technique was used for
attempted) curing of columns and slabs respectively.
At least 1 other strategy To be verified Due to the advanced stage of the project, this could
has been adopted to not be verified. However, as per compliance report
minimize water received against due diligence I site visit report, use
consumption during of water reducing admixtures (CHRYSO
construction. Superplasticizer) was done in concrete.
Additionally, batch mix reports of M-25, M-30, M-45
grade concrete was shared in the compliance
report.
Image 10: Recyclable waste was observed to be taken away from the site.
Refer Image: 11
Refer Image: 12 to 14
Appraisal 9.1.2 Ensure that the refrigerant used in the HVAC systems and refrigeration
equipment is CFC and HCFC free.
The refrigerant used in Yes R-410a and R-1343a refrigerant were used in the in
the HVAC and the Split air conditioning system and air-cooled
refrigeration equipment chillers installed in the project.
are CFC and HCFC free.
Refer Image: 15 & 16
(Mandatory)
Appraisal 9.1.3 Ensure that the fire suppression systems and fire extinguishers installed in the
project are halon free.
The fire suppression To be verified This could not be observed during the site visit as
system and fire this work was yet to be initiated on site.
extinguishers installed
on site is halon free.
(Mandatory)
Appraisal 9.1.4 Ensure that all the insulation used in the building envelope and for HVAC systems.
refrigerant used in the HVAC systems and refrigeration equipment are HFC free.
All the insulation used in To be verified This will be verified during the final documentation.
the building envelope
and for HVAC systems,
the refrigerant used in
the HVAC and
refrigeration equipment
are HFC free.
Image 155: R410A refrigerant was used in the Split Air condition units installed in the project.
Image 16: R 134a refrigerant was used in the chillers installed in the project.
Refer Images:
Appraisal 12.1.4 Ensure that all interior wall and ceiling finishes (including, but not limited to,
primers and paints) have low volatile organic compound (VOC) content as per Table 12.3c and are
lead-free.
Use of low VOC and lead- To be verified Project team stated that low VOC and lead-free
free paints paints are used in the project. However, technical
specification sheets and purchase order of paints
were not available during the site visit.
Appraisal 12.1.5 Ensure that all adhesives and sealants used have low VOC content as per Tables
12.4c and 12.5c and that interior composite wood products do not have urea–formaldehyde as a
bonding resin.
Use of low VOC To be verified Project team stated that low VOC adhesives and
adhesives and sealants sealants have been used in the project. Sealant
(make: MCCOY) was seen during the site visit.
However, technical specification sheets and
purchase order of adhesives and sealants were not
available during the site visit.
Refer Image: 21
Use of interior composite To be verified Project team stated that composite wood products
wood products with no used in the project did not use urea–formaldehyde
urea–formaldehyde as a as a bonding resin.
bonding resin.
Refer Image: 22
Image 21: Sealant for windows was observed during the site visit.
Image 22: Composite wood products used in interiors were observed during the site visit.
Image23: Thermal insulated blocks were observed during the site visit.
Roof Covering To be verified Information regarding this was not available during
the site visit.
External Walling To be verified AAC blocks and Thermal insulated blocks were used
in the construction of external walls.
External Wall Finish To be verified Texture paints were used in external wall finishes
of the project.
External Window To be verified SGU and DGU were installed in the project.
Appraisal 20.1.2 Demonstrate reduction in the GWP value of the building interiors and finishes as
per the LCA benchmarks mentioned in Table 20.2c
Interior Materials
Internal Wall and To be verified Project team stated that AAC blocks, Drywalls and
Partitions High-Pressure Laminates, were used in all the
internal walls and partitions of the project.
Refer Images: 24
Wall Finish To be verified The following types of internal wall finishes were
observed in the project:
• MDF paneling,
• Paints,
• Acoustic paneling,
• Engineered marble,
• Ceramic tiles
Refer Images: 25 to 27
Floor Finish To be verified The following types of floor finishes were observed
in the project:
• Vitrified tiles
• Granite
• Italian marble
• Ceramic tiles
• Kota stone
Refer Images: 28 to 32
Ceiling Finish To be verified The following types of ceiling finishes were
observed on site:
• Gypsum False ceiling with paint
• Acoustic panels
• Perforated metal false ceiling
• Open cell aluminum false ceiling
Refer Images: 33 to 35
Internal door and frame To be verified The following types of internal doors and frames
were observed:
• Flush Doors with wooden frames
• Glass doors with aluminium frames
• Metallic fire doors
Image 27: Ceramic tile paneling was done in toilets of the project.
Image 29: Italian Marble was used in entrance and common area of the project.
Image 30: Kota stone was used in service staff resting areas.
Image 33: Perforated metal false ceiling was installed in the project.
Image 34: Perforated metal false ceiling was installed in the project.
Image 35: Open cell aluminium false ceiling was done in the project.
Image 36: Flush doors with Wooden frames were installed in the project.
Image 37: Glass doors with aluminium frames were installed in the project.
Refer Images:
Provision of clean Yes The following observations were made during the
drinking water, hygienic site visit:
working and living • Drinking water facilities were provided in
conditions, and the site area and labour accommodation
area.
sanitation facilities for
• Clean and hygienic toilets for construction
the workers. workers were provided in the site and
(Mandatory) labour accommodation area.
• A clean and hygienic bathing area was
provided at the labour accommodation area.
• Clean and hygienic labour accommodation
was provided for the construction workers.
The hutments had provision for daylight and
ventilation. Waste bins were provided for
the collection of food waste. General
cleanliness was maintained in the area
surrounding the labour accommodation.
Refer Images:
Drinking water test Yes The drinking water test report was not observed
report was available during the site visit. However, drinking water report
during the site visit. was submitted along the compliance report
(Mandatory) received against due diligence I site visit report
conforming to IS 10500 standards.
Provision of crèche Yes Creche facility was provided near the labour
facility for children of accommodation.
construction workers in
case their families are
allowed to work/live at
the construction site.
(Mandatory)
Appraisal 23.1.2: Adopt one alternative out of the following for the construction workers on-site.
Provision of grocery To be verified Project team stated that they had conducted two
store/canteen within awareness programmes with construction workers.
site/labour However, documents w.r.t. same were submitted
during the site visit.
accommodation OR
organization of at least
2 events during the
entire construction
phase to create
environmental
awareness among
construction workers.
C-26 Positive Social Impact
PARTLY MANDATORY
Appraisal 26.1.4 Ensure that tobacco smoking is prohibited on-site during the entire construction
phase.
Measures have been Yes ‘No smoking’ signage were displayed at multiple
taken to ensure no locations on site.
smoking on site during
Refer Image:
construction.
(Mandatory)
Image 38: Workers were seen wearing safety shoes and safety helmets during the site visit.
Image 40: Drinking water facility was provided on site for the workers.
Image 41: Clean and hygienic toilets were provided on site for the workers.
Image 6: Clean bathing area was provided for workers in the hutment area.
Image 43: Clean and hygienic labour accommodation was provided near the site.
Image 44: Clean and hygienic labour accommodation was provided near the site.
ANNEXURE 1
Controls • Time clock has been Project team stated that thermostat was
installed as per ECBC 2017- proposed to be installed for temperature
5.2.3.1 control. Additionally, the entire building
• Temperature controls have will be controlled through a BMS system.
been installed as per ECBC
2017- 5.2.3.2
• Occupancy controls have
been installed as per ECBC
2017- 5.2.3.3
• Two-speed motors/pony
motors/variable speed
drives have been installed
as per ECBC 2017- 5.2.3.4
Piping Piping insulation is compliant EPS was used for piping insulation.
Insulation with ECBC 2017- 5.2.6.1
Refer Image: 12
Ductwork and Ductwork insulation is Nitrile rubber was used as ducting
plenum compliant with ECBC 2017- insulation in the project.
Insulation 5.2.6.2
Refer Image: 13
System System Balancing is compliant The work was yet to be initiated. It will be
Balancing with ECBC 2017- 5.2.7 verified in the next visit.
• Solar Water heating is Solar water heaters are not proposed to be
complaint with ECBC 2017- installed in the project.
5.2.9.1.
Service water
• Heating Equipment
heating
Efficiency is complaint with
ECBC 2017- 5.2.9.2.
• Piping Insulation is
complaint with ECBC 2017-
5.2.9.4.
Section 2: Lighting and controls
Lighting • Automatic lighting shutoff is • Project team stated that occupancy
controls complaint with ECBC 2017- sensors were proposed in the
6.2.1.1. project.
• Space control is complaint • Manual switches were used for
Refer Image: 48
• Exterior Lighting Control is The work was yet to be initiated. Project
complaint with ECBC 2017- team stated that automatic timer control
6.2.1.5. will be provided for controlling all the
external lighting fixtures.
• Exit signs is complaint with The work was yet to be initiated. It will be
ECBC 2017- 6.2.2. verified in the next visit.
Section 3: Electrical and Renewable Energy Systems
Transformers Transformers installed on site Existing transformers of 2.5 MVA capacity
meet ECBC 2017- 7.2.1.1 at were installed in the campus which will be
50% and 100% load rating used for the project.