Professional Documents
Culture Documents
Presented By:
1
LECTURE OUTLINE
1. Construction Equipment
2. Construction Methods and Products
3. Construction Safety
4. Case Studies
1. Construction Equipment
Every project must be analyzed to determine the construction sequence (approach), identify
equipment needs
Construction Access
Equipment examples
2
3
LECTURE OUTLINE
1. Construction Equipment
LECTURE OUTLINE
1. Construction Equipment
2. Construction Methods and Products
3. Construction Safety
4. Case Studies
4
Occupational Safety and Health Administration (OSHA)
http://www.osha.gov/
Questions
and
Answers
5
Slab Cabin Run Stormwater
Bio-retention Project
A Growing
Greener
Stormwater
Management
Demonstration
Project
10/9/2007 11
• Supporters
– The Clearwater Conservancy
– The Millbrook Marsh Advisory Committee
– Spring Creek Watershed Community
– Centre County Planning Commission
– Spring Creek Trout Unlimited
– Penn State Department of Meteorology
10/9/2007 12
6
Project Need
1
Slab Cabin Run
3 Thompson Run
7
Technologies Applied
• In-stream Structures Based on Natural Channel Design
Criteria
– Rock and log cross vanes to control the elevation of the
streambed
– Set to allow stream to overflow to marsh floodplain during
bankfull event
– Designed for low impact installation
10/9/2007 15
PHASE 2 PHASE 1
(7 Acres) (6.5 Acres)
8
Results
Completed Structures
9
Bankfull Conditions
10
Construction
• Maintain operation of existing paved trails
• Phasing of project – 4 separate locations
• Material access to sites
• Trout stream – restrictive dates for work
• Raise stream by average of 1’ – surveying had to be
accurate
• Connecting bankfull flood to wetlands/floodplains on the
other side of the paved trail
• Weather – not a problem for this project
Construction
• Project Phases
• 4 locations
• Material and equipment
staging and sequencing
11
Construction
Construction
• Frustration
• Time delays
• Sensitive pedestrian environment
12
Construction
Construction
• Log Cross Vane Installation
13
Construction
Phase 1
Construction
Phase 2
14
Construction
Phase 2
Construction
Phase 2
• Phase 2
• Rock Cross Vane
Installation
15
Construction
Phase 3A
• Culvert Installation
• Maintain pedestrian
access to trail
• Staging supplies
• Surveying accuracy
Construction
Phase 3A
• Culvert
Installation
• Final stabilization
16
Construction
Phase 3A
• Final stabilization
Construction
• Final stabilization at
Phase 2
• Final stabilization at
Phase 1
17
Construction
Phase 3B
Questions
18
Construction
• Hazardous Waste
• Buried building foundations
• Abandoned pipes
• Petroleum contaminated soils from pipes
• Constricted Right-of-Way
• Construction Sequencing (bridge project)
• Invasive Plants, Coal fines prohibited plant success
• Weather
• Proper material size
Construction
• Existing conditions
19
Construction
• Existing conditions
• Sediment loading
• Flashy urban stream
Construction
• Size of boulders
20
Construction
• Surveying
• Sequence of
construction
• Surprises
Construction
• Cross Vane Installation
21
Construction
• Taking shape
• Surveying during
construction is very
important
Construction
22
Construction
Construction
23
Construction
Construction
24